A catchment area having D index value of (15) mm/hr experienced the storm of the following intension: 1) 50 mm/hr for 2 hrs 2) 30 mm/hr for 1/2 hr The resulting surface runoff was (10x106) m³. Find the catchment area.

Answers

Answer 1

The D index value is a method of estimating the time of concentration in an area and has units of mm/hr. In this case, a catchment area has a D index value of 15 mm/ hr and has experienced a storm of two different intensities:

50 mm/hr for 2 hours and 30 mm/hr for 0.5 hours. The resulting surface runoff was 10x10^6 m³. The catchment area can be determined using the following steps:
1. Determine the rainfall depth: To calculate the rainfall depth for each of the storm intensities, multiply the intensity by the duration.


2. Determine the total rainfall depth: The total rainfall depth is the sum of the rainfall depths for each storm.
Total rainfall depth = 100 mm + 15 mm = 115 mm
3. Calculate the runoff volume: The runoff volume can be calculated using the following equation:
Runoff volume = Catchment area * Rainfall depth * (1 + 0.007 * Rainfall depth)
where the rainfall depth is in mm and the runoff volume is in m³.
To know more about concentration visit:
https://brainly.com/question/13872928

#SPJ11


Related Questions

You could maintain a personal inventory of your own tendencies as a consumer over the course of 1-­‐2 days in terms of unsustainable consumption practices as a useful way to begin to identify potential obstacles to adoption of sustainable solutions.
a. Provide a discussion of your unsustainable consumption practices and resistance to sustainable products and practices in general based on your personal inventory.
b. Create a proposed "Corporate" Sustainability Business Plan for another company you have worked for, are working for, would like to work for in the future, or a company of interest. Select a firm of your choice

Answers

a. Unsustainable consumption practices and resistance to sustainable products and practices based on personal inventory: Over the course of 1-2 days, I have identified various unsustainable consumption practices that I engage in. One of these practices is excessive use of single-use plastics, such as water bottles and plastic bags.

I have realized that I have a tendency to use these products once and dispose of them, which contributes to the already existing problem of plastic pollution. I have also realized that I tend to purchase products that are not sustainably produced or sourced.

Invest in water-efficient technology such as water-efficient coffee machines and dishwashers. Implement waste reduction programs such as the donation of unsold food to local food banks and the use of reusable cups and utensils. Invest in composting and recycling programs to reduce waste generation. Expand the company's ethical sourcing program to increase the proportion of sustainably sourced coffee to 100%.Through the implementation of this "Corporate" Sustainability Business Plan, Starbucks Corporation will reduce its environmental impact while promoting sustainable practices within the coffee industry.

To know more about practices  visit:

brainly.com/question/12721079

#SPJ11

A farmer on the Namoi River is developing flood irrigation for her cotton farm. She has an existing bore that she pumps 300 L/s from a sand aquifer beneath her property. The sand aquifer lies at 80 m depth and is 30 m thick. The hydraulic conductivity of the sand is 50 m/day and the storage coefficient of the sand aquifer is 0.00015. At the end of 100 days continuously pumping, the water level in her abstraction bore is 50 m below ground surface. To preventing the pump from running without water and being damaged she has set a low-level cut-out on the pump at 65 m below. ground, 5 m above the top of the pump. She now wishes to double the irrigated area by installing a second abstraction bore at a location 1000 m to the south of the first bore on the other side of her property. Assume that the aquifer properties remain the same over the property and that the aquifer is horizontal. (a) Draw a sketch of the problem. [3 marks] (b) What will be the additional drawdown at her existing bore due to this new bore pumping for the same 100 days? Provide your answers with 6 significant figures. [5 marks] (c) Will this be an issue for her existing pump? Qualify your answer. [2 marks] Her neighbour, seeing the increased profit from the larger irrigated area, also wishes to develop an abstraction bore from the same aquifer. The neighbour's preferred location is a site 300 m to the north of the farmer's first abstraction bore. Assume that this third bore will also pump at 300 L/s for 100 days and that the aquifer properties remain the same. (d) What will the drawdown at the original farmer's first bore now be? Provide your answers with 6 significant figures. [marks 5] (e) How do you think the farmer should approach the neighbour to resolve any possible future conflict?

Answers

(a) Sketch of the problem: The given problem requires to investigate the drawdown impact on the existing borehole if a new borehole is pumped continuously for the same time. Also, we need to estimate the drawdown of the first borehole when a new borehole is drilled in the north of the first borehole. Therefore, the conceptual model .

(b) Additional drawdown: The additional drawdown in the existing borehole due to the new borehole will be calculated using the Theis equation. The equation is as follows:

[tex]s = Q / (4 π T) (W(u) - W(ur)) = (25920 m3/day) / (4 π × 50 m/day) (0.416 - 0.0) = 263.8 m[/tex]
The additional drawdown in the existing borehole due to the second borehole will be 263.8 m.

(c) Issue for the existing pump: Yes, this could be an issue for the existing pump because the low-level cut-out on the pump is set at 65 m below the ground, which is 5 m above the top of the pump. The calculated additional drawdown (i.e., 263.8 m) is higher than the low-level cut-out, which could cause damage to the pump.

[tex]s = Q / (4 π T) (W(u) - W(ur)) = (25920 m3/day) / (4 π × 50 m/day) (0.416 - 0.108) = 160.8 m[/tex]

Therefore, the total drawdown in the existing borehole due to the second and third borehole will be:

[tex]Stotal = 263.8 + 160.8 = 424.6 m[/tex]
(e) Approach to resolve the future conflict: The farmer could approach the neighbor by explaining the possible consequences of abstraction bore and its impact on the surrounding aquifer. The farmer could also recommend the neighbor to seek professional advice from a hydrogeologist to understand the sustainable yield of the aquifer and its impact on the environment.

To know more about hydrogeologist visit:-

https://brainly.com/question/13428729

#SPJ11

A 6m x 6m slab panel serves as a floor for a light storage room, The slab has no ceiling on it but with a 25mm thick concrete fill finish for the flooring. The slab is an interior slab with adjacent slabs on all of its sides. Determine the required rebar spacing for the top column strip using a diameter 12 rebar. f'c= 28 MPa
fy = 414 MPa

Answers

Spacing of bars = (Effective depth - clear cover - half the diameter of the largest bar - half the diameter of the smallest bar) / (Number of bars - 1) Spacing between the adjacent slabs on all of its sides is 50 mm For the slab of size 6 m x 6 m, the spacing between the adjacent slabs on all sides will be 50 + 50 = 100 mm or 0.1 m

The effective depth will be, Effective depth = Overall depth - (0.5 x diameter of largest bar) - (0.5 x diameter of stirrup)= [tex](250 mm - 6 mm) - (0.5 x 12 mm) = 229 mm = 0.229 m[/tex]

The moment of resistance of the section is given by,[tex]M = (f'c / 6) * b * d²= (28 × 10⁶ / 6) × 1 × 0.229²= 573876.92 Nm[/tex]

The bending moment acting on one meter width of the beam will be,Bending moment = M / Width of the beam= [tex]573876.92 / 1= 573876.92 Nm/m[/tex]

The maximum tension developed in the extreme fibre will be[tex],f_s = (fy / γs) × As[/tex]Where,γs = 1.15As = Area of steel reinforcement[tex]As = (0.85 × f_y × A_1)/f_c[/tex]'Where,A_1 = Area of concrete below the centroid of steel sectionMaximum tension developed in the extreme fibre

,[tex]f_s = (fy / γs) × As= (414 × 10⁶ / 1.15) × [(0.85 × 414 × π × 12²) / (28 × 10⁶)]f_s = 1325.37 N/mm²[/tex]

[tex]A_s = (M × 10⁶) / (0.87 × fy × d)A_s = (573.88 × 10⁶) / (0.87 × 414 × 0.229)A_s = 4788.73 mm²/[/tex]

Number of bars = Spacing of bars / center-to-center distance between two bars + 1Spacing between the adjacent bars will be,Center-to-center distance = 12 + 34 = 46 mm

Number of bars = [tex]34 / 46 + 1= 1.74 ≈ 2[/tex]Thus, the number of bars required in the top column strip would be 2 and the spacing between the bars will be 34 mm.

