Fluid flows at 1 L/s through a 200 mm diameter pipe. Determine whether is laminar or turbulent if the fluid is (a) Air (v = 1.51 x 10-5), (b) hydrogen (v = 1.08 x 10-4), (c) water (v = 1.02 x 106 m2/s

Answers

Answer 1

Laminar and turbulent flows can be distinguished by the Reynolds number (Re). The fluid in a pipe is laminar if Re<2300. Turbulent flows, on the other hand, occur when Re>4000.

Intermediate flows have Re values ranging from 2300 to 4000. A fluid flows through a 200 mm diameter pipe at a rate of 1 L/s. Determine if it is laminar or turbulent if the fluid is air, hydrogen, or water.

The fluid's viscosity, density, and flow rate are used to compute the Reynolds number. Part a. Re for air is computed using the following equation:

[tex]Re = ρVD/µ= (1.225 kg/m3)(1 L/s / 1000 kg/L) (0.2 m) / (1.51 x 10-5 Ns/m2)= 19359.[/tex]

The value of Re > 4000 for air, which indicates that it is in the turbulent region. Re for hydrogen is computed using the following equation:

[tex]Re = ρVD/µ= (0.0901 kg/m3)(1 L/s / 1000 kg/L) (0.2 m) / (1.08 x 10-4 Ns/m2)= 1501.7[/tex].

The value of Re < 2300 for hydrogen, which indicates that it is in the laminar region. c. Re for water is computed using the following equation:

[tex]Re = ρVD/µ= (1000 kg/m3)(1 L/s / 1000 kg/L) (0.2 m) / (1.02 x 106 Ns/m2)= 39.21.[/tex]

The value of Re < 2300 for water, which indicates that it is in the laminar region. the air flow is turbulent, and the hydrogen and water flows are laminar.

To know more about viscosity visit:-

https://brainly.com/question/30759211

#SPJ11


Related Questions

2.50m x 2.50m square footing supports a 350mm x 400mm reinforced concrete column carrying a factored axial load of 930 kN. Use fc = 28 MPa and fy = 415 MPa. Use 20mm diameter reinforcing steel bars bothways. Clear concrete cover is 70 mm
A. Determine the effective depth of footing for wide-beam action
B. Determine the effective depth of footing based on two way action.
C. Determine the required safe thickness of footing.

Answers

a) To find the effective depth of the footing, use the formula for wide-beam action:

be =[tex][bc + {(12AsFy) / (0.85fc(b - d))}] / 2[/tex],where:bc = width of the columnAs = area of steel reinforcement in the footing

Fy = steel yield strengthfc = compressive strength of the concreteb = width of the footingd = effective depth of the footing

Substituting the values given,be =[tex][0.4 + {(12 x 0.031416 x 415) / (0.85 x 28 x (2.5 - 0.07))}] / 2= 0.844 m[/tex]Therefore, the effective depth of the footing for wide-beam action is 0.844 m.

b) To find the effective depth of the footing based on two-way action, use the formula:deff = [tex]0.75{[Asfy + (bt)^2/2]}^(1/2) / (0.85fc)[/tex]bwhere:t = thickness of the footing

Substituting the values given and solving for deff,deff =[tex]0.75{[0.031416 x 415 + (2.5 x 0.35)^2/2]}^(1/2) / (0.85 x 28 x 2.5)= 0.60 m[/tex]

The effective depth of the footing based on two-way action is 0.60 m.c) The required safe thickness of the footing can be calculated as follows:V = factored axial load on the column = 930 kN, or 930,000

[tex]Nq = 1 - V/[4(b + t)fc][/tex ]where:q = non-dimensional bearing capacity factorb = width of the footing d = effective depth of the footingt = thickness of the footing for a footing width of 2.5 m and a value of q = 0.15, the minimum thickness of the footing required for safe bearing capacity is 0.35 m.

the required safe thickness of the footing is 0.35 m.

To know more about effective depth visit:-

https://brainly.com/question/31427952

#SPJ11

Compute the safe ultimate moment of a T-beam beam with a flange width 2500mm, flange thickness of 80mm, web thickness of 300mm and an overall depth of 900mm. The beam is reinforced with an unbonded tendon having an area Aps = 1000mm2 and located 80mm from the bottom fiber of the beam, fc' =35MPa. The beam has a simple span of 6m.

