1. how many paths are there? 2. the critical path is the a) longest path. b) shortest path. c) path with the most activities. d) path with the fewest activities.

Answers

Answer 1

Answer to the question is (a) longest path. The critical path is determined by identifying all the possible paths and calculating their durations, and the one with the longest duration is identified as the critical path.

Explain how many paths are there?

The number of paths can vary depending on the specific situation or system being analyzed.

The critical path is the longest path in terms of duration or time required to complete all its activities. It is the sequence of tasks or activities that must be completed in order to complete the project within the minimum possible time.

The critical path determines the total duration of the project, and any delay in the critical path activities will cause a delay in the project's completion time.

Therefore, the answer to the question is (a) longest path. The critical path is determined by identifying all the possible paths and calculating their durations, and the one with the longest duration is identified as the critical path.

The critical path method (CPM) is a popular technique used in project management to identify and manage the critical path.

Learn more about critical path.

brainly.com/question/16519233

#SPJ11


Related Questions

use the 60 mutual funds in the table above to conduct the hypothesis test. what is the p value? p value is (to 4 decimals)

Answers

Welch's two-sample t-test indicates that the average of Load Return's population is significantly greater than the average of No Load Return's population, with a large effect size.

The null hypothesis (H0) that the two population means are equal is rejected as the p-value (0.005) is less than the chosen significance level (α=0.05). This indicates that the chance of a Type 1 error is small, and the alternative hypothesis (H1) that the average of Load Return's population is greater than the average of No Load Return's population is supported.

The test statistic (T=-2.646) falls outside the 95% critical value accepted range, which further supports the rejection of H0. The effect size (0.68) is considered large, indicating that the difference between the two population means is substantial.

Learn more about p-value

https://brainly.com/question/13786078

#SPJ4


Complete Question:

use the 60 mutual funds in the table below to conduct the hypothesis test. what is the p value? p value is (to 4 decimals)

The length of one leg of a right triangle is 2 times the length of the other, and the
length of the hypotenuse is 12. What is the length of the longest leg?

Answers

Answer:

[tex]\frac{24\sqrt{5} }{5}[/tex]

Step-by-step explanation:

Let's start by assigning one of the unknown legs with the variable x.

We know that the other leg is 2 times the length of x, so we can write:

2x

We also know that the length of the hypotenuse is 12.

From here, we can use the Pythagorean Theorem.

Recall that the Pythagorean Theorem is:

[tex]a^2+b^2=c^2[/tex]

where a is the length of one leg, b is the length of the other leg, and c is the length of the hypotenuse.

Let's substitute the values. We have:

[tex]x^2+(2x^2)=12^2=\\x^2+4x^2=144=\\5x^2=144=\\x^2=\frac{144}{5}=\\x=\frac{12}{\sqrt{5} }[/tex]

Let's rationalize the denominator by multiplying the numerator and denominator by [tex]\sqrt{5}[/tex], like so:

[tex]\frac{12}{\sqrt{5} } =\\\frac{12\sqrt{5} }{5}[/tex]

Therefore, [tex]x=\frac{12\sqrt{5} }{5}[/tex]

Let's solve for 2x:

[tex]2x=\\2(\frac{12\sqrt{5} }{5})=\\ \frac{24\sqrt{5} }{5}[/tex]

So, the length of the longest leg is [tex]\frac{24\sqrt{5} }{5}[/tex]

The box plot represents the scores on quizzes in a history class.

A box plot uses a number line from 69 to 87 with tick marks every one-half unit. The box extends from 75 to 82 on the number line. A line in the box is at 79. The lines outside the box end at 70 and 84. The graph is titled History Quizzes, and the line is labeled Scores on Quizzes.

What value does 75% of the data lie below? Find the value.

Answers

75% of the data lies below 81.5.

What value does 75% of the data lie below? Find the value.

In a box plot, the box represents the middle 50% of the data, with the lower edge of the box (the "whisker") representing the 25th percentile and the upper edge of the box (the other "whisker") representing the 75th percentile.

Since the lower edge of the box is at 75, we know that at least 25% of the data lies below 75. Similarly, since the upper edge of the box is at 82, we know that at least 25% of the data lies above 82. Therefore, the middle 50% of the data lies between 75 and 82.

To find the value that 75% of the data lies below, we need to find the 75th percentile. Since the line in the box is at 79, we know that 50% of the data lies below 79. Therefore, we need to find the value that is greater than 79 and such that 75% of the data lies below it.

We can use the length of the box (82 - 75 = 7) to find the size of each quartile. Since the middle 50% of the data lies in the box, each quartile contains 25/2 = 12.5% of the data.

To find the value that 75% of the data lies below, we need to add 12.5% to 50% (which is the location of the line in the box). Therefore, we need to find the value that is greater than 79 and such that 62.5% of the data lies below it.

