Answer the question

Answer The Question

Answers

Answer 1

Answer: 1.5 miles per hour, 1 hour per 1.5 miles


Related Questions

Employers in the United States allocate n fewer vacation days than the 25 days given by the average Japanese employer. Write an expression to show the number of vacation days given to the U.S. workers.

Answers

Answer:

gsugaqsgsuguwsqsw

Step-by-step explanation:

wshwsbgshswswswsw f word you

what's the constant proportionality of y=1/2x​

Answers

Answer:

k=1/2

Step-by-step explanation:

A direct variation equation has the form

y=kx ← k is the constant variationy = 1/2x is in this form thus is a direct variation equation with k=1/2

a 300° sector of a circle of raduis 8cm bent to from a cone .Find the radius of this cone and its vertical angle​

Answers

Answer:the sector is 280°

Step-by-step explanation:

Simplify the expression:
-29 - 1 - 4 - 89

Answers

Answer:

-123

Step-by-step explanation:

Answer:

-123

Step-by-step explanation:

-(29+1+4+89)

-(30+4+89)

-(34+89)

-123

hope this helps good luck at school :))

the difference between the two roots of the equation x^2-5x c is 0.25. find c

Answers

Answer:

x² - 5x + c = 0

x = (5 + √(25 - 4c))/2

difference of roots = √(25 - 4c) = 1/4

25 - 4c = 1/16

-4c = -399/16

c = 399/64

View Policies Current Attempt in Progress Using the information provided in the table, the network diagram and the project completion time = 26 weeks, calculate the minimum time for completing the pro

Answers

The minimum time for completing the project, based on the critical path analysis, is 18 weeks. The critical path, which consists of activities with zero slack time, includes activities A, B, C, F, G, and H. By summing up the durations of these critical activities, we find that the minimum time for completing the project is 18 weeks.


To calculate the minimum time for completing the project, we need to identify the critical path, which consists of activities with zero slack time. Here are the step-by-step calculations:

1. Assign forward and backward pass values:

  Start by assigning the project start time as Early Start (ES) = 0 for Activity A. Then, calculate the Early Finish (EF) for each activity by adding the duration to the ES. The backward pass starts from the project completion time, which is the Late Finish (LF) for Activity I, initially set at 26 weeks. Calculate the Late Start (LS) for each activity by subtracting the duration from the LF.

  Activity A: ES = 0, EF = ES + 4 = 4, LS = LF - 4 = 26 - 4 = 22, LF = 26

  Activity B: ES = 4, EF = ES + 3 = 4 + 3 = 7, LS = LF - 3 = 26 - 3 = 23, LF = 26

  Activity C: ES = 7, EF = ES + 2 = 7 + 2 = 9, LS = LF - 2 = 26 - 2 = 24, LF = 26

  Activity D: ES = 7, EF = ES + 6 = 7 + 6 = 13, LS = LF - 6 = 26 - 6 = 20, LF = 26

  Activity E: ES = 13, EF = ES + 5 = 13 + 5 = 18, LS = LF - 5 = 26 - 5 = 21, LF = 26

  Activity F: ES = 13, EF = ES + 4 = 13 + 4 = 17, LS = LF - 4 = 26 - 4 = 22, LF = 26

  Activity G: ES = 18, EF = ES + 2 = 18 + 2 = 20, LS = LF - 2 = 26 - 2 = 24, LF = 26

  Activity H: ES = 20, EF = ES + 3 = 20 + 3 = 23, LS = LF - 3 = 26 - 3 = 23, LF = 26

  Activity I: ES = 9, EF = ES + 5 = 9 + 5 = 14, LS = LF - 5 = 26 - 5 = 21, LF = 26

2. Calculate slack time:

  Slack time (ST) can be calculated by subtracting the EF from the LS or the ES from the LF for each activity.

  Activity A: ST = LS - EF = 22 - 4 = 18

  Activity B: ST = LS - EF = 23 - 7 = 16

  Activity C: ST = LS - EF = 24 - 9 = 15

  Activity D: ST = LS - EF = 20 - 13 = 7

  Activity E: ST = LS - EF = 21 - 18 = 3

  Activity F: ST = LS - EF = 22 - 17 = 5

  Activity G: ST = LS - EF = 24 - 20 = 4

  Activity H: ST = LS - EF = 23 - 23 = 0

  Activity I: ST = LS - EF = 21 - 14 = 7

3. Identify the critical path:

  The critical path consists of activities with zero slack time. In this case, the critical path includes activities A, B, C, F, G, and H.