Answers

The safe ultimate moment of a T-beam beam is 5,930,060.18 N.mm.

Step 1: Calculate the effective depth of the beam Effective depth, [tex]d = h – 0.5tf= 900 – 0.5(80) = 860mm[/tex]

Step 2: Compute the depth of the equivalent rectangular stress block The depth of the equivalent rectangular stress block, a = 0.85d= 0.85 × 860 = 731mm

Step 3: Compute the ultimate compressive strain for the concrete The ultimate compressive strain for the concrete, εcu = 0.0035 + (0.00175/0.45)× (d – a)= 0.0035 + (0.00175/0.45)× (860 – 731)= 0.0042

Step 4: Here we assume da as 0.85d'.d' = d – (tw/2 + a)= 860 – (300/2 + 731) = -191.5mm
[tex]da = 0.85d = 0.85 × 860 = 731mm[/tex]
[tex]Mu = 0.90 × 1.2 × 1860 × 1000 × (860 – 731 – (-191.5))= 3,189,276 N.mm[/tex]
[tex]Mpe = Asfy (d – a – da)/2 = Asfy(0.5d’ + a – da)[/tex]
[tex]415 × 1000 × (0.5(191.5) + 731 – 731) = 80,922 N.mm[/tex]

[tex]As = (Mu)/(0.95×f'c×(d – 0 .5a) + 0.95fy(As)/As)[/tex]
[tex](3,189,276)/(0.95 × 35 × (860 – 0.5 × 731) + 0.95 × 415 × As/1000)[/tex]
[tex]As = 1052.07 mm²[/tex]

Step 5: By substituting the values, we get;
[tex]Mu = 0.95 × 1052.07 × 415 × (860 – 731/2) + 0.95 × 35 × 2500 × 731 × 731/2= 5,930,060.18 N.mm[/tex]
So, the safe ultimate moment of a T-beam beam is [tex]5,930,060.18[/tex] N.mm.

To know more about effective depth visit:-

https://brainly.com/question/31427952

#SPJ11

Estimating are the fundamental of building construction as it provides all parties on information such as the overall cost of the building, the material needed to construct a building, resources needed to fulfil trades of work and even information on contractual aspect of construction project.
Over the years, measurement have becoming more and more important to construction sector as more and more industry and macro-economic sector started utilizing estimation as part of construction fundamentals. However, since the emergence of the concept "Industrial Revolution 4.0" across the globe, various technologies and software are being developed as an initiative to traditional measurement.
Hence, as the future prospect of our construction sector, you are required to study on the "effect of modernization to estimating" in general.
You are required to discuss on
Traditional estimating
Involvement of technologies in estimating
Pro and cons of the involvement of technologies in estimating
Pick one (1) software or application that is being used in the industry (Eg: Cubicost, Primavera, etc…)
Introduce them in general.
What can they do in terms of estimation.
Why do you choose them as your software.
Conclusion (Please include your findings on the matters discuss above – Technologies is good initiative to estimation, it is not good, etc…)
You shall provide the discussion in the form of report and the following shall be taken into consideration while preparing for your report.
Not more than 15 pages (Minimum 10 Pages)
Include cover page, table of content, reference and necessary formatting
Use ‘Times New Roman’ fonts
Use 14 font size for topic, 12 font size for heading and 11 font size for the body
1.5 line and paragraph spacing
All paragraph should be in justify format
The student has to prepare a slide for presentation in which will cover for all content under the report.
The slides shall be:
Not more than 15 slides
15 minutes’ presentation time
Cover all parts under the report
Use your own creativity as there will be marks for slides Submit your slide along with your report

Answers

Estimation is a crucial part of construction work. It helps in providing information about the cost of building a structure, the necessary materials required to construct a building, resources required to carry out various trades, and information on contractual aspects of construction projects.

The importance of measurements in construction has been increasing over the years. As the world witnesses Industry Revolution 4.0, new software and technologies are being developed to replace traditional measurement methods. This report explores the effect of modernization on estimating and the involvement of technology in estimating in general.