Since the length of the number line is 87 - 69 = 18, each tick mark represents 0.5 units. Therefore, to find the tick mark that corresponds to the 62.5th percentile, we can add 0.5 units for every 12.5% increase. Starting from 79, we need to add 0.5 x 5 = 2.5 units to reach the tick mark that corresponds to the 62.5th percentile. Therefore, the value that 75% of the data lies below is:

79 + 2.5 = 81.5

So, 75% of the data lies below 81.5.

to know more about value

brainly.com/question/30145972

#SPJ1

Answer:

The lower quatile (Q1), and it is 79

Step-by-step explanation:

If you were to pick 84 that would be 100%

Twins Isaac and Isaiah were just born. Isaac weighs
6
66 pounds
2
22 ounces and Isaiah weighs
5
55 pounds
4
44 ounces.
How many ounces do Isaac and Isaiah weigh together?
ounces

Answers

Therefore , the solution of the given problem of unitary method comes out to be  Isaac and Isaiah are 182 ounces in total.

Definition of a unitary method.

Use the tried-and-true fundamental method, the actual variables, and any relevant information gleaned from general and specific questions to complete expression the assignment. Customers may be given another chance to taste the products in response. If these adjustments don't happen, we'll lose out on significant advancements in our understanding of programmes.

Here,

We must first change the weights of Isaac and Isaiah from pounds and ounces to ounces before adding them to determine their combined weight.

Weight of Isaac: six pounds 2 ounces = 6 * 16 + 2

= 96 + 2

= 98 ounces

Isaiah is 5 pounds in weight.

= 5 * 16 + 4

= 80 + 4

= 84 ounces

Together, Isaac and Isaiah weighed

98 ounces + 84 ounces = 182 ounces

As a result, Isaac and Isaiah are 182 ounces in total.

To know more about unitary method visit:

https://brainly.com/question/28276953

#SPJ1  

a report claims that the proportion of all adults who are vegetarians is 0.12. believing this claimed value is incorrect, a researcher surveys a large random sample of 1,000 adults and finds that 140 of the adults in the sample are vegetarians. what will the test statistic be equal to in this example? as you are engaging in calculations, try not to do a lot of rounding until you get to the very end, and choose the answer below that is closest to what you calculate. a. 2.5 b. 1.4 c. 1.9 d. 0.3 d. less than 0.1

Answers

The correct answer is (c) 1.9

How to calculate the test statistic?

To calculate the test statistic in this example, we can use the formula for a z-test for proportions:

[tex]z = (p - P) / \sqrt{[P(1-P) / n][/tex]

where:

p is the sample proportion of vegetarians (140/1000 = 0.14)

P is the hypothesized population proportion of vegetarians (0.12)

n is the sample size (1000)

Substituting these values into the formula, we get:

[tex]z = (0.14 - 0.12) / \sqrt{[0.12(1-0.12) / 1000][/tex]

z = 0.02 / 0.0110

z = 1.818 (rounded to three decimal places)

Therefore, the test statistic in this example will be approximately equal to 1.818. The answer closest to this value is (c) 1.9

Learn more about test statistic

brainly.com/question/14128303

#SPJ11

WILL MATK AS BRAINLEIST!!
Question in picture!

Answers

The area of the region is 6 square unit.

Here is how to arrive at the area of the region

The base of the triangle is the distance between the x-coordinates where the curves y = √x and y = −x + 6 intersect, which is 2. The height of the triangle is the distance between the y-coordinate where y = 0 intersects the y-axis and the y-coordinate where the line y = −x + 6 intersects the y-axis. This distance is 6.

Therefore, the area of the region bounded by the curves y = √x, y = −x + 6, and y = 0 is:

Area = 1/2 * base * height

    = 1/2 * 2 * 6

    = 6

Learn more about area of region here:

https://brainly.com/question/31377501

#SPJ1

if we run a regression with a sample of 30 observations using a dependent variable, 3 independent variables, and a constant how many degrees of freedom does the model have?

Answers

The model have 4 degrees of freedom if a regression model has a sample of 30 observations using a dependent variable, 3 independent variables, and a constant.

In a linear regression model, the degrees of freedom for the model are calculated as the number of independent variables plus one (for the constant or intercept term). Therefore, in this case, since the model has 3 independent variables and a constant, the degrees of freedom for the model would be 3 + 1 = 4.

The degrees of freedom for the model represent the number of parameters estimated from the data to build the model. These parameters are the coefficients or weights of the independent variables and the constant term.

The degrees of freedom for the model are used to calculate the F-statistic, which is a measure of the overall significance of the regression model. The F-statistic is calculated as the ratio of the explained variance to the unexplained variance of the model, and it is compared to the F-distribution with degrees of freedom (k, n-k-1), where k is the number of independent variables and n is the sample size.

To know more about regression model here

https://brainly.com/question/16972231

#SPJ4

You spin the spinner once. What is P (5 or divisor of 16)

Answers

The probability of getting a 5 or a divisor of 16 when spinning the spinner is 1/2 or 50%.