4. Calculate the minimum project completion time:

  Sum up the durations of the activities on the critical path to find the minimum time for completing the project.

 Minimum Time = Duration of Activity A + Duration of Activity B + Duration of Activity C + Duration of Activity F + Duration of Activity G + Duration of Activity H

              = 4 + 3 + 2 + 4 + 2 + 3

              = 18 weeks

Therefore, the minimum time for completing the project is 18 weeks.

To know more about critical path analysis, refer here:

https://brainly.com/question/30869744#

#SPJ11

At the movies your ticket costs 12 dollars. Each item at the concession stand cost 4 dollars a piece. What does f(2)=20 mean?

Answers

Answer: F(2)=20 means the total cost or the amount if money you spent at the movies after buying a ticket and buying 2 items at the concession stand.

Explanation: One ticket is $12 and if each item is $4, then in order to get to a total of $20, then you would need 2 items, since 2 x $4 = $8, and that plus $12 is $20.

I hope this helps!

James and Amanda are selling cheesecakes for a school fundraiser. Customers can buy pecan cheesecakes and chocolate marble cheesecakes. James sold 12 pecan cheesecakes and 1 chocolate marble cheesecake for a total of $157. Amanda sold 3 pecan cheesecakes and 5 chocolate marble cheesecakes for a total of $101. What is the cost each of one pecan cheesecake and one chocolate marble cheesecake?

Answers

Answer:

The cost of one pecan cheesecake is $12 and

the cost of 1 chocolate marble cheesecake is 13$

Step-by-step explanation:

Let the cost of one pecan cheesecake be x

And the cost of one chocolate marble cheesecake be y

Now, James sold 12 pecan cheesecakes and 1 chocolate marble cheesecake for $157, we represent this as,

12x + y = 157 (i)

And, Amanda sold 3 pecan cheesecakes and 5 chocolate marble cheesecake for $101, we represent this as,

3x + 5y = 101  (ii)

now, we just need to solve these two equations to get the amounts,

since 12x + y = 157

y = 157 - 12x

putting value of y in (ii)

3x + 5(157-12x) = 101

3x +785 - 60x = 101

-57x + 628 = 101

-57x = 101 - 785

-57x = -684

multiplying by -1 on both sides,

57x = 684

x = 684/57

x = 12

Now, finding y using, y = 157 - 12x

since x = 12,

y = 157 - (12)(12)

y = 157 - 144

y = 13

So, the cost of one pecan cheesecake is $12 and the cost of 1 chocolate marble cheesecake is 13$

TIME REMAININ
57:14
1
2
3
4
5
What is the equation of the line passing through the points (2, -1) and (5, -10) in slope-intercept form?
EEEE
O y=-3x-5
O y=-3x+5
O y = 3x-5
O y=3x+5

Answers

Answer:

-3×+5

Step-by-step explanation:

y=mx+b

m= y2-y1÷x2-x1

= -10+1÷5-2

= -9÷3

= -3

now,

y= -3×+b

-10 = -3(5)+b

-10 = -15+b

-10+15 = b

b= 5

therefore, y= -3×+5

The equation of the line passing through the points (2, -1) and (5, -10) in slope-intercept form is y= -3x+ 5.

What is Slope?

A line's slope is determined by how its y coordinate changes in relation to how its x coordinate changes. y and x are the net changes in the y and x coordinates, respectively. Therefore, it is possible to write the

change in y coordinate with respect to the change in x coordinate as,

m = Δy/Δx where, m is the slope

We have the points as (5, -10) and (2, -1).

So, the slope of line

slope = (-1 + 10) / (2 -5)

slope = 9/ (-3)

Slope= -3

Now, using the slope intercept form

y= mx+ b

y= -3x + b

and, the line passes through (2, -1)

-1 = -3(2) + b

-1 + 6 = b

b= 5

Then, the equation of line is

y= -3x + 5

Learn more about Slope here:

https://brainly.com/question/3605446

#SPJ7

What is the value of x?