To know more about Effective depth visit:-

https://brainly.com/question/31427952

#SPJ11

A WTP receives (15140 m³/day) of water. Five clariflcculators unit each c (12) m outside diameter were used in the plant. If the detention time at th flocculation part is ( 25 ) min. ( assume the minimum values needed in th design):-
1- Calculate the dimensions of the inside flocculation part.
2- Calculate the( d.t) needed for settling parts of clariflcculators.

Answers

1. Dimensions of the inside flocculation part We have been provided with the flow rate of water that a water treatment plant (WTP) receives daily which is 15,140 m³/day, and the number of clari flocculators unit each of 12 meters outside diameter which is five (5). We are to calculate the dimensions of the inside flocculation part of the clari flocculators. The detention time at the flocculation part is given to be 25 minutes.

Let’s use the formula for surface area of a cylinder to solve for the inside diameter and height of the flocculation part.Surface area of a cylinder = 2πrh + 2πr²Where r is the radius of the cylinderh is the height of the cylinderπ is the mathematical constant, pi which is approximately 3.14Surface area of the clariflocculators = flow rate / surface loading rateSurface loading rate is 10 – 20 m³/day.

m²Let’s assume the surface loading rate to be 10 m³/day.m²Surface area of clariflocculators = 15,140 / 10 = 1514 m²Total surface area of five clariflocculators = 1514 x 5 = 7570 m²Total outside surface area of five clariflocculators = πdLh + 5πd²/4Where d is the outside diameter of clariflocculatorh is the height of clariflocculator Total outside surface area of five clariflocculators = 5 x 3.14 x 12 x h + 5 x 3.14 x 12² / 4 = 2260.16h + 678.24

We know that the detention time of water at the flocculation part is 25 minutes but we can convert it to seconds which is a more preferable unit of time for calculation purpose.25 minutes = 25 x 60 seconds = 1500 secondsNow we can use the formula for volume of a cylinder to find the inside diameter and height of the flocculation part.Volume of a cylinder = πr²hLet the inside diameter be dI and the height of the flocculation part be HTotal volume of five clariflocculators = 15140 x 25 x 60 = 22,710,000 cm³ = 22,710,000 / 10³ = 22,710 mL.

To know more about flocculation visit:

https://brainly.com/question/30676469

#SPJ11

Three vehicles pass a mile posy at 50, 40, and 35.3 mph repectively. What is the time mean speed of the three vehicles?
Calculate the rate of flow of vehicles from the following data: Time period Volume (vehicles)
4-4:15 700
4:16-4:30 812
4:31-5:00 1635

Answers

The rate of flow of vehicles is:

[tex]\[\frac{700}{15} = 46.67 \text{ vehicles per minute}\][/tex]

[tex]\[\frac{812}{14} \approx 58 \text{ vehicles per minute}\][/tex]

[tex]\[\frac{1635}{29} \approx 56.38 \text{ vehicles per minute}\][/tex]

The time mean speed of the three vehicles is 41.43 mph.

The formula for finding the time mean speed is given as follows:

[tex]\[\frac{\text{Total Distance}}{\text{Total Time}}\][/tex]

The distance covered by the three vehicles can be found as follows:For the first vehicle,

[tex]\[\text{Distance} = \text{Speed} \times \text{Time}[/tex]

              [tex]= 50 \text{ mph} \times 1 \text{ hour}[/tex]

              [tex]= 50\text{ miles}\][/tex]

For the second vehicle,

[tex]\[\text{Distance} = \text{Speed} \times \text{Time}[/tex]

              [tex]= 40 \text{ mph} \times 1 \text{ hour}[/tex]

              [tex]= 40\text{ miles}\][/tex]

For the third vehicle,

[tex]\[\text{Distance} = \text{Speed} \times \text{Time}[/tex]

              [tex]= 35.3 \text{ mph} \times 1 \text{ hour}[/tex]

              [tex]= 35.3\text{ miles}\][/tex]

Therefore, the total distance covered by the three vehicles is [tex]$50 + 40 + 35.3 = 125.3\text{ miles}$[/tex].

The total time taken by the three vehicles is

[tex]\[\text{Total Time} = \frac{\text{Total Distance}}{\text{Speed}}[/tex]

                  [tex]= \frac{125.3\text{ miles}}{41.43 \text{ mph}} \approx 3.02 \text{ hours}\][/tex]

Therefore, the time mean speed of the three vehicles is

[tex]\[\frac{125.3\text{ miles}}{3.02 \text{ hours}} \approx 41.43 \text{ mph}\][/tex]

Rate of flow of vehicles is calculated by dividing the volume of vehicles by the time period as shown below:

For the time period 4-4:15, the rate of flow is:

[tex]\[\frac{700}{15-0}\][/tex]

For the time period 4:16-4:30, the rate of flow is:

[tex]\[\frac{812}{30-16}\][/tex]

For the time period 4:31-5:00, the rate of flow is:

[tex]\[\frac{1635}{60-31}\][/tex]

Therefore, the rate of flow of vehicles is

[tex]\[\frac{700}{15} = 46.67 \text{ vehicles per minute}\][/tex]

[tex]\[\frac{812}{14} \approx 58 \text{ vehicles per minute}\][/tex]

[tex]\[\frac{1635}{29} \approx 56.38 \text{ vehicles per minute}\][/tex]

For more such questions on rate of flow, click on:

https://brainly.com/question/30618961

#SPJ8

You are an engineer in a construction company, Bina Sdn Bhd. You are given the task to supervise the construction project of a badminton hall owned by the JKKK Kampung Pisang. Discuss the scope of works to be accomplished in a project. This project must be completed within 6 months from the date of project award. Discuss the scope of works to be accomplished in this project.

Answers

As an engineer in a construction company, the scope of works to be accomplished in a construction project of a badminton hall owned by JKKK Kampung Pisang include the following :Planning and Designing- It includes preparing a blueprint and layout for the project, identifying the materials and resources required, and developing a plan to meet the project's objectives.

Site Preparation- This involves clearing the site, leveling the ground, and making it ready for construction .Foundation Works- The construction of the foundation walls, columns, and beams for the building structure form a vital part of the scope of work. This includes excavation, footing and foundation, concrete works, etc.

In conclusion, the scope of work for the construction project of a badminton hall owned by JKKK Kampung Pisang is extensive and requires careful planning and execution. The project must be completed within six months from the date of award, and it is the responsibility of the construction company to ensure that the project is completed on time and within budget.

To know more about  engineer visit:

brainly.com/question/18063037

#SPJ11

A braced column of 6 m long fixed at both ends is proposed to carry a designed load of 1500 KN. In this design, column section of 203 x 203 x 60kgm¯¹ with grade S275 is used and the section is in Class 1.
(a) Calculate the effective length and slenderness ratio of the column section about the major axis. (CO1-PO2) (C4)
(b) Check the buckling resistance of the column. (CO2-PO5) (C4)

Answers

(a) Calculation of Effective Length of Column: Effective length is given by le = 1.0LThe given column is fixed at both ends. Therefore, the effective length will be le = L = 6 m Effective length of the column le = 6 m Calculation of slenderness ratio:

Slenderness ratio is given byλ = K * l / rwhere, K = effective length factorl = effective length of column   r = radius of gyrationλ = slenderness ratio of the column Section area of the column A = b * hwhere, b = breadth of column

h = depth of column mFor the given section, b = h = 203 mm  

A = section area Therefore, [tex]ry = √(7035.82367 * 10⁻⁴ / 4.1209 * 10⁻³) = 0.5240[/tex]m Slenderness ratio of column sectionλ = K * le / ry  where, K = effective length factor = 1 for both fixed endsλ = 1 * 6 / 0.5240 = 11.45 about major axis.