To find the probability of getting a 5 or a divisor of 16, we need to first understand what the spinner looks like. Assuming that the spinner has equally sized sections labeled 1 through 8, we can see that a divisor of 16 would be either 1, 2, or 4.

So, out of the eight possible outcomes, there are three that are divisors of 16 (1, 2, and 4) and one that is a 5. Therefore, there are four possible outcomes that satisfy the condition of getting a 5 or a divisor of 16.

To calculate the probability of getting a 5 or a divisor of 16, we divide the number of favorable outcomes (4) by the total number of possible outcomes (8). This gives us:

P(5 or divisor of 16) = favorable outcomes / total outcomes

= 4/8

= 1/2 or 50%

To know more about probability here

https://brainly.com/question/11234923

#SPJ4

Which of the following quotes could be used as strong support for the claim, "Tom is characterized as a dominant and aggressive individual"?

1: Making a short deft movement, Tom Buchanan broke her nose with his open hand.

2: I went up to New York with Tom on the train one afternoon, and when we stopped by the ashheaps he jumped to his feet and, taking hold of my elbow, literally forced me from the car. "We're getting off," he insisted. "I want you to meet my girl."

3: Two shining arrogant eyes had established dominance over his face and gave him the appearance of always leaning aggressively forward.

4: All quotes mentioned here could be used to support the claim that Tom is characterized as a dominant and aggressive individual.

Answers

While all the quotes suggest Tom's aggressive behavior, the third quote provides the most direct evidence of his dominant and aggressive personality traits.

What is quadratic equation?

it's a second-degree quadratic equation which is an algebraic equation in x.

The first quote mentioned describes an act of physical aggression committed by Tom, but it only provides evidence of his aggression towards a specific individual and does not necessarily suggest that he is generally a dominant or aggressive person.

The second quote shows Tom forcing the narrator to do something against their will, which could be interpreted as a sign of dominance, but it does not necessarily imply aggression.

On the other hand, the third quote specifically describes Tom's appearance as having "shining arrogant eyes" that establish dominance and make him appear aggressively forward. This provides strong evidence that Tom is characterized as a dominant and aggressive individual not just in his actions but also in his demeanor and appearance.

Therefore, while all the quotes suggest Tom's aggressive behavior, the third quote provides the most direct evidence of his dominant and aggressive personality traits.

To learn more about quadratic equation from the given link:

brainly.com/question/30098550

#SPJ1

What is the answer and how do I get there?

Answers

The value of the missing side length is 2√6. Option C

How to determine the value

We have that the six trigonometric identities are;

sinecosinetangentcotangentsecantcosecant

From the information given, we have that;

Using the tangent identity,

tan 60 = 6√6/y

find the value

y = 6√6 /√3

Using the sine identity

sin 45 =  6√6 /√3/x

sin45 =6√18/3 × 1/x

√2/2x = 6√18/3

x = 2√18/√2

x = 2√36

x = 2√6

Learn more about trigonometric identities at: https://brainly.com/question/7331447

#SPJ1

in par 12.2 cm 9.3 cm 9.3 cm 7.9 cm 26.5 cm 9.3 cm 17.2 cm 9.3 cm. ? 21.5 cm​

Answers

Stop using brainly. This whole website has became a big money grab over the last few months and they will remove all your posts and answers unless you pay them money. I've had it happen several times now.

a student willing to participate in a debate competition is required to fill out a registration form. answers to the follow questions on the form are what type of data?

Answers

A student willing to participate in a debate competition is required to fill out a registration form.

Form filling in two types of data i.e.,

Quantitative dataCategorical data

Quantitative data :

Quantitative data is data that can be counted or measured in numerical values. The two main types of quantitative data are discrete data and continuous data. Height in feet, age in years, and weight in pounds are examples of quantitative data. Qualitative data is descriptive data that is not expressed numerically.

Categorical data:

Categorical data is a collection of information that is divided into groups. i.e., if an organization or agency is trying to get a biodata of its employees, the resulting data is referred to as categorical.

a. What is your date of birth?

Quantitative.

b. Have you participated in any debate competition previously?

Categorical.

c. If yes, how many debate competitions have you participated so far?

Quantitative.

d. Have you won any of the competitions?

Categorical.

e. If yes, how many have you won?

Quantitative.

Learn more about Quantitative data at:

https://brainly.com/question/14810759

#SPJ4

The given question is incomplete, complete question is:

A student willing to participate in a debate competition required to fill a registration form. State

whether each of the following information about the participant provides categorical or quantitative

data.

a. What is your date of birth?

b. Have you participated in any debate competition previously?

c. If yes, how many debate competitions have you participated so far?

d. Have you won any of the competitions?

e. If yes, how many have you won?

Please write answer in two parts. A. Main answer (correctly paraphrased, addressing all aspect of the question) B. Explanation (Step-by-step explanation)

Find the LCM of 12x & 36x
i need answer asap ​

Answers

To find the LCM (Least Common Multiple) of 12x and 36x, we can first factor each expression:

12x = 2^2 * 3 * x
36x = 2^2 * 3^2 * x

The LCM is the product of the highest powers of all prime factors involved. In this case, the prime factors are 2, 3, and x.