Answers

Answer:

x = 70

Step-by-step explanation:

The angles are same side interior angles and when the lines are parallel same side interior angles are supplementary

45+ (2x-5) = 180

Combine like terms

2x +40 = 180

Subtract 40 from each side

2x+40-40 =180-40

2x = 140

Divide by 2

2x/2 = 140/2

x = 70

x = 70

City A has a travel demand function q=3.0×106−4000t, and road performance function t1​=30+6×10−6q, where t is in minutes. There is a proposal to expand the road such that the road performance function will become t2​=20+3×10−6q, with a construction cost of $9.6×107 Q9.1: Given that the value of time is $1.5 per minute, justify the proposal. Q9.2: To what value of the construction cost would the proposal become justified?

Answers

Q9.1: To justify the proposal, we need to compare the benefits of the road expansion (in terms of reduced travel time) with its costs. The value of time represents the monetary value individuals place on their time spent traveling. In this case, the value of time is $1.5 per minute.

First, let's calculate the reduction in travel time resulting from the road expansion. We compare the two road performance functions: t1​ = 30 + 6×10−6q and t2​ = 20 + 3×10−6q. By subtracting t2​ from t1​, we can determine the time savings: Δt = t1​ - t2​ = (30 + 6×10−6q) - (20 + 3×10−6q)    = 10 + 3×10−6q Next, we multiply the time savings by the number of trips (q) to obtain the total time savings: Total Time Savings = Δt × q = (10 + 3×10−6q) × q Now, we can determine the monetary value of the time savings by multiplying the total time savings by the value of time ($1.5 per minute): Monetary Value of Time Savings = Total Time Savings × Value of Time                             

= (10 + 3×10−6q) × q × $1.5  If the monetary value of the time savings exceeds the construction cost of $9.6×107, then the proposal is justified. Q9.2: To determine the construction cost at which the proposal becomes justified, we set the monetary value of the time savings equal to the construction cost and solve for q: (10 + 3×10−6q) × q × $1.5 = $9.6×107 By solving this equation for q, we can find the corresponding construction cost at which the proposal becomes justified.

Learn more about total time savings here: brainly.com/question/33195786

#SPJ11

Question 3; (5+2+5 Marks) Let Sw ${[ H8 H² H[]} i) Show that S is linearly independent. ii) Deduce that S is a basis for Maz iii) Express A as a linear combination of the vectors in S and find (4)s, where A = 24) -15

Answers

Express a vector A = [24, -15] as a linear combination of vectors in S, we solve the system of equations formed by equating A to the linear combination of S's vectors and find the coefficients.

i) To show that S = {[8, 2, 5], [H, H², H³]} is linearly independent, we set up the equation:

a * [8, 2, 5] + b * [H, H², H³] = [0, 0, 0]

Expanding this equation gives us the following system of equations:

8a + bH = 0

2a + bH² = 0

5a + bH³ = 0

To prove that S is linearly independent, we need to show that the only solution to this system is a = b = 0. Solving these equations will confirm the linear independence of S.

ii) Since S is linearly independent and contains two vectors, it forms a basis for a two-dimensional space, which we'll denote as Maz.

iii) To express vector A = [24, -15] as a linear combination of the vectors in S, we set up the equation:

[24, -15] = c * [8, 2, 5] + d * [H, H², H³]

Expanding this equation gives us the following system of equations:

8c + dH = 24

2c + dH² = -15

5c + dH³ = 0

By solving this system, we find the coefficients c and d that represent the linear combination of vectors in S that equals A.

Finally, substituting the values of c and d, we obtain the vector (4)s.

Learn more about coefficients here:

https://brainly.com/question/13431100

#SPJ11

The Empire State Building is 1250 feet tall. If an object is thrown upward from the top of the building at an initial velocity of 38 feet per second, its height s seconds after it is thrown is given by the function h(s)=16s^2+38s+1250.
. How long will it take for the ball to hit the ground?

Answers

s = (-38 ± √(-6556)) / 32

Since the term inside the square root is negative, the equation has no real solutions. This means that the ball will not hit the ground.