To know more about slenderness visit:

https://brainly.com/question/27944552

#SPJ11

Disinfection:
The process of Ultraviolet Irradiation (generated by low pressure mercury vapor lamps) is the most widely used primary disinfection process in modern drinking water treatment plants in the United States and abroad, while chlorination is the most widely used approach for secondary disinfection (only applied in the United States)
a) Describe the reason(s) why UV Irradiation generated using LPMVL is an effective primary disinfectant. b) Why does UV Irradiation is not considered as an alternative secondary disinfectant?

Answers

UV Irradiation generated using LPMVL (Low Pressure Mercury Vapor Lamps) is an effective primary disinfectant because it can successfully disinfect microorganisms such as bacteria, viruses, and protozoa without adding any chemicals or altering the taste or odor of water.

UV irradiation alters the DNA or RNA of microorganisms, destroying their ability to reproduce and spread, thus, preventing diseases. It is one of the few primary disinfection methods that can inactivate Cryptosporidium and Giardia. Additionally, UV irradiation is safe, easy to operate, and maintain, and it does not produce harmful by-products such as trihalomethanes (THMs).

UV Irradiation is not considered as an alternative secondary disinfectant because it is not persistent and cannot provide residual disinfection. Secondary disinfection is essential in ensuring that any microorganisms that may have survived the primary disinfection process are eliminated and that any potential contamination is prevented as the water moves through the distribution system to consumers.

Chlorine, can provide residual disinfection, ensuring that any microorganisms that may be introduced to the water are neutralized as the water moves through the pipeline.

To know more about microorganisms visit:-

https://brainly.com/question/18861725

#SPJ11

A sewer pipe, 2.5 m in diameter, roughness size n=0.014 and bed slope of 0.00017, is used to carry storm runoff. It has been decided to discharge this water into a concrete lined water course which is to have a best rectangular profile and is laid at the same slope. If the pipe flows at a maximum of 50% capacity determine the dimensions of the required channel.

Answers

The required dimensions of the rectangular channel are:b = 8.055 m, h = 0.6936 m. The pipe flows at a maximum of 50% capacity If the pipe flows at a maximum of 50% capacity, then the discharge is equal to one-half of the maximum discharge.

The Manning formula is:

[tex]Q = (1/n)A(R^(2/3))(S^(1/2))[/tex] ,Q is the discharge (m³/s)A is the cross-sectional area (m²)n is the Manning's roughness coefficientR is the hydraulic radius (m)S is the bed slope (m/m)R = A/P, where P is the wetted perimeter of the pipe. For a circular pipe, P = πd. Therefore, the hydraulic radius of the pipe is:

[tex]R = A/P = (π/4)d²/(πd) = (1/4)d = 0.625 m[/tex]

Qmax = [tex]AVmax = 2A(R^(2/3))(S^(1/2))/(1/n) = 2.5³(π/4)(0.625)^(2/3)(0.00017)^(1/2)/(0.014) = 2.81 m³/s[/tex]

Therefore, the discharge into the concrete lined water course is one-half of this value, or:[tex]Q = 2.81/2 = 1.405 m³/s[/tex]The dimensions of the rectangular channel can be determined using the continuity equation.

The Manning formula can be used to determine the required width and depth of the channel. Substituting the given values, we have

[tex]Q = (1/n)A(R^(2/3))(S^(1/2))1.405 = (1/0.014)bh(2bh/(b+2h))^(2/3)(0.00017)^(1/2)[/tex]

Since the depth of the channel cannot be negative, the depth of the channel is h = 0.6936 m. Therefore, the required width of the channel is:

[tex]b = Q/(nhR^(2/3)(S^(1/2))) = 1.405/(0.014)(0.6936)(0.625)^(2/3)(0.00017)^(1/2) = 8.055 m[/tex]

To know more about dimensions visit:-

https://brainly.com/question/31460047

#SPJ11

Which of these is a benefit of suspended growth systems over attached growth?
(a)The process is more stable and less susceptible to shock
(b)none of these
(c)The microbes have greater protection in the biofilm that is formed
(d)The concentration of microbes can be much higher giving greater efficiency

Answers

The correct answer is option (d).The benefit of suspended growth systems over attached growth are that the concentration of microbes can be much higher giving greater efficiency.

Suspended growth systems are wastewater treatment systems that involve the biological removal of waste by microorganisms that are suspended in wastewater. The organisms in this process metabolize the organic matter in the wastewater and convert it into biological cell tissue, water, and carbon dioxide.

Activated sludge and aerated lagoons are examples of suspended growth systems. Attached growth systems are wastewater treatment systems that involve microorganisms growing on a surface in the treatment process.

This increased concentration also means that the time required for wastewater treatment is reduced. Additionally, suspended growth systems are more flexible and can be used for a wider range of wastewater types than attached growth systems.

Therefore,  The concentration of microbes can be much higher giving greater efficiency.

To know more about microorganisms visit:-

https://brainly.com/question/9004624

#SPJ11

Estimate the flood discharge through a rectangular channel of (8m) wide, if the depth of water at two section of (150m) a part was (2.95 m and 2.8 m). and the drop in the water surface elevation was found to be (0.15m), (n-0.025), K, = 0.6 for contraction.

Answers

The flood discharge through a rectangular channel of 8m wide, if the depth of water at two sections 150m apart was 2.95m and 2.8m can be estimated as shown below:Given.

Width of rectangular channel = 8mDepth of water at the first section, y1 = 2.95mDepth of water at the second section, [tex]y2 = 2.8m[/tex]Distance between the two sections = 150mDrop in water surface elevation = 0.15mCoefficient of contraction, K, = 0.6Value of n = 0.025Let us assume that the flow rate is more than 100.

Hence, the normal depth is to be estimated using the Manning's equation as shown below: Q = A V Where ,Q = Discharge A = Cross-sectional area V = Velocity Let us consider the discharge to be Q Let the hydraulic radius be given by [tex]R = A/P[/tex], where P is the wetted perimeter Manning's equation can be written.

To know more about discharge visit:

https://brainly.com/question/24060655

#SPJ11

Mr. Jobert commissioned you to estimate the construction of a certain structure. As Engineers, our job includes giving detailed estimate inclusive of labor and materials. If approved, the contract for building the structure will be awarded to you.
However, Mr. Jobert already had a previous consultation with Prudencio, an independent foreman, who offered labor and services at a cheaper price.
How will you convince Mr. Jobert to engage in your services instead of Prudencio's?
Cite applicable provisions of the Code of Ethics for such situation.

Answers

As engineers, it is our responsibility to provide a comprehensive estimate that includes labor and materials. The code of ethics for engineers obliges us to uphold professional ethics and practices.

To be able to convince Mr. Jobert to engage in our services instead of Prudencio's, I will take the following steps. First, I will highlight our commitment to providing high-quality services, backed by our wealth of experience.

Furthermore, I will explain to him the numerous benefits of our services, including the high level of professionalism, the use of high-quality materials, and the use of modern technologies.

TO know more about estimate visit:

https://brainly.com/question/28579204

#SPJ11

a) Considering a four-step travel demand modeling process, list the types of data that should be collected and possible data sources associated with each step in the process b) Briefly discuss in what ways transportation (system) influences land use (activity system)?