The highest power of 2 is 2^2, which appears in both factorizations.
The highest power of 3 is 3^2, which only appears in the factorization of 36x.
The highest power of x is x, which appears in both factorizations.

Therefore, the LCM of 12x and 36x is:

LCM(12x, 36x) = 2^2 * 3^2 * x = 36x

So the LCM of 12x and 36x is 36x.

A classmate of yours stated that a solid line is not a good representation of an arithmetic sequences. What logical assumption is your classmate using?
The classmate is not correct. A line is a good representation of an arithmetic sequence.
A line is a series of dots that represent each value of the sequence.
A line has the same slope as the common difference in the sequence.
An arithmetic sequence is a set of discrete values, whereas a line is a continuous set of values.

Answers

The logical assumption used is: An arithmetic sequence is a set of discrete values, whereas a line is a continuous set of values.

What is arithmetic sequence?

An arithmetic sequence is a set of numbers where, with the exception of the first term, each term is obtained by adding a fixed constant to the term before it. Every pair of following terms in the sequence has the same fixed constant, which is known as the common difference. A1 stands for the first term in an arithmetic sequence, while an is used to represent the nth term.

A solid line symbolises continuous numbers, whereas the classmate's logical presumption is that an arithmetic series comprises of discrete values. This presumption is untrue, though, as a line can effectively represent an arithmetic series.

Learn more about arithmetic sequence here:

https://brainly.com/question/29616017

#SPJ1

Select three expressions equivalent to 28xy + 16x.

Answers

The three equivalent expressions to 28xy + 16x are:

4x(7y + 4)2(14xy + 8x)4xy(7 + 4).

What are three equivalent expressions to 28xy + 16x?

These expressions can be obtained by factoring out common terms from the original expression, resulting in equivalent expressions with the same values when evaluated.

For example, 4x(7y + 4) can be simplified to 28xy + 16x by using the distributive property. Similarly, 2(14xy + 8x) and 4xy(7 + 4) can also be obtained by factoring out common terms and rearranging the expression. Therefore, all three expressions are equivalent to the original expression, 28xy + 16x.

Read more about expressions

brainly.com/question/1859113

#SPJ1

Answer:

There are many expressions that are equivalent to 28xy + 16x, but here are three possible examples:

4x(7y + 4)

4(7xy + 4x)

8(3.5xy + 2x)

All three of these expressions follow the distributive property of multiplication over addition and simplify to 28xy + 16x.

Step-by-step explanation:

You are helping with some repairs at home. You drop a hammer and it hits the floor at a speed of 4 feet per second. If the acceleration due to gravity (g) is 32 feet/second 2, how far above the ground (h) was the hammer when you dropped it? Use the formula:

Answers

Step-by-step explanation:

vf = vo + at      vo = 0 in this case  ( you dropped it from 'at rest')

4 f/s = 32 t

t = 1/8 s

df = do + vot + 1/2 at^2                  df = final position = 0 ft (on the ground)

0 = do  + 0   + 1/2 (-32)(1/8)^2

   solve for do = 1/4 foot

If I mean absolute division is close to 0 then what does that mean about the data set

Answers

Answer:

If the mean absolute deviation of a data set is close to 0, it means that the data values in the set are very close to the mean of the set. In other words, the data points are clustered tightly around the average value, indicating that there is little variation or dispersion in the data.

This can be useful information in analyzing the data, as it suggests that the data is relatively homogeneous and consistent. On the other hand, if the mean absolute deviation is large, it suggests that the data is widely spread out and may have significant variability, which may require further investigation or analysis.

traffic engineers in florida want to reduce the rate of accidents between pedestrians and cars at intersections. research has shown that replacing stoplights with roundabouts (also called traffic circles) can improve safety for bikers and pedestrians. engineers wanted to test this concept so it can be applied across florida, and last year, they replaced five timed stoplights in a florida city with roundabouts. the accident rates at five intersections before the intervention were 5.1, 3.4, 6.1, 4.9, and 4.1 accidents per month. after installing roundabouts, the new rates of pedestrian accidents were 4.5, 3.6, 5.5, 4.8, and 4.1 accidents per month. does replacing stoplights with roundabouts significantly reduce the rate of accidents at intersections? use an alpha value of 0.05 in your decision.

Answers

Replacing stoplights with roundabouts does not significantly reduce the rate of accidents at intersections based on the given data.

Based on the statistical analysis, replacing stoplights with roundabouts does not significantly reduce the rate of accidents at intersections.

To test this hypothesis, we will use a paired t-test, which compares the means of two sets of paired data. The null hypothesis is that there is no significant difference between the mean accident rates before and after installing roundabouts, while the alternative hypothesis is that the mean accident rate after installing roundabouts is significantly lower than before.