To determine how long it will take for the ball to hit the ground, we need to find the value of s when the height h(s) equals zero. In other words, we need to solve the equation:

16s^2 + 38s + 1250 = 0

We can use the quadratic formula to solve this equation. The quadratic formula states that for an equation in the form of ax^2 + bx + c = 0, the solutions for x are given by:

x = (-b ± √(b^2 - 4ac)) / (2a)

For our equation, a = 16, b = 38, and c = 1250. Plugging these values into the quadratic formula, we have:

s = (-38 ± √(38^2 - 4(16)(1250))) / (2(16))

Simplifying further, we get:

s = (-38 ± √(1444 - 8000)) / 32

s = (-38 ± √(-6556)) / 32

Since the term inside the square root is negative, the equation has no real solutions. This means that the ball will not hit the ground.

This result does not reflect reality. In reality, the ball would eventually hit the ground due to factors such as air resistance. The given equation does not take these factors into account.

for such more question on equation

https://brainly.com/question/17145398

#SPJ8

describe the reflective properties of these conic sections: parabola ellipse hyperbola

Answers

The reflective properties of conic sections can be exploited in various applications, such as focusing light or radio waves, enhancing signal reception, and designing optical systems. Each conic section exhibits unique reflective characteristics based on the arrangement of its foci and the shape of the curve.

Let's discuss the reflective properties of the three conic sections: parabola, ellipse, and hyperbola.

Parabola:

Reflective Property: A parabola has a single focus point, located either above or below the vertex. Any ray of light parallel to the axis of symmetry of the parabola will reflect off the curve and pass through the focus point.

Application: This property of the parabola makes it useful in designing reflective surfaces, such as satellite dishes or car headlights, where incoming parallel light rays are focused at a single point.

Ellipse:

Reflective Property: An ellipse has two foci, located at the two foci points on the major axis. When a ray of light enters the ellipse, it reflects off the inner surface of the curve, obeying the law of reflection. The angle of incidence is equal to the angle of reflection.

Application: The reflective property of the ellipse is utilized in applications such as astronomy, where elliptical mirrors are used in telescopes to focus light from distant celestial objects onto a focal point.

Hyperbola:

Reflective Property: A hyperbola has two foci, one on each branch of the curve. When a ray of light enters one branch of the hyperbola, it reflects off the inner surface of the curve, obeying the law of reflection. The angle of incidence is equal to the angle of reflection.

Application: The reflective property of the hyperbola finds applications in antenna design, specifically in satellite dishes and radio telescopes. The hyperbolic shape allows incoming waves to be focused or directed towards a specific point or receiver.

for such more question on reflective properties

https://brainly.com/question/29667212

#SPJ8

The side lengths of different triangles are given. Which triangle is a right triangle?
A. 6, 7, 13
B. V21, 99, 11
C. 10, 60, 61
D. ✓35, 14,7

Answers

Answer:

D

Step-by-step explanation:

solve 7+3(2g-6)= -29

Answers

Answer:

g=-3

Step-by-step explanation:

7+3(2g-6)=-29

7+6g-18=-29

6g=-29+18-7

6g=-18

g=-3

I think this is the right answer :D hope this helps ;)

Answer:

g = -3

Step-by-step explanation:

[tex]7+3(2g-6)= -29\\\\\mathrm{Subtract\:}7\mathrm{\:from\:both\:sides}\\\\7+3\left(2g-6\right)-7=-29-7\\\\Simplify\\\\3\left(2g-6\right)=-36\\\\\mathrm{Divide\:both\:sides\:by\:}3\\\\\frac{3\left(2g-6\right)}{3}=\frac{-36}{3}\\\\Simplify\\\\2g-6=-12\\\\\mathrm{Add\:}6\mathrm{\:to\:both\:sides}\\\\2g-6+6=-12+6\\\\Simplify\\\\2g =-6\\\\\mathrm{Divide\:both\:sides\:by\:}2\\\\\frac{2g}{2}=\frac{-6}{2}\\\\Simplify\\\\g =-3[/tex]

WILL GIVE BRAINLIEST! - Please check the attached picture, please answer thoroughly!

Answers

The fencing that will be required for the rectangular plot is: 162 m

How to find the perimeter of the rectangle?