Answers

a) The Three-step travel demand modeling process consists of trip generation, trip distribution, mode choice, and. Each step requires different data and possible data sources:

Trip Generation: This step involves gathering data on the number of trips that originate from or end at specific locations within a geographic area. Data sources for this step include household surveys, census data, and land use surveys.

Trip Distribution: The process of allocating generated trips to their respective destinations is called trip distribution. Data sources for this step include destination surveys, travel surveys, and employment data.

Mode Choice: This step involves predicting the modes of transportation that individuals will use to travel to their destinations. Data sources for this step include mode-specific surveys, household travel surveys, and transit ridership data.

Land use patterns are often influenced by transportation infrastructure, and transportation networks are influenced by land use patterns. Residential areas may be designed with cul-de-sacs, which discourage through-traffic, while commercial areas may be designed with more direct, arterial roads.

To know more about trip distribution visit:-

https://brainly.com/question/32790996

#SPJ11

1. A contractor has a project involving the construction of a small manufacturing plant. The contractor has selected a borrow site and has decided to use 27-cubic yard dump trucks to haul the needed fill material. The contractor has decided to use a hydraulic excavator with a shovel attachment to load the trucks. The excavator has expected productivity as 422cy/hr at 100% efficiency, and the truck cycle time excluding loading is 0.48hr. The job site operation efficiency is assumed as 0.8. a) How many dump trucks will be needed to work with the excavator? Select one: a. 8 b. 9 c. 6 d. 7 b)What is the expected fleet production if only 6 trucks are available to the fleet? Select one: a. 225 cy/hr b. 238 cy/hr c. 298 cy/hr d. 281 cy/hr
c) What is the expected fleet production if 11 trucks are available to the fleet?
Select one:a.422 cy/hr
b.516 cy/hr
c.338 cy/hr d.437 cy/hr d) How many dump trucks will be needed to work with the excavator?
Select one:
a.8
b.9
c.6
d.7

Answers

The answer is option (c) 6.

a) Number of dump trucks needed to work with excavator The total number of trucks needed to work with excavator can be calculated as; Number of trucks needed =

= [tex](422/27) × 0.48 × 0.8 = 6[/tex]

Therefore, the number of dump trucks needed to work with the excavator is 6.

b) Expected fleet production if only 6 trucks are available to the fleet Given, number of dump trucks available = 6The volume of each truck = 27 cubic yards Expected output = 100%

The job site operation efficiency is assumed as 0.8.Volume of excavator (bucket) = 422 cy/hr

[tex](6 × 27 × 60 / (0.48 × 6)) × 0.8 = 135 × 0.8 = 108 cy/hr[/tex]

Therefore, the expected fleet production if only 6 trucks are available to the fleet is 108 cy/hr.

c) Expected fleet production if 11 trucks are available to the fleet Given, number of dump trucks available = 11The volume of each truck = 27 cubic yards Expected output = 100%

The job site operation efficiency is assumed as 0.8.

Volume of excavator (bucket) = 422 cy/hr

The expected fleet production can be calculated as :- [tex](11 × 27 × 60 / (0.48 × 11)) × 0.8 = 297.5 cy/hr[/tex]

Therefore, the expected fleet production if 11 trucks are available to the fleet is 297.5 cy/hr.

The number of dump trucks needed to work with the excavator is given as 6.

To know more about Volume visit:-

https://brainly.com/question/24086520

#SPJ11

List three factors that increase compressive strength of intact rock material in laboratory testing: (3)

Answers

Compressive strength of rock is the ability of the rock material to resist failure under compressive loads. It is an important parameter to evaluate the stability of rock structures such as dams, tunnels, and foundations.

1. Mineralogy of the rock: The mineral composition of rock has a direct effect on its compressive strength. Rocks that are rich in quartz and feldspar minerals are generally stronger than those composed of softer minerals like clay and gypsum.

2. Porosity and density of the rock: The porosity and density of rock can affect its compressive strength.  This is because porosity weakens the rock by providing planes of weakness for crack propagation, while density provides more interlocking between grains, thus enhancing the rock's strength.

3. Confining pressure: The confining pressure is the pressure applied to the rock specimen during the laboratory test. It represents the pressure that the rock would experience in the field due to the weight of overlying rock or soil.

the mineralogy of rock, its porosity and density, and the confining pressure are three important factors that affect the compressive strength of intact rock material in laboratory testing.

To know more about Compressive strength visit:-

https://brainly.com/question/31102674

#SPJ11

1. "Clients engage many participants in the construction of a building project; many more are involved through sub-contracting and regulation." Discuss this statement and explain what techniques and/or mechanisms are typically introduced into contractual documents to deal with the contractual issues arising from the large number of diverse participants in the process.
Please note this question does not involve comparison of different contracting types. Your answer should principally be addressed with one type of contract or standard form in mind.
please attach the references

Answers

The construction project involves many stakeholders that include clients, contractors, sub-contractors, and regulators. This aspect of the construction process demands the need for several mechanisms and techniques to address the contractual issues that may arise in the process.

In the construction process, the client is the initiator of the project, and the main objective is to deliver the building project within the set time frame, budget, and quality specifications.  The design and build contract helps mitigate the contractual issues that may arise during the construction process by creating a collaborative environment that enhances teamwork.

The mechanism enables the participants to work together to solve any contractual issues and ensures that all parties comply with the contractual obligations. The use of the design and build contract and the NEC3 contract has been instrumental in addressing the contractual issues arising from the large number of diverse participants in the process.

These mechanisms promote a collaborative approach to problem-solving and risk management that ensures that all parties comply with the contractual obligations. The contractual framework creates a collaborative environment that encourages teamwork and enhances the overall quality of the project.

Therefore, the construction industry should embrace these mechanisms to enhance the construction process.

To know more about stakeholders visit:-

https://brainly.com/question/30241824

#SPJ11

A non vented logger records a pressure of 64.41 kPa while suspended in a piezometer at a depth of 16.85 m below TOC. which is 193.97 m AHD. A nearby barometric logger records 100.2 kPa Assuming p= 1001.7 kg/m³, what is the hydraulic head in the piezometer?

Answers

The hydraulic head in the piezometer is 177.12 m. Hydraulic head is defined as the height of the water above a given point of measurement. The hydraulic head is obtained by subtracting the height of the pressure transducer from the elevation of the water table.

Hydraulic Head, denoted as h, is given by the formula:

[tex]h = z + p/γ[/tex]where h = hydraulic head, z = height of pressure transducer above datum, p = pressure, and γ = unit weight of water.

When a non-vented logger records a pressure of 64.41 kPa while suspended in a piezometer at a depth of 16.85 m below TOC and a nearby barometric logger records 100.2 kPa,

we can determine the hydraulic head in the piezometer by using the formula above.

The unit weight of water (γ) is 1001.7 kg/m³.

[tex]h = z + p/γ= 193.97 - 16.85 + (100.2 - 64.41)/(1001.7)[/tex]= [tex]177.12 m.[/tex]

To know more about piezometer visit:-

https://brainly.com/question/14950670

#SPJ11

for credit card processing, stock exchanges, and airline reservations, data availability must be continuous. there are many other examples of mission critical applications. research online to find two other mission critical applications and explain why data availability must be continuous for these applications.

Answers

In both cases, continuous data availability is crucial for real-time decision-making, timely response, and maintaining the overall functioning and safety of the systems involved.

1. Emergency Medical Services (EMS):

- Continuous data availability is vital for delivering timely and effective care to patients.

- EMS providers rely on real-time access to critical patient information such as medical history, allergies, medications, and vital signs.