Here are the steps to conduct the paired t-test:

Calculate the difference between the accident rates before and after installing roundabouts for each intersection.Calculate the mean and standard deviation of the differences.Calculate the t-value using the formula: t = (mean of the differences) / (standard deviation of the differences / sqrt(n)), where n is the number of paired observations.Calculate the degrees of freedom using the formula: df = n - 1.Find the critical t-value at a 0.05 level of significance and df from a t-distribution table.Compare the calculated t-value with the critical t-value. If the calculated t-value is greater than the critical t-value, reject the null hypothesis. If the calculated t-value is less than or equal to the critical t-value, fail to reject the null hypothesis.

Using the given data, the differences between the accident rates before and after installing roundabouts are:

-0.6, 0.2, 0.6, -0.1, 0

The mean of the differences is 0.02, and the standard deviation is 0.43. There are 5 paired observations, so the degrees of freedom are 4.

Using the formula, we get:

t = 0.02 / (0.43 / √(5)) = 0.14

The critical t-value at a 0.05 level of significance and 4 degrees of freedom is 2.776 from a t-distribution table.

Since the calculated t-value (0.14) is less than the critical t-value (2.776), we fail to reject the null hypothesis. Therefore, we can conclude that replacing stoplights with roundabouts does not significantly reduce the rate of accidents at intersections based on the given data.

Learn more about the null hypothesis

https://brainly.com/question/25263462

#SPJ4

Find the measure of angle a and B. Round to the nearest degree.

Answers

The measure of angle A and angle B are 32° and 58° respectively.

What is the measure of anglw A and B?

The figures in the image are right-triangle.

To find the measure of angle A and B, we use the trigonometric ratio.

For angle A:

Angle θ = ?

Opposite to angle θ = 8

Hypotensue = 15

Note that: sine = opposite / hypotensue

sinθ = 8 / 15

Take th sine inverse

θ = sin⁻¹( 8/15 )

θ = 32°

Angle A = 32°

For angle B:

Angle B = ?

Adjacent to angle B = 8

Hypotensue = 15

Note that: cosine = adjacent / hypotensue

cosB = 8/15

Take th cosine inverse

B = cos⁻¹( 8/15 )

B = 58°

Therefore, angle B measures 58 degrees.

Learn more about trigonometric ratio here: brainly.com/question/28016662

#SPJ1

Find side a and side c when b = 12, = 93°, = 30°

Answers

The length of the third side of the triangle is approximately 5.6 units.

To find the length of the third side of the triangle, we can use the Law of Cosines, which relates the lengths of the sides of a triangle to the cosine of the angle between them. The formula is

c² = a² + b² - 2ab×cos(C)

Where c is the length of the third side of the triangle, and C is the angle opposite to side c.

We can plug in the given values to get:

c² = 4.5² + 6^2 - 24.56×cos(35°)

We can solve for c by taking the square root of both sides

c = √(4.5^2 + 6^2 - 24.56×cos(35°))

Evaluate the right-hand side to get

c ≈ 5.6 units

Learn more about Law of Cosines here

brainly.com/question/17289163

#SPJ4

I have solved the question in general, as the given question is incomplete.

The complete question is:

You are given two sides of a triangle, a = 4.5 and b = 6, the angle between them is 35 degrees, how do you find the third side?

What is an equation of the line that is perpendicular to y + 1 = -3(x-5) and passes through the point (4,-6)?

Answers

[tex]\boxed{\bold{y + 6 = \frac{1}{3} (x - 4)}}[/tex]

Replace the second y (y1) and the 2nd x (x1) with the new points and then -3 become 1/3 due to perpendicular meaning opposite reciprocal (2/3 reciprocal is 3/2 and the opposite would be its negative, -3/2, for example)

So there's your answer plus some info for future knowledge

Answer:

y + 6 = 1/3 (x-4)

Step-by-step explanation:

An aircraft (at Z) is spotted by two observers (at X and Y) who are L = 1850 feet apart. As the airplane
passes over the line joining them, each observer takes a sighting of the angle of elevation to the plane,
as indicated in the figure. If A=25°, and B=25°, how high is the airplane?

Answers

Answer: We can use trigonometry to solve this problem. Let's call the height of the airplane H, and let's call the distance from observer X to the airplane D. Then the distance from observer Y to the airplane is L - D.

From the point of view of observer X, we can write:

tan(A) = H / D

tan(25°) = H / D

From the point of view of observer Y, we can write:

tan(B) = H / (L - D)

tan(25°) = H / (L - D)

We now have two equations with two unknowns (H and D). We can solve for one of the unknowns in terms of the other, and then substitute that expression into the other equation to eliminate one of the unknowns.