The formula to find the perimeter of a rectangle is:

Perimeter = 2(Length + Width)

Now, we are told that each of the three rectangular plots measure 20m by 11m and as such, if we have 3 meters between each plot and also the boundary of the plot, then we can say that:

Length of Plot = 3 + 11 + 3 + 11 + 3 + 11 + 3 = 45 m

Width of plot = 20 + 3 + 3 = 26 m

Thus:

Fencing required = 2(45 + 36)

Fencing required = 2 * 81

Fencing required =  162 m

Read more about Rectangle perimeter at: https://brainly.com/question/24571594

#SPJ1

Becky and Barbara are shopping for clothes. Becky bought dresses that cost $14.50 and $20 and a pair of flip-flops for $8.25. Barbara bought a blouse for $8.25, a skirt for $20 and a pair of jeans for $14.50. How much did the two women spend together?

Answers

Answer:

$85.50 dollars

Step-by-step explanation:

Becky bought a $14.50 and $20 dress, and a $8.25 pair of flipflops. That is $42.75 . Barbara bought differernt things but still spent the same amount of $42.75 . So if you add those up, it would be $85.50 that they have spent together. Hope this helps :)

Help Very Much Needed !Solve For X In The Diagram

Answers

Answer:

x = 10

Step-by-step explanation

The exterior angle = the sum of the 2 interior angles (which is the other way to solve the other problem you just posted.)

-10 + 14x = 60 + 7x            Add 10 to both sides

-10+10+14x =60+10+7x     Combine

14x = 70 + 7x                     Subtract 7x from both sides

14x-7x = 70+7x-7x             Combine

7x = 70                              Divide by 7

7x/7 = 70/7

x = 10

Use the method for solving homogeneous equations to solve the following differential equation. Dx/dt = 4x² + 9t √6²+x² / 4tx
Ignoring lost solutions, if any, an implicit solution in the form F(t,x) = C is ___ =C, where C is an arbitrary constant. (Type an expression using x and t as the variables.)

Answers

The implicit solution to the given differential equation Dx/dt = 4x² + (9t/√(6²+x²)) / (4tx) using the method for solving homogeneous equations is F(t,x) = C, where C is an arbitrary constant.

To solve the given differential equation, we can separate the variables and integrate both sides. Rearranging the equation, we have:

(4tx) Dx = (4x² + (9t/√(6²+x²))) dt. Next, we integrate both sides. Integrating the left side with respect to x and the right side with respect to t, we get:

∫(4tx) Dx = ∫(4x² + (9t/√(6²+x²))) dt. Integrating both sides will result in a function F(t,x) on the left side and the integral on the right side. Since we are looking for an implicit solution in the form F(t,x) = C, we can write the equation as:

F(t,x) = C. cccThis represents the general solution to the given differential equation, where C is an arbitrary constant. The specific form of the function F(t,x) will depend on the integration process and the initial conditions, if provided.

Learn more about equations here:

https://brainly.com/question/29538993

#SPJ11


The patient's recovery time from a particular surgical procedure is normally distributed with a mean of 7 days and a standard deviation of 7.92 days. What is the probability that it will take more than 11 day to a randomly selected patient to recover from the surgical procedure? QUestion 7 The patient's recovery time from a particular surgical procedure is normally distributed with a mean of 20 days and a standard deviation of 2.24 days. Let X - is the number of days a randomly selected patient needs to recover from the surgical procedure. What is the upper bound of the 90% confidence interval of X ? QUESTION 8 The time needed to find a parking space is normally distributed with a mean of 15 minutes and a standard deviation of 4.89 minutes. 90% of the time, it takes more than how many minutes to find a parking space?

Answers

The upper bound of the 90% confidence interval for the recovery time is approximately 23.696 days.

It takes more than approximately 21.257 minutes to find a parking space 90% of the time.

To find the probability that it will take more than 11 days to recover from the surgical procedure, we need to calculate the area under the normal distribution curve to the right of 11 days.

Mean (μ) = 7 days

Standard deviation (σ) = 7.92 days

We can standardize the value of 11 days using the z-score formula:

z = (x - μ) / σ

z = (11 - 7) / 7.92

z = 0.506

Using a standard normal distribution table or a calculator, we can find the probability corresponding to the z-score of 0.506. The probability is approximately 0.3051.