The process of estimating involves the preparation of a detailed plan and a detailed estimate. The estimate should include the cost of labor, materials, and other expenses that will be required to complete the construction project. A traditional estimate is usually done by an estimator.

To know more about Estimation visit:

https://brainly.com/question/30870295

#SPJ11

Draw a detailed block diagram of an NMR spectrometer and label
all components. Describe the function of each component in
detail.

Answers

An NMR spectrometer consists of several components, including sample preparation, RF generator, transmitter, detector, amplifier, data acquisition system, and a computer. These components work together to prepare and load the sample, generate and apply RF pulses, detect the signal, amplify it, convert it to a digital format, and process it using a computer.

A detailed block diagram of an NMR spectrometer illustrates the various components and their functions within the instrument. Each component is labeled to indicate its role in the circuit. The key components of an NMR spectrometer and their functions are as follows:

1. Sample preparation and loading: This section includes sample holders designed to accommodate different sample sizes and orientations. Its purpose is to prepare the sample and load it into the instrument.

2. Radiofrequency generator: The RF generator produces an oscillating voltage at the resonant frequency of the nucleus under study. It supplies the transmitter with the RF pulse required to excite the nuclei and modulates the signal for detection.

3. Transmitter: The transmitter applies the RF pulse to the sample, and its duration and amplitude can be adjusted to control the level of excitation of the nuclei.

4. Detector: The detector senses the magnetic field of the sample and generates a voltage signal proportional to the field strength. It detects the signal emitted by the sample after excitation, which can be further amplified and digitized.

5. Amplifier: The amplifier increases the magnitude of the signal produced by the detector, enhancing its strength for further processing. The gain of the amplifier can be adjusted to control the instrument's sensitivity.

6. Data acquisition: The data acquisition system converts the amplified signal from analog to digital form, making it suitable for processing by a computer. It enables the conversion of the signal into a digital format for subsequent analysis.

7. Computer: The computer governs the instrument's operation, controlling its functions and processing the digitized signal. It manages data acquisition, analysis, and visualization.

In summary, an NMR spectrometer consists of multiple components working together to perform various functions. The sample preparation and loading section prepares and introduces the sample, while the RF generator and transmitter generate and apply the RF pulse. The detector detects the resulting signal, which is then amplified by an amplifier. The data acquisition system converts the amplified signal into a digital format for processing by a computer, which controls the instrument and analyzes the data.

Learn more about NMR spectrometer

https://brainly.com/question/14052745

#SPJ11

(a) Explain the applications of low strain and high strain dynamic pile load tests. (b) A 0.8 m diameter concrete pile is driven at a site as shown in Figure below, where the water table is at the ground surface. The pile's design uplift load is 800 kN. Assume No is 35 for the sand layer. Pile-soil interaction factor a in clay is 0.6. Pile-soil interface friction angle in sand is 75% of the friction angle of sand.
(i) Determine the pile's required length to support the uplift load if the factor of safety is 2.5. Note: Round pile length to the nearest 0.5 m.
(ii) Check whether the calculated pile length is sufficient to carry an axial load of 2 MN with a factor of safety of 3.0. (iii) If 10 piles are used with a pile cap as a group, calculate the axial load carrying capacity of the pile group. The centre to centre spacing between piles in the group is 1.0 m.

Answers

This is frequently used in conjunction with static pile load testing for a more complete picture of pile capacity and performance.

Friction capacity of sand pile =[tex]35 x π/4 x (0.8)2 x (140 - 0) / (2 x 2.5) = 479.67 kN[/tex]

Net ultimate bearing capacity = [tex]479.67 + 45.83 = 525.5 kN[/tex]

Required pile length =[tex]{[(800 + 0)/525.5] + 0} / (2.5 x 0.6 x π/4 x (0.82))= 15.45 m ≈ 15.5 m[/tex]

(ii) Check whether the calculated pile length is sufficient to carry an axial load of 2 MN with a factor of safety of 3.0

Ultimate capacity of pile = Net ultimate bearing capacity + side resistance capacity= [tex]525.5 + (0.6 x π/4 x (0.8)2 x 27.5 x 1000) = 707.9 kN[/tex]

Ultimate capacity of 10 piles = [tex]707.9 kN x 10 = 7079 kN[/tex]

FOS for axial load =[tex]7079 / 2000 x 3 = 10.6 > 3.0,[/tex]

Therefore, the pile length is sufficient.