Let's solve the first equation for D:

D = H / tan(25°)

Substituting this expression for D into the second equation, we get:

tan(25°) = H / (L - H / tan(25°))

Multiplying both sides by (L - H / tan(25°)), we get:

tan(25°) (L - H / tan(25°)) = H

Expanding the left-hand side, we get:

tan(25°) L - H = H tan^2(25°)

Adding H to both sides, we get:

tan(25°) L = H (1 + tan^2(25°))

Dividing both sides by (1 + tan^2(25°)), we get:

H = (tan(25°) L) / (1 + tan^2(25°))

Now we can substitute this expression for H into the equation D = H / tan(25°) to get:

D = ((tan(25°) L) / (1 + tan^2(25°))) / tan(25°)

Simplifying, we get:

D = L / (1 + tan^2(25°))

Now that we know the distance D, we can use the equation tan(A) = H / D to find H:

tan(25°) = H / D

H = D tan(25°)

Substituting D = L / (1 + tan^2(25°)), we get:

H = (L / (1 + tan^2(25°))) tan(25°)

Plugging in the given values L = 1850 feet and A = B = 25°, we get:

H = (1850 / (1 + tan^2(25°))) tan(25°)

H ≈ 697.3 feet

Therefore, the airplane is about 697.3 feet high.

Step-by-step explanation:

what is the total number of teaspoons of water conditioner kallie will use for all the water in the 12 fish tanks?

show your work

Answers

Answer:

6 teaspoons

Step-by-step explanation:

If there are 12 tanks of 20 quarters each, that is 240 quarts of water in total. A quarter is only 1/4 of gallon, so you divide 240/4 to give you 60 Gallons. If it is 1 tsp per 10 gallons, that is 6 tsps for 60 gallons

What is the reason for Statement 3 of the two-column proof?
O Linear Pair Postulate
O Angle Addition Postulate
O Definition of complementary angles
Definition of angle
k
Given: mzJMK = 52"
m2KML = 38
Prove: ZJML is a right angle.
Statements
1. m/JMK = 52"
2 m/KML = 38"
3.
M
m/JMK+m/KML = m/JML
4.52 +38 = m/JML
5.90 = m/JML
6 /JML is a right angle
Reasons
Given
Given
Substitution
Property of Equality
Simplification
Definition of right
angle

Answers

The measure of ∠JMK =52° and ∠KML = 38°.

Three rays ML, MK, and MJ share an endpoint M. Ray MK forms a bisector as shown in the attached image and the bisector divides angle JML into two parts.

To Prove:  is a right angle.

Proof:

Statements  Reasons

1. m∠JMK = 52°                  Given

2. m∠KML = 38°                  Given

3. m∠JMK + m∠KML = m∠JML

The reason for statement 3 is Angle addition postulate. As angle JML is composed of 2 angles that is angle JMK and angle KML. So by adding the measures of angles JMK and KML, we will get the measure of angle JML which is referred as Angle addition postulate.

4. 52° + 38° =m∠JML            Substitution property of equality

5. 90° = m∠JML                    Simplification

6. ∠JML is a right angle.      Definition of right angle

To know more about angle check the below link:

https://brainly.com/question/25716982

#SPJ9

a survey of an urban university showed that 1,010 of 1,500 students sampled supported a fee increase to fund improvements to the student recreation center. using the 95% level of confidence, what is the confidence interval for the proportion of students supporting the fee increase

Answers

The 95% confidence interval for the proportion of students supporting the fee increase is (0.6453, 0.7013), indicating with 95% confidence where the true proportion of supporters is likely to fall based on the sample data.

How to find the confidence interval for the proportion?

Using the given information, the sample proportion of students supporting the fee increase is 1,010/1,500 = 0.6733. To find the confidence interval for the population proportion, we can use the formula:

CI = p ± z*√(p(1-p)/n)

where p is the sample proportion, z is the z-score corresponding to the level of confidence (95% in this case), and n is the sample size.

Using a standard normal distribution table or calculator, the z-score for a 95% confidence level is approximately 1.96.

Plugging in the values, we get:

CI = 0.6733 ± 1.96 * √(0.6733*(1-0.6733)/1500)

CI = 0.6733 ± 0.028

Therefore, the 95% confidence interval for the proportion of students supporting the fee increase is (0.6453, 0.7013) to the nearest thousandth.

Learn more about Confidence interval

brainly.com/question/24131141

#SPJ11

if you want to save $900,000 for your retirement, you invest your money in a savings account that has an APR of 6% which is compounded each month. you are 20 years old and planning to retire at age 65, how much money do you need to deposit into the savings account each month in order to reach your retirement goal at age 65?

Answers

We need to deposit $326.56 into the savings account each month in order to reach your retirement goal at age 65, assuming an APR of 6% compounded monthly.

What is Compound interest?

Compound interest is a type of interest that is calculated not only on the principal amount of money borrowed or invested, but also on the accumulated interest from previous periods. In other words, it is interest calculated on both the initial principal and the interest earned in previous periods.