Therefore, the probability that it will take more than 11 days to recover is approximately 0.3051 or 30.51%.

Question 8:

To find the upper bound of the 90% confidence interval for the number of days needed to recover from the surgical procedure, we need to calculate the z-score corresponding to the desired confidence level and then find the corresponding value using the standard deviation.

Given:

Mean (μ) = 20 days

Standard deviation (σ) = 2.24 days

For a 90% confidence interval, the z-score corresponding to the upper tail probability of 0.10 (1 - 0.90) is approximately 1.645.

Using the formula for the upper bound of the confidence interval:

Upper bound = μ + (z * σ)

Upper bound = 20 + (1.645 * 2.24)

Upper bound ≈ 23.696

Therefore, the upper bound of the 90% confidence interval for the recovery time is approximately 23.696 days.

Question 9:

To find the time it takes more than 90% of the time to find a parking space, we need to calculate the z-score corresponding to the desired upper tail probability and then find the corresponding value using the standard deviation.

Mean (μ) = 15 minutes

Standard deviation (σ) = 4.89 minutes

For a probability of 90%, the upper tail probability is 1 - 0.90 = 0.10.

Using a standard normal distribution table or a calculator, we can find the z-score corresponding to the upper tail probability of 0.10, which is approximately 1.282.

Using the formula for the upper bound:

Upper bound = μ + (z * σ)

Upper bound = 15 + (1.282 * 4.89)

Upper bound ≈ 21.257

Therefore, it takes more than approximately 21.257 minutes to find a parking space 90% of the time.

Learn more about approximately from

https://brainly.com/question/27894163

#SPJ11

Simplify 15-12\4 - -21+9/8

Answers

Answer:

= -1031/8

Step-by-step explanation:

Hope I get brainliest

92
Is the polynomial a monomial, binomial, or trinomial? Choose the correct type of polynomial.

Binomial

Trinomial

Monomial

Answers

the correct one is monomial

the sum of two numbers is 75 . one is five more than 6 times the other number. what are the two numbers

Answers

Step-by-step explanation:

Let the two numbers be X and Y respectively.

We know that :

(a) X = 6Y + 5

(b) X + Y = 75

7Y + 5 = 75

X = 65

Y = 10

Answer:

y= 10         x = 65

Step-by-step explanation

did the same assignment lol

- mark me brainliest !

The following three points are the locations of important facilities in a transportation network: (26,16), (51,59), and (36,41). The coordinates are in miles. a. Calculate the Euclidean distances (in miles) between each of the three pairs of facilties. (Enter your responses rounded to wo decimal places.) dAB​= miles; dBC​= miles; dAC​= miles. b. Calculate these distances using rectlinear distances. (Enter your responses as integers.) dAB​= miles; dBC​= miles, dAC​= miles.

Answers

a. To calculate the Euclidean distances between the three pairs of facilities, we use the formula:

d = sqrt((x2 - x1)^2 + (y2 - y1)^2)

where (x1, y1) and (x2, y2) are the coordinates of the two points. Calculating the Euclidean distances:

dAB = sqrt((51 - 26)^2 + (59 - 16)^2) ≈ 47.39 miles

dBC = sqrt((36 - 51)^2 + (41 - 59)^2) ≈ 23.53 miles

dAC = sqrt((36 - 26)^2 + (41 - 16)^2) ≈ 25.00 miles

b. To calculate the rectilinear distances, we use the formula:

d = |x2 - x1| + |y2 - y1|

Calculating the rectilinear distances:

dAB = |51 - 26| + |59 - 16| = 25 + 43 = 68 miles

dBC = |36 - 51| + |41 - 59| = 15 + 18 = 33 miles

dAC = |36 - 26| + |41 - 16| = 10 + 25 = 35 miles

Therefore, the Euclidean distances are approximately dAB = 47.39 miles, dBC = 23.53 miles, and dAC = 25.00 miles. The rectilinear distances are dAB = 68 miles, dBC = 33 miles, and dAC = 35 miles.