- Interruption in data availability could lead to delays in treatment or jeopardize patient safety.

- Continuous data availability ensures immediate access to accurate patient information, enabling informed decisions and timely interventions.

2. Power Grid Management:

- Power grid management requires continuous data availability for effective monitoring and control.

- Real-time data from sensors, smart meters, and control systems is essential for grid operators.

- Interruptions in data availability can lead to extended power outages and grid instability.

- Continuous data availability enables prompt detection and response to faults or outages, ensuring a stable and reliable power supply.

Learn more about Emergency Medical Services here:

https://brainly.com/question/17257100

#SPJ4

A thermostat control with dial markings from 0 to 200 is used to regulate the temperature of an oil bath. A calibration plot on logarithmic coordinates of the temperature (°F) versus the dial setting R is a straight line that passes through the points (R1= 10.0, T1 = 110.0 °F) and (R2=60.0, T2=250.0 °F).

a. In the equation T(°F) = ARb, what are the values of A and b?

b.Estimate the thermostat setting need to obtain a temperature of 340.0°F. R =

c. Estimate the thermostat setting needed to obtain a temperature of 120.0°C. R =

Answers

The values of A and b are approximately A = 55.13 and b = 0.692. The thermostat setting needed to obtain a temperature of 340.0°F is R = 73.31, and the thermostat setting needed to obtain a temperature of 120.0°C is R = 36.43.

a. To obtain the values of A and b, we can utilize the logarithmic form of the equation for a straight line, which is log y = log A + b log x. By rearranging it into the form y = mx + c, we have: log T(°F) = log A + b log R. Taking the antilog of both sides, we can express it as: T = A(R^b). Comparing this equation with T = ARb, we find A = 10^(log A) and b = log R/log T. Substituting the given values (R1,T1) = (10.0,110.0) and (R2,T2) = (60.0,250.0), we can calculate the values of A and b as A = 55.13 and b = 0.692.

b. To determine the thermostat setting needed to achieve a temperature of 340.0°F, we can use the equation T = ARb and substitute T = 340°F. Solving for R, we find R = (T/A)^(1/b) = (340/55.13)^(1/0.692) = 73.31.

c. Similarly, to find the thermostat setting required for a temperature of 120.0°C (248°F), we can use the equation T = ARb and substitute T = 120°C. Solving for R, we obtain R = (T/A)^(1/b) = (248/55.13)^(1/0.692) = 36.43.

Therefore, the thermostat setting needed to attain a temperature of 340.0°F is R = 73.31, and the thermostat setting needed to achieve a temperature of 120.0°C is R = 36.43.

Learn more about thermostat

https://brainly.com/question/32266604

#SPJ11

A beam is loaded with the following service loads: Moment due to Dead Load = 312 kN-m Moment due to Live Load = 339 kN-m Section: b-37 cm and d=52 cm. Material properties: f'c-30 MPa and fy=420 MPa Use rhomax = 0.019 for all calculations If required, compression reinforcement centroid is located 70mm from extreme compression face Calculate the the sum of the tension and compression reinforcements (if required) in mm² Use NSCP2015. Consider the displaced area of concrete. Answer in 2 decimal places

Answers

The question is about calculating the sum of the tension and compression reinforcements (if required) of a beam with the following specifications: Section: b-37 cm and d=52 cm. Moment due to Dead Load = 312 kN-m. Moment due to Live Load = 339 kN-m. Material properties: f'c-30 MPa and fy=420 MPa. Use rhomax = 0.019 for all calculations.

If required, compression reinforcement centroid is located 70mm from the extreme compression face. The answer is:To calculate the sum of the tension and compression reinforcements, we have to calculate the ultimate moment of resistance, Mu, of the beam first and check whether it is greater than or less than the given factored moment:

Dead Load Moment = 312 kN-m,Live Load Moment = 339 kN-mThe ultimate moment of resistance of the beam, Mu, is calculated as follows:First, we calculate the area of tension steel required: From the given data, rhomax = 0.019 We have to calculate the area of tension steel (As) first:

As = 0.019 × b × d = 0.019 × 37 × 52 = 37.076 mm²As per NSCP Table 7.5.1, the minimum As required for Mu is:Minimum As = 0.45 × fy/f's × b × d= 0.45 × 420/0.85 × 37 × 52 = 163.82 mm²Now, we have to calculate the area of compression steel (Asc) required:  From the given data, compression reinforcement centroid is located 70 mm from extreme compression face.

To know more about Material visit:

https://brainly.com/question/27403649

#SPJ11

Contract completion date has just lapsed. The Architect (A) did not issue the Certificate of Non- Completion right away. It is likely that the Contractor (C) may need another 10 weeks before substantial completion is possible.
In the last interim payment certification, A has in gross certified 70% of the contract sum of HK$210M with contract retention deducted at a maximum 10%. 2 weeks ago, C has submitted a new interim payment application at a value of total work done at 90% of the original scope of contract and a sum of HK$20,000,000 on contract variation. At the same time, C submitted a notice of substantial completion of the works inviting A for inspection
To C, all the variations were incurred from the Architect's instructed change in -
(a) curtain wall design from glass size width of 800 mm wide to 1000 mm wide, and
(b) extra 6 numbers of piles from the 30 piles originally outlined in the BD approved piling plan as part of the tender drawings.
The contract adopted the HKIA/HKIS/HKICM Standard Form of Building Contract 2006 (Without Quantities) on lump sum basis (the "Contract"). It includes a soil investigation report with was marked for reference.
Today, A (4th week after original contract completion date) issued an Interim Payment Certificate ("IP") with the followings:-
(i) (ii) Liquidated Ascertained Damage retention calculated at 4 weeks of delay; Work done at 80% on original scope; and
(iii) No variation claim.
A did not conducted completion inspection.
Provide your answers for the following question:-
(a) Assuming that you are C who wished to argue, among others, on the IP, prepare your claims with quotes on referenced clauses in the Contract.
(i) monetary claim, and(12%)
(ii) time claim.(12%)
(b)
Provide arguments and the likely defence of A to your proposed claims.(16%)

Answers

(a) Assuming that you are C who wished to argue, among others, on the IP, prepare your claims with quotes on referenced clauses in the Contract. (b) Provide arguments and the likely defence of A to your proposed claims.

(i) Monetary claim :C could argue that the certification of the Interim Payment Certificate issued by A is incomplete, inaccurate, or otherwise deficient. He has calculated that his work is worth[tex]HK$20,000,000[/tex], and he could cite clauses 30 and 31 of the Contract to back up his argument.

ii) Time claim :C may claim that he is entitled to an extension of time due to the Architect's changes to the curtain wall design and the piling plan. He may argue that this would take into account the impact of these modifications on his working time.

(i) Monetary claim: A could argue that the Interim Payment Certificate is correct and that the Contractor's work is worth no more than HK$16,800,000. Clause 30 of the Contract states that the quantity surveyor should make a decision on the value of the work done, and A has done so.

(ii) Time claim: A could argue that the modifications to the curtain wall design and piling plan had little impact on the Contractor's working time, and therefore, he is not entitled to an extension. Clause 23.2 of the Contract allows for time extensions only if the modifications cause a significant delay, and A could argue that this was not the case.

To know more about Monetary visit:-

https://brainly.com/question/28199887

#SPJ11

A dam was designed for a flow rate of 2500 cu-mecs. The dam must be modelled in an hydraulics laboratory to sort out the calibration of such dam (like to find out minor design details) Since it is a retaining structure, it should be modelled as a distorted. Consider H-scale 1:50, V- scale 1:30. What will be the required flows rate in l/s, be at the lab. What are the two components of the EIA and what is the role in planning a dam projects? Discuss NEMA. What is EMP and EA?