(iii) Axial load carrying capacity of pile group= (No of piles x Ultimate capacity of single pile x Reduction factor)/FOSEquivalent diameter, Deq =[tex](N x Ap)1/2 = (10 x π/4 x 0.82)1/2 = 3.52 m[/tex]

Reduction factor, [tex]Rf = (1 – 0.3/Deq) x (1 – 0.3/Hf) = 0.763 x 0.8 = 0.61[/tex]

Axial load carrying capacity of pile group = [tex](10 x 707.9 x 0.61) / 2.5= 10960.84 kN = 10.96 MN[/tex]

Therefore, the axial load carrying capacity of the pile group is 10.96 MN.

To know more about conjunction visit:-

https://brainly.com/question/28839904

#SPJ11

(a) m³/s A broad-crested weir is located in a wide prismatic channel with a bed surface slope of So=2×10 with a discharge per unit width of q=1.5 m The bed surface roughness has a Manning's coefficient of n is 0.015. Assuming per m width. that energy losses may be neglected (and no hydraulic jumps do occur):
(i) find the normal and critical flow depths and respective flow energies for this channel flow.
(ii) find the height of the weir, so that the flow over the weir will just obtain the critical flow depth.
(iii) find the flow depths just upstream the weir (approaching), at the weir, and downstream of the weir, for a weir height of 0.2 m.
(iv) find the flow depths just upstream the weir (approaching), at the weir, and downstream of the weir, for a weir height of 0.5 m.

Answers

(a) m³/sA broad-crested weir is located in a wide prismatic channel with a bed surface slope of So=2×10 with a discharge per unit width of q=1.5 m. The bed surface roughness has a Manning's coefficient of n is 0.015.

(i) So, the normal depth calculation for a broad-crested weir is given by the following equation:

[tex]qn^2 = (g/2) * (n^2) * Q^2 * S^(3/2[/tex])Where, q = Discharge per unit width n = Manning's coefficient of channel bedS = Bed slope Q = Discharge per unit width g = Acceleration due to gravity[tex]n = 0.015S = 2×10Q = 1.5 m³/s= 0.2306 J/m³[/tex]

(ii) qc = 1.84 * H^(3/2)where qc = Flow over the weir H = Weir height

For a weir height such that the flow over the weir will just obtain the critical flow depth, qc = q, and

[tex]H = hcqc = 1.84 * Hc^(3/2)1.5 = 1.84 * Hc^(3/2)Hc = (1.5 / 1.84)^(2/3)Hc = 0.6007 m[/tex]

The height of the weir for the flow over the weir to just obtain the critical flow depth is Hc = 0.6007 m

(iii) The flow depths just upstream the weir (approaching) is h_1 = h_n.The flow depth at the weir is h_2 = yc.For the downstream of the weir, the flow depth h_3 can be calculated as:[tex]h_3 = sqrt((h_2^2) + ((2/3) * H))h_3 = sqrt((0.2165^2) + ((2/3) * 0.2))h_3 = 0.3012 m[/tex]

(iv) The flow depths just upstream the weir (approaching) is h_1 = h_n.The flow depth at the weir is h_2 = yc.For the downstream of the weir, the flow depth h_3 can be calculated as:

[tex]h_3 = sqrt((h_2^2) + ((2/3) * H))h_3 = sqrt((0.2165^2) + ((2/3) * 0.5))h_3 = 0.2974 m[/tex]

To know more about prismatic visit:-

https://brainly.com/question/30819926

#SPJ11

Design a non-cylinder prestressed concrete pipe of 600 mm internal diameter to withstand a working hydrostatic pressure of 1.05 N/mm 2 , using a 2.5 mm high-tensile wire stressed to 1000 N/mm 2 at transfer. Permissible maximum and minimum stresses in concrete at transfer and service loads are 14 and 0.7 N/mm 2 . The loss ratio is 0.8. Calculate also the test pressure required to produce a tensile stress of 0.7 N/mm 2 in concrete when applied immediately after tensioning and also the winding stress in steel if E s ​ =210kN/mm 2 and E c ​ =35kN/mm 2 .

Answers

To design a non-cylinder