To determine how much money you need to deposit into the savings account each month in order to reach your retirement goal at age 65, you can use the formula for future value of an annuity:

FV = [tex]PMT * \frac{(1 + r/n)^{n*t} - 1 }{r/n}[/tex]

where:

FV is the future value, which is the amount of money you want to save for retirement ($900,000 in this case)

PMT is the payment you need to make each month

r is the annual interest rate (6% in this case)

n is the number of times the interest is compounded per year (12 in this case, since the interest is compounded monthly)

t is the number of years until retirement (45 in this case, since you are 20 years old and planning to retire at age 65)

Substituting these values into the formula, we get:

$900,000 =  [tex]PMT * \frac{(1 + 0.06/12)^{12*45} - 1 }{0.06/12}[/tex]

$900,000 = [tex]PMT * \frac{(1 + 0.005)^{540} - 1 }{0.005}[/tex]

$900,000 = [tex]PMT * \frac{(1.005)^{540} - 1 }{0.005}[/tex]

$900,000 = [tex]PMT * \frac{(14.78 - 1) }{0.005}[/tex]

$900,000 = PMT × 2756

   ∴ PMT = $326.56

Therefore, you need to deposit $326.56  into the savings account each month in order to reach your retirement goal at age 65, assuming an APR of 6% compounded monthly.

To learn more about Compound interest visit the link:

https://brainly.com/question/28020457

#SPJ1

Which equation is perpendicular to y= -2/7x - 5 and passes through (2,4)?

Answers

the answer to your question is y = (-7/2)x + 11

Lines m and n intersect to form various angles.
Which angle is a vertical angle with ∠6?


∠5

none of these


∠8


∠7

Answers

Answer:

Angles 6 and 8 are vertical angles.

please someone help and give answers !!!

Answers

16.) Mean average deviation= option C

17.) Range of a data set = option E.

18.) First quartile = opinion AB

19.) Second quartile = option B

20.) Third quartile = option A

21.) Interquartile range = option D

How to determine the measures of the spread?

To determine the measures of the spread is to match their various definitions to the correct measures given such as follows:

16.) Mean average deviation: The average deviation of data from the mean.

17.) Range of a data set : The difference between the highest value and the lowest value in a numerical data set.

18.) First quartile: The median in the lower half.

19.) Second quartile: The median value in a data set.

20.) Third quartile: The median in the upper half.

21.) Interquartile range: The distance between the first and the third quartile.

Learn more about range here:

https://brainly.com/question/26098895

#SPJ1

A point that moves on a coordinate line is said to be in simple _________ ___________ if its distance d from the origin at time t is given by either d = a sin ωt or d = a cos ωt.

Answers

A point that moves on a coordinate line is said to be in simple harmonic motion if its distance d from the origin at time

t  is given by either d = a sin ωt or d = a cos ωt.

Simple harmonic motion, or SHM for short, is a particular kind of periodic motion of a body that results from a dynamic

equilibrium between an inertial force that is proportional to the body's acceleration away from the static equilibrium

position and a restoring force on the moving object that is directly proportional to the size of the object's displacement

and acts towards the object's equilibrium position. If friction or any other energy dissipation is not present, it leads to an

oscillation that is represented by a sinusoid and that lasts indefinitely.

The oscillation of a mass on a spring when it is subject to the linear elastic restoring force specified by Hooke's law is a

good example of simple harmonic motion, which may be used as a mathematical model for many different motions.

The motion has a single resonant frequency and is sinusoidal in time. Simple harmonic motion can be used to simulate

a variety of other phenomena, such as the motion of a simple pendulum, though it is only a good approximation when

the angle of the swing is small; for more information, see small-angle approximation. In order for the model to be

accurate, the net force acting on the object at the end of the pendulum must be proportional to the displacement.

Molecular vibration can also be modelled using straightforward harmonic motion.