Answers

The dam was designed for a flow rate of 2500 cu-mecs. But, the dam needs to be modeled in an hydraulics laboratory to sort out the calibration of the dam. Since it is a retaining structure, it should be modeled as a distorted. Consider H-scale 1:50, V- scale 1:30.

The main purpose of EIA is to determine the potential impact of a proposed project on the environment and society. It is a formal study that analyzes and assesses the impact of a proposed project on the environment and social structure.

The organization's main objective is to ensure that environmental considerations are taken into account in the decision-making process. The key functions of NEMA include environmental impact assessment, environmental audit, environmental monitoring, and enforcement of environmental regulations. NEMA also has a mandate to coordinate environmental management activities with other stakeholders.

An Environmental Management Plan (EMP) is a document that outlines how a proposed project will manage its environmental impacts. It is an essential part of the environmental management process, and it provides guidelines for monitoring and managing environmental impacts during the project's construction and operation. The main goal of an EA is to identify potential environmental impacts and to suggest ways to mitigate them.

To know more about calibration visit:-

https://brainly.com/question/28325954

#SPJ11

1. Design a chlorine contact basin (serpentine) to disinfect 1 MGD flow and meet 4- log virus removal with a free chlorine residual of 0.1 mg/L (pH=7, Temp = 25C). Use a length:width ratio of approximately 20:1 and a depth of 4 to 6 feet.
2. Alter the design to achieve 3-log removal of Giardia cysts using free chlorine (still must treat 1 MGD, pH=7, T=25C). How would the design change if you used chlorine dioxide?
3. Design the disinfection system for an existing pipeline and storage tank as follows: the chlorine is added to the filter effluent in a 12-inch pipe that is 400 ft long and empties into a 2 MG storage tank. Flow rate is 2 MGD and you must achieve 4-log virus removal. Assume pH = 7, Temp = 20C and the tank is square with dimensions, L:W:H= 134:134:15ft You will select the chlorine residual and any internal modifications to the tank.

Answers

1) Volume = 4.5 liters

2) Volume required will be less .

Given,

Chlorine contact basin .

1)

Chlorine treatment chamber  or tanks (pre or post treatment) is open to atmosphere with dimensions of 220X11X1.83 meters.

The volume is equal to 1MGD assuming US gallon of 4.5 liters.

2)

The chlorine dioxide (gas) is harmful to working persons (ClO₂) and has to be contained in a chamber. The ClO₂  explosive and catches fire hence preserved in chilled water tanks at 5 degree celsius. This also acts as disinfectant but the design principles are different. The volume space is far less compared to conventional chlorination tanks and very effective as disinfectant. It also has no smell unlike chlorine.

Know more about serpentine,

https://brainly.com/question/22285332

#SPJ4

1) If you were asked to perform an excavation contract for oil pipeline project competitively with limited boring data, what type of contract would you want and why? Please explain briefly.
2) given a single person with a $96000 income, apply the standard deduction and tax rate in 2015, which of the following is closest to the tax this person should pay? Assume single filing status.
3) What is the main driver in petroleum projects, and why?

Answers

If I were asked to perform an excavation contract for an oil pipeline project competitively with limited boring data, I would choose a unit price contract. A unit price contract is a construction contract where the contractor bids on a fixed price per unit of work, such as per cubic meter of soil removed or per foot of pipeline installed.

The advantage of this type of contract is that it allows for flexibility in pricing and risk allocation. It is ideal for a situation where there is limited information on the scope of work or soil conditions because the owner is only paying for the actual amount of work performed.

This reduces the risk of unforeseen costs or changes in scope. The unit price contract also promotes efficiency because the contractor has an incentive to complete the work as quickly and efficiently as possible.

Given a single person with a $96000 income, applying the standard deduction and tax rate in 2015, the tax this person should pay would be $18,790.  The profitability of petroleum projects is largely dependent on the global market for oil and gas and the balance of supply and demand.

The companies that are successful in petroleum projects are those that can effectively manage costs, mitigate risks, and stay competitive in a dynamic and challenging market.

To know more about global market visit:-

https://brainly.com/question/31787182

#SPJ11

The helical spring has 10 turns of 20 mm diameter wire. If maximum shearing stress must not exceed 200 MPa and the elongation is 71.125mm. calculate the mean diameter of spring and the spring index(m) if the load is 3498.38N and G-83GPa

Answers

Given: Number of turns=10Diameter of wire=20mmMax shearing stress = 200 MP Elongation=71.125 mm Load = 3498.38 NG=83 G Pa To find: Mean diameter of spring and the spring index(m).

Formula Used: Total elongation of spring = (4FL)/(πd^3G)whereF = LoadL = Length of springd = Mean diameter of spring G = Modulus of rigidity of the material Spring index(m) = D/dwhere,D = Mean diameterd = Diameter of wire Calculation: Length of spring = Total length - Compression Length of spring = 20 - (10 x 20)Length of spring = -180mm

Total elongation of spring = 71.125 - (-180)Total elongation of spring = 251.125mm Substituting the given values in the formula[tex]:251.125 = (4 x 3498.38 x -180) / (πd^3 x 83 x 10^9)On solving the above equation, we get:d^3 = (4 x 3498.38 x 180 x 10^3) / (251.125 x π x 83 x 10^9)d^3 = 0.00131223d = 0.108 mm[/tex]Spring index(m) = D/dD = 20 mm Spring index(m) = 20/0.108Spring index(m) = 185.18As we know ,D = (d + D)/2Mean diameter of spring = 2D - d= 2 x 20 - 0.108Mean diameter of spring = 39.892 mm Therefore, the mean diameter of the spring is 39.892 mm and the spring index (m) is 185.18.

To know more about  spring visit:

brainly.com/question/30106794

#SPJ11

A steel rod is 3m long and 60mm diameter. An axial pull of 150kN is suddenly applied to the
rod. Calculate the instantaneous stress induced and also the instantaneous elongation produced in the
rod. Take E-200GN/mm

Answers

A steel rod is 3m long and has a diameter of 60mm. If an axial pull of 150kN is applied to the rod, The value of E is 200GN/mm.

Instantaneous stress induced:
The instantaneous stress induced in the steel rod can be calculated using the formula:[tex]σ = P/A[/tex], where σ is the stress, P is the axial force and A is the cross-sectional area of the rod. The cross-sectional area of the rod is given as:
[tex]A = π/4 * d² = π/4 * (60)² = 2827.43 mm²[/tex]
Thus, the instantaneous stress induced is:
[tex]σ = P/A = 150000/2827.43 ≈ 53.04 N/mm² or MPa[/tex]

Instantaneous elongation produced:
The instantaneous elongation produced in the steel rod can be calculated using the formula:[tex]δ = PL/AE[/tex], where δ is the elongation, P is the axial force, L is the length of the rod, A is the cross-sectional area of the rod, and E is the Young's modulus of elasticity for the material. Substituting the values:
[tex]δ = PL/AE = 150000*3000/(2827.43*200000) = 0.798 mm[/tex] (approx.)

Therefore, the instantaneous stress induced in the rod is 53.04 MPa, and the instantaneous elongation produced in the rod is 0.798 mm.

To know more about elongation visit:-

https://brainly.com/question/32416877

#SPJ11

After a re-evaluation of the duration of activity B, it has been provided the following data. Most likely duration = 10 Optimistic Duration = 16 Pessimistic Duration = 25 Using the three-point estimating technique the new duration of activity B is a. 7 b. 15 c. 17 d. 22

Answers

Three-point estimating technique: Three-point estimating technique is a method used in project management for calculating the estimates of the project management activity.