Learn more about the Euclidean here: brainly.com/question/31485782

#SPJ11

How many meatballs do frank need to make if there are 20 adults and 8 children the equation is m=4a+2c

Answers

The equation is 4 meatballs for every adult and 3 for every child. Replace a and c and solve:

M = 4(20) + 2(8)

M = 80 + 16

M = 96

They need 96 meatballs.

5. ( 3 points) Assume you are located a BFS for some Linear Programming problem with a minimization objective. If the reduced cost of all non-basic variables is strictly ≥0, does this mean your current BFS is optimal? Please explain your answer. 9. ( 3 points) If you are using the Big M method and you use k artificial variables to find an initial basic feasible solution (BFS), can it ever take more than k pivots before you find a "real" basic feasible solution ("real" meaning a BFS that only includes variables in the original problem)? Please explain your answer.

Answers

It is indeed possible for it to take more than k pivots to find a "real" BFS when using the Big M method, where k is the number of artificial variables introduced.

If the reduced cost of all non-basic variables is strictly ≥0, it does not necessarily mean that the current basic feasible solution (BFS) is optimal. The reduced cost of a variable represents the amount by which the objective function value would improve if that variable were included in the current BFS. When the reduced cost is ≥0 for all non-basic variables, it indicates that there is no incentive to include any of those variables in the current BFS as they would not contribute to improving the objective function.

However, it is still possible that the current BFS is not optimal. There could be other feasible solutions that have a lower objective function value, and these solutions might involve changing the current set of basic variables. To determine optimality, additional criteria need to be considered, such as the feasibility of the solution and the optimality conditions of the linear programming problem.

When using the Big M method to find an initial basic feasible solution (BFS), it is possible that it may take more than k pivots to find a "real" basic feasible solution that includes only the variables in the original problem.

The Big M method introduces artificial variables with a large coefficient (M) in the objective function to enforce constraints during the initial phase of solving a linear programming problem. These artificial variables ensure that all constraints are satisfied and provide a starting BFS. However, these artificial variables are not part of the original problem and need to be removed to obtain a "real" BFS.

The number of pivots required to find a "real" BFS depends on the particular problem and the choice of artificial variables. It is possible that additional pivots are needed to eliminate the artificial variables and identify a feasible solution that includes only the original variables.

Therefore, it is indeed possible for it to take more than k pivots to find a "real" BFS when using the Big M method, where k is the number of artificial variables introduced.

Learn more about  Big M method  from

https://brainly.com/question/33248464

#SPJ11

what is the non-dimensional surface temperature of a sphere with a biot number of 8 and a non-dimensional centerline temperature of 0.29?

Answers

The non-dimensional surface temperature of a sphere with a Biot number of 8 and a non-dimensional centerline temperature of 0.29 is approximately 2.32.

The non-dimensional surface temperature of a sphere can be determined using the Biot number and the non-dimensional centerline temperature. The Biot number is a dimensionless quantity that represents the ratio of internal thermal resistance to external thermal resistance.

The relationship between the non-dimensional surface temperature (θ) and the Biot number (Bi) is given by the following equation:

θ = θ_s/ θ_c

Given that the Biot number (Bi) is 8 and the non-dimensional centerline temperature (θ_c) is 0.29, we can rearrange the equation to solve for the non-dimensional surface temperature (θ).

θ = Bi × θ_c

θ = 8 × 0.29

θ ≅ 2.32

Therefore, the non-dimensional surface temperature of a sphere with a Biot number of 8 and a non-dimensional centerline temperature of 0.29 is approximately 2.32.

To learn more about biot numbers,

brainly.com/question/15219947

6th grade math plz help me

Answers

1) 8 41/48
2) 9 16/27
3) 41 2/5
4) 13 55/63
hope this helps x

Which equation has a constant of proportionality equal to 5?

Answers

Answer:

its a :)

Step-by-step explanation:

have a good day!!

Other Questions
If the field capacity of a soil is 30% by volume and the permanent wilting point is 10% by volume, what is the plant available water? 30 cm/m 20% 30% 0.30 First person to answer gets brainliest The level of availability for the product or service is referred to as A) selective distribution.B) intensive distribution. C) exclusive distribution. D) distribution intensity. Explain each of the following: a. Agency problem- b. Maximizing shareholders' wealth- c. The tradeoff between risk and return-d. Market Efficiency - e. Cash flow is what matters- f. Time value of money- Managing Front office operationsDiscussion Questions 1. What steps could the staff at Gordon Sumner's hotel have taken timi their service? clean rooms used for sterile biological research are sealed and operate at slightly above Part II: OTFDConsider the following scenarios:Imagine your friend asks for your opinion about an outfit she wants to buy.Your friend wants to know what you think about a certain video game that is new in stores.You want to ask someone you like to come to your soccer game.Something else you find in your everyday life.Use your This Is It! attitude to create your own OTFD. You can use one of the examples above or a real situation you have.Provide a two or three sentence description of the situation you are using. Then provide a sentence to describe how you might have approached the other person before learning about OTFD.Create an actual OTFD for the situation. Include a sentence for each part of OTFD. dimensional formula of accelaration due to gravity This means that Rosengarten needs $1.62 in fixed assets for every dollar in sales when it reaches full capacity. At the projected sales level of $1,250, it needs $1,250 1.62 = $2,025 in fixed assets, which is $225 lower than our projection of $2,250 in fixed assets. So, EFN is $565 225 = $340. Blue Sky Mfg., Inc., is currently operating at 90 percent of fixed asset capacity. Current sales are $712,000. How much can sales increase before any new fixed assets are needed? 18-year-olds living in California and 24-year-olds living in Tokyo don't always have much in common. Toyota, through its research, knew that one attribute common to most members of the target market was an interest in individuality. Discovering this is an example ofChoices:a. trait matching.b. selective perception.c. finding a shared characteristic.d. a unique selling proposition.e. message vulnerability. QUESTION FIVE Evaluate whether the formation of the Common Market for Eastern and Southern Africa (COMESA) has in anyway compromised the welfare benefits typically associated with a customs union. Faiza, Krish and Joe start cycling around the park from the same point at the same time. Faiza circles the park in 60 seconds, Krish and Joe circle the park in 14 seconds and 25 seconds respectively. Find the least time in minutes after which they all will meet at a place together. 1.) Bankruptcy Risk and Z-Score AnalysisFollowing are selected ratios for Logitech International SA for the companys 2019 fiscal year.Note: Complete the entire question in Excel and format each answer to two decimal places. Then enter the answers into the provided spaces below with two decimal places.in thousands (except price per share and shares outstanding)Current assets $1,350,436 EBIT $263,194Current liabilities $552,721 Total liabilities $652,794Total assets $1,558,575 Sales revenue $2,147,008Retained earnings $1,365,036 Shares outstanding 165,862,887Price per share $39.34 Compute and interpret the Altman Z-score.Note: Convert shares outstanding to "in thousands" for your computation.Z-scoreAnswer Fill in the Blank Complete the following sentence. An essential part of the scientific method is that an experiment must be able to be ______. What do you think makes one company more reliable or better fortheir employees than another company? Mara sufre de migraa cronica 1. Tom tries to borrow moncy for his tuition from Arshdeep, He, however, plans to go to a casino with the money. Arshdeep faces the problem of A) moral hazard B) adverse selection C) free riding D) Evil borrower Another 2 questions on percentage WILL GIVE BRAINLIEST!!!!!! Please use attachment as a template and show full steps including making sure that categories are fully viewable.Sunblessed Juice Company sells bags of oranges and cartons of orange juice. Sunblessed grades oranges on a scale of 1 (poor) to 10 (excellent). At present, Sunblessed has 220,000 pounds of grade 6 oranges and 150,000 pounds of grade 9 oranges on hand. The aver- age quality of oranges sold in bags must be at least 7, and the average quality of the oranges used to produce orange juice must be at least 8. Each pound of oranges that is used for juice yields a revenue of $2.25 and incurs a variable cost (consisting of labor costs, variable overhead costs, inventory costs, and so on) of $1.35. Each pound of oranges sold in bags yields a revenue of $2.00 and incurs a variable cost of $1.20.a. Determine how Sunblessed can maximize its profit.b. Use SolverTable to determine how a change in the cost per bag of oranges changes the optimal solution.c. Use SolverTable to determine how a change in the amount of grade 6 oranges available affects the optimal solution.d. Use SolverTable to determine how simultaneous changes in the required average quality required for juice and the average quality required for bags change the optimal solution