for such more question on simple harmonic motion

https://brainly.com/question/26114128

#SPJ11

Other Questions
A tapeworm is an organism that may live in the intestines of an animal. When the animal eats, the tapeworm feeds upon the nutrients of the ingested food. This relationship between the tapeworm and the animal is an example of _______. A. predation B. commensalism C. mutualism D. parasitism CORRECT OR INCORRECTsalivary secretions (which start starch breakdown) are insufficient until about 12 months of age. pancreatic amylase levels may not be sufficient until 12 to 18 months of age 2CO(g) + O(g) 2CO(g)9.0 L of O2 react with excess CO atSTP. How many moles of CO2 formduring the reaction?[?] mol COmol COEnter Please help this is due in 4 hours!! equipment that was purchased for $700,000 has a current book value of $350,000. assume a capital gains tax rate of 28%. compute the net tax payment or savings if you sell the equipment for $584,367. Once upon a time there was a farmer named Fanny. Fanny went to townfor supplies. While she was in town, she bought a specially trained foxnamed Federico who could balance plates on his nose (she thought herchildren would like him). Fanny bought a chicken because she lovedomelets and always wanted fresh eggs. She also bought a bag of cornseed so she could grow corn on the cob for picnics. Unfortunately,Fanny forgot that she had to cross a river to get back to her farm. Shemay only take one thing at a time in the boat. She cannot leave the foxand the chicken together on either side of the river, or the fox will eat thechicken. Likewise, she cannot leave the chicken alone with the bag ofcorn or the chicken will eat the corn. You must help Fanny get her fox,her chicken, and her bag of corn safely across a river in a boat. What isthe fewest number of trips needed to get everything across the riverwithout anything being eaten? From one side of the river to the otherside of the river counts as one trip. what mass of cu(s) is electroplated by running 23.0 a of current through a cu2 (aq) solution for 4.00 h ? express your answer to three significant figures and include the appropriate units. If anyone is reading this rn i would be so flipping happy if you solves this for me i have been putting this same question up for 2 days now and 9 times please help me Explain, in your own words, why functional words, as opposed to content words, are limited in number abc company holds a well-diversified portfolio in the amount of $90,000 that has an expected return of 11.0% and a beta of 1.15. it is buying 1,000 shares of def company stock at $10 a share and adding them to its portfolio. def company has an expected return of 13.0% and a beta of 1.34. currently, the risk free rate is 3.5%, and the stock market return is 8.2%. what will the required rate of return on the new portfolio be after the purchase of def stock? (hint: compute a new portfolio beta first and then use the capm.) modern (i branded) intel cpus use a(n) ________ package for socketed cpus. You have collected Sanofi Inc's historical earnings per share information up to the end of year 2020. You have determined that the average growth rate of earnings is 12%. The 2020 year-end EPS amounted to R21.78. Based on your analysis of Sanofis fundamentals you estimate that the firm's earnings will continue to grow at its average historical growth rate for the next year but that in the following year, as a result of the launch of a new product the firm is currently developing, earnings will grow at a rate of 20% per year for two years. After this, you project that the earnings growth rate will decrease by 10% for the next year, to its long-term sustainable rate. You project that the firm will maintain a 50% dividend pay-out ratio and that the appropriate market capitalisation rate for Sanofi Inc is 15%.You currently have 100 shares of Sanofi, Your expected dividend amount in 2021 is equal to R ___round off your answer to two decimal places. If the firm's shares are currently trading at R620 per share, you will buy/sell/hold) ___the shares because they are (undervalued/overvalued correctly valued)___ as the intrinsic value is equal to R ___round off your answer to two decimal places. The terminal value at the end of the 4th year is equal to R___ round off your answer to the nearest whole number The following two payment options each has a present value of X. (i)140 at the end of each year, forever, with the first payment due at t = 1. (ii)A payment of 1971.24 at t = 10, followed by 140 at the end of each year, forever, with the first payment of 140 due at t = 11. Find X. a.1.740.54 b.1.854.05 c.1.778.38 d.1.891.89 e.1.816.22 if there are no other feasible solutions with a larger objective function value in the immediate neighborhood, then the feasible solution is known as the ________ is the most stable social group among band societies with a seasonal pattern of population dispersal.select one:a.lineageb.bandc.nuclear familyd.clane.expanded family household The dissolution or liquidation of an LLC is most likely to occur: (Check all that apply.)-at the end of the fiscal year, after all taxes are paid.-when a majority of the members vote to end the business.-when a competitor offers to buy the business.-when an event defined in the operating agreement occurs, such as the death of a member. if i have 21 liters of gas held art a pressure of 78 atm and temperature of 900k , what will be the volume of the gas if i decreased the pressure to 45atm and decrease the temperature to 750k TRUE / FALSE 1. Intent to discriminate must be proven for a disparate impact case to be successful. 2. If the plaintiff proves their prima facie case under the McDonnell Douglas standard, the burden of proof shifts to the defendant to evidence a legitimate and nondiscriminatory reason for the discriminatory action. 3. them. Generally, regarding employment at-will, employees may be fired just because the boss doesn't like 4. An independent contractor is not considered an employee but is entitled to minimum wage and overtime protections. 5. One of the principal's duties is to keep an accounting during the agency relationship. 6. If an agent is acting within the scope of her employment, should she commit an intentional tort harming a third party the principal may be liable for the injuries sustained. The Social Security Act is funded through mandatory employment taxes paid by both the employer and employee. 8. The Fair Labor Standards Act does not cover all employees. 9. When an employee suffers a job related injury, the employee always has a choice of suing the employer in court or seeking workers' compensation. 10. Once an employee has established that she has a covered disability, the Americans with Disabilities Act requires that the employer make reasonable accommodations allowing the employee to perform the essential functions of the job. What is the area of the following right triangle? You have two stocks from which to pick. The first stock has a current stock price of $46 and earnings per share of $3.63. The second stock has a current stock price of $36.50 and earnings per share of $4.31. Both firms are in the media industry, and the average P/E ratio for the industry is 12. Use the P/E ratio to determine which stock you expect to have higher earnings. What is the P/E ratio of the first stock and of the second stock? (Round your answers to 2 decimal places.) P/E ratio First stock Second stock Which stock is expected to have higher earnings growth in the future? O First stock Second stock