The three-point estimating technique is used in estimating the cost and duration of a project. Activity B can be defined as a task that must be completed within a specific time frame and assigned to a specific project member in the project plan.

The duration of Activity B has been reevaluated as follows: Most likely duration = 10Optimistic Duration = 16Pessimistic Duration = 25New duration of Activity B: We can use the three-point estimating technique to determine the new duration of Activity B as follows.

TO know more about estimating visit:

https://brainly.com/question/30870295

#SPJ11

Soft soil can be identified by various methods before and after conducting site investigation. Plan how to identify soft soil accurately during the desk study, site visit, field test, and laboratory test.

Answers

Soft soil can be identified by various methods before and after conducting a site investigation. Before a site investigation, a desk study should be done to determine the geology of the area. In the desk study, geological maps can be used to identify areas where soft soil is likely to occur.

Reports from previous investigations in the area should be studied to identify areas with soft soils. During a site visit, there are several ways of identifying soft soils.  if the soil is waterlogged or contains a lot of organic matter, it could also be an indication that the soil is soft.

Before conducting a field test, it is important to visually inspect the soil. Soil with a higher water content is more likely to be soft. After collecting soil samples from the site, laboratory tests can be conducted to determine the physical properties of the soil.

A direct shear test, for instance, is used to determine the shear strength of the soil. In summary, identifying soft soil accurately during the desk study, site visit, field test, and laboratory test is essential to ensure the stability of any structures built on the soil. It is important to carry out a thorough investigation to ensure that all necessary measures are taken to avoid any future problems.

To know more about geology visit:-

https://brainly.com/question/1047182

#SPJ11

Congratulations! You found employment working for an environmental engineering firm. Your company has been hired to conduct a slope stability analysis for a hillslope located in central California. The necessary observations made on the study slope are as follows:
Regolith cohesion = 1100 N/m²
Regolith thickness = 10 m
Density of regolith = 2200 kg/m³ Density of water = 1000 kg/m³
Slope angle on which regolith rests = 14 degrees Angle of internal friction = 15 degrees
Gravitational acceleration = 9.8 m/s²
The regolith is unsaturated.
There is a home situated at the top of the slope, about 20 m from the edge.

Answers

Given data: Regolith cohesion = 1100 N/m²Regolith thickness = 10 m Density of regolith = 2200 kg/m³Density of water = 1000 kg/m³Slope angle on which regolith rests = 14 degrees Angle of internal friction = 15 degrees Gravitational acceleration = 9.8 m/s²Regolith is unsaturated.

Home situated at the top of the slope, about 20 m from the edge .Slope stability analysis: It acts vertically downward and is given by: G=γHwhere γ is the density of the regolith and H is the thickness of the regolith. The gravitational force acting on the regolith is given by: G=2200×10×9.8=215600 N/m²Slope stability analysis: The safety factor (SF) is defined as the ratio of the resisting forces to the driving forces. The resisting forces are the shear strength of the regolith, while the driving forces are the gravitational force acting on the regolith. Therefore, the safety factor is given by: SF=S/G=1777.16/215600=0.0082The safety factor is less than 1, which implies that the slope is unstable and will fail.

Therefore, the slope stability analysis recommends stabilizing the slope. The stabilization methods that can be employed are:1. Reducing the slope angle by cutting the slope back.2. Building retaining walls to hold the slope in place.3. Using soil nails or anchors to reinforce the slope.4. Using vegetation to stabilize the slope. The stability of the home located at the top of the slope needs to be considered during the slope stabilization process. The stability analysis can be performed by considering the safety factor of the slope after stabilization.

To know more about   internal visit:

brainly.com/question/27004586

#SPJ11

What is the MINIMUM shank diameter permitted for screws used to anchor masonry veneer to steel backing?
1. 0.121 in.
2. 0.190 in.
3. 0.260 in.
4. 0.311 in.

Answers

The correct answer to the given question is option 2, which is "0.190 in."The shank diameter permitted for screws used to anchor masonry veneer to steel backing is 0.190 in.

Screws are frequently used to anchor masonry veneer to steel backing. The minimum shank diameter allowed for such screws is specified in the code. The shank diameter of the screw should be verified since masonry veneer can be used as a veneer over a variety of substrates. The screw should have a minimum shank diameter of 0.190 inches, as defined by the code. It's worth noting that shank diameters that aren't explicitly specified in the code may be utilized as long as they're equal in diameter or larger than the minimum shank diameter permitted by the code. The code also specifies the length and spacing of screws used to anchor masonry veneer to steel backing. Therefore, the correct answer to the given question is option 2, which is "0.190 in."The shank diameter permitted for screws used to anchor masonry veneer to steel backing is 0.190 in.

To learn more about shank, visit:

https://brainly.com/question/16931159

#SPJ11

Other Questions
You are a researcher studying the lifespan of a certain species of bacteria. From a previous study of the bacteria revealed a standard deviation of =4.8 hours. You would like to estimate the mean lifespan for this species of bacteria to be within a margin of error of 0.6 hours at a 98% level of confidence. What is minimum sample size should you gather to achieve a 0.6 hour margin of error? (If your answer is not a whole number, then increase answer up to next whole number.) 11= bacteria Describe and discuss the challenges a Spanish construction company specialising in designing and delivering sustainable energy power plants would need to consider when seeking to grow organically in Egypt. The company has no experience of operating in Egypt but has worked extensively in the United Arab Emirates. The annual turnover of the company in 2020 was 2 billion, employing 6,000 people across all their operating divisions. Question 1 A the very common feature of an organization is in it having multiple divisions, consisting of a head office and a number of separate operating divisions, a distinction that is made within a corporate strategy, business unit strategy and functional strategy.Required:A-Explain each of the corporate & business unit strategy .B-Explain the functional strategies by referring to each of the production, financial, marketing and human resource functions. (4 marks; 1 mark for each function)Question 2 Toyota Company was a pioneer in adopting & implementing the production control system known as the Just-In Time system.RequiredDiscuss the concept of the Just-In Time system What are the prerequisites or requirements for a successful implementation of (JIT)? Identify at least six advantages and 3 drawbacks of the (JIT) Explain how the JIT system benefited Toyota Explain how a fast-food restaurant can apply and benefit from a JIT system. In order to calculate Cost of Goods Sold under the periodic inventory system, a company must O A. identify the cost of goods available for sale and subtract ending inventory. O B. start with beginning Martin Corporation, the maker of a variety of rubber products, is in the midst of a business downturn and has many idle facilities. Nationwide Tire Company has approached Martin to produce 300,000 oversized tire tubes for $2.40 each. Martin predicts that its variable costs will be $2.60 each. Its fixed costs, which had been averaging $2.00 per unit on a variety of products, will now be spread over twice as much volume. The president commented, "Sure we will lose $.20 each on the variable costs, but we will gain $1 per unit by spreading our fixed costs over more units. Therefore, we should take the offer because it would gain us $.80 per unit." Martin currently has a volume of 300,000 units, sales of $1,200,000, variable costs of $780,000, and fixed costs of $600,000. Required: a. Compute the impact on operating profit if the special order is accepted. b. Based on your calculations, explain why you agree or do not agree with the president. c. Would it be beneficial for Martin to take a loss on this order if it desires to enter this market? Briefly discuss. manufacturer fills soda bottles. Periodically the company tests to see if there is a difference between the mean amounts of soda put in bottles of regular cola and diet cola. A random sample of 19 bottles of regular cola has a mean of 500.4mL of soda with a standard deviation of 3.5mL. A random sample of 17 bottles of diet cola has a mean of 502.9mL of soda with a standard deviation of 2.8mL. Test the claim that there is a difference between the mean fill levels for the two types of soda using a 0.05 level of significance. Assume that both populations are approximately normal and that the population variances are not equal since different machines are used to fill bottles of regular cola and diet cola. Let bottles of regular cola be Population 1 and let bottles of diet cola be Population 2.Step 2 of 3 : Compute the value of the test statistic. Round your answer to three decimal places Capital Investment, Discount Rates, Intangible and Indirect Benefits, Time Horizon, Contemporary Manufacturing Environment Mallette Manufacturing, Inc., produces washing machines, dryers, and dishwashers. Because of increasing competition, Mallette is considering investing in an automated manufacturing system. Since competition is most keen for dishwashers, the production process for this line has been selected for initial evaluation. In 2019, the top nine automobile manufacturers controlled 91.8 percent of the market. What kind of competition is this? a. Perfect competition b. Monopolistic competition c. Monopoly d. Oligopoly e. Natural monopoly A Moving to another question will save this response Question 12 Which form of marketing involves engaging directly with carefully targeted individual consumers and customer communities to both obman and customer relationships? Oa Niche marketing Ob Oc O d. Advertising - Public Relations Sales promotion O. Direct marketing Moving to another question will save this response. Question 12 of 24 MANAGING INVENTORIES AND DEBTORS Nellie Ngubane recently became a B. Com graduate, specialising in working capital management. As a result of her excellent academic record she was recruited by a recently established private company. The company is in the retail sector and specialises in the sale of designer bathtubs. Plans are in place to establish branches at other major cities. As an upstart company it was unable to afford to employ separate managers for each of the functional areas. So Nellie was employed as the manager who was responsible for all aspects pertaining to the inventories and debtors of the company. When she started her job at the company, she discovered the following: The company was seeking to expand rapidly and customer satisfaction was the priority. As a result, cred it was granted to as many of the applicants as possible and adequate inventories were maintained in order to prevent stock-outs from occurring. The average monthly demand for the bathtubs was 400. The selling price of the bathtubs was R7 500 and a mark-up of 50% on cost was used. All the sales are on credit and the credit terms are 60 days. Collection costs of approximately R50 per unit sold were incurred. The annual holding cost of a bathtub was 1% of the cost of the item. The cost of placing an order for bathtubs was R18.75. The cost of capital was 12%. Nellie has proposed the following to the CEO: The company should take advantage of a 4% discount from the manufacturer by ordering 100 bathtubs each time instead of ordering the EOQ. 2) Bluesy Tuesday invested $500,000 cash in available-for-sale marketable securities in early November. On December 31, the quoted market price for these securities is $552,000. Which of the following statements is correct? A) Bluesy's December income statement includes a $52,000 gain on investments. B) If Bluesy sells these investments on January 2 for $589,000, it will report a loss of $37,000. C) Bluesy's December 31 balance sheet reports marketable securities at $500,000 and an unrealized holding gain on investments of $52,000. D) Bluesy's December 31 balance sheet reports marketable securities at $552,000 and an unrealized holding gain on investments of $52,000. 3) On December 30, 2022, Blando Inc. sold available for sale marketable securities costing $800,000 for $850,000 cash. The securities were purchased on January 2, 2019 and the market value of the securities on December 31, 2020 and December 31, 2021 was $820,000 and $780,000, respectively. How much gain or loss will Blando report in its income statement for the year ending December 31, 2022? A) A $50,000 gain. B) A $20,000 loss. C) A $60,000 gain. D)A $80,000 gain An adult Latino male patient that has been admitted to the emergency room has the following recorded on their electronic medical chart: 100.7 oral temperature (normal = 99 to 97), fever, headache, swollen lymph nodes, tachycardia (increased heart rate), and a white blood cell count of 13,000 per microliter (normal = 4, 500 to 11, 000 per microliter). What is wrong with the patient? What is the possible cause of the symptoms that the patient is experiencing? Explain your answer using the information recorded on the medical chart, etc. Why is it important for a Geographer to understand and apply the scientific method to geographic events and processes?Compare/Contrast Daylight and Standard Time, as well as, the International Date Line. Also, what are the exact dates for Daylight and Standard Time changes for 2022? Finally, what is the name of the time zone you are currently located and how many hours away (+ or -) from Greenwich Mean Time (GMT)?What is GIS and how can this tool assist Geographers to understand the planet's processes? Suppose that there are two students, John and Mary. John is assigned to be in the treatment group and Mary in the control group. The treatment is a tutoring program, where John will work with a one-on-one tutor for three hours each week. Mary receives no extra tutoring. YM refers to the Mary's test scores and YJ to John's, T is a dummy variable that takes on the value 1 if the person is in the treatment group and 0 if the person is in the control group. In this example, which of the following states of the world are directly observed? (Select all that apply.) a.YMT=0 b.YMT=1 c.YJT=0d.YJT=1 Case Study Change ManagementIn a recent leadership team meeting. George Kasey, the CEO of Kasey Food, a Canadian chain of meat production, raised concerns that business is slow due to the lack of focus on innovation.While Kasey Food had been very successful in marketing their products in the past, it is currently seeing a decline in sales. George K. had previously challenged his leadership team to come up with innovative ideas to drive continued success, but results have not yet improved. The chain suffers especially because of the unexpected rise in demand for vegan food. Therefore George K. started looking for a potential business partner to expedite the company's involvement in vegan products.In addition to the possibility of acquiring knowledge and skills around vegan nutrition, Kasey Food is evaluating a merger with an innovative company that is based in Southern America. This would also provide an opportunity to (at least partially) transfer production to save on costs and to secure access to the continent's market after Pandemic. Concerning this possible merger, the business development manager has already started looking into potential legal issues.As a next step, the business development manager worked on an analysis to identify where the company currently stands and what it wants to achieve in a new combined post- merger organization. Based on the findings, a decision was made to limit potential merger partners to companies that have similar target customers, i.e. a focus on retailers and restaurants, to build a sustainable combined business model.However, the company cultures of potential partners investigated could not be more different. Kasey Food's employees benefit from long-term employment, working in a highly process-driven and structured environment. In contrast, the staff of companies that are rising stars in the vegan food space are usually very young teams, living in a company culture that is driven by flat hierarchies, pragmatism, and fast pace.While George K. is close to deciding regarding the merger, managers are reporting that morale amongst workers is declining. Employees are sensing upcoming changes but have not been informed officially. Therefore, many rumors exist, and a general anxiety is building up. George K. has now requested his Chief Operating Officer to develop a communication plan within the next seven days.Answer these questions based on the case study1. Identify the challenges faced by Kasey Food and prepare a diagnosis. You should choose the best tools and factors for change diagnosis and make explicit reference to them in your answer. The current salvage value of a piece of machinery is $50,000. Salvage value exactly one year from now is $40,000. Operating cost for the upcoming year is $15,000. Annual effective interest rate is 10%. What is the opportunity cost of operating this machine one more year from today? Julie has a low credit rating, plus she was furloughed from her job 2 months ago. She has a new job starting next week and expects a salary to start again in a couple of weeks. Since she is a little short on money to pay her rent, she decided to borrow $100 from a loan company, which will charge her only $10 interest if the $110 is paid no morethan 1 week after the loan is made. What are the:(Draw the Cashflow) (a)nominal annual and(b)effective annual interest rates that she will pay on this loan? - 1 Find the exact value of tan sin 4 010 B Undefined X 0/0 ? franks needs to drive 204 mi from city a to city b. after having driven x mi, the distance remaining r(x) (in mi) is given by r(x) =204-xA)evaluate r (98) and interpret the meaning.B) determine the distance remaining after 143 miA) r(98)=? thus, after driving ? mi, frank still has ? mi remaining. Banks need to know their cost of capital and cost of funds.' Evaluate this statement and the methods used to calculate the cost of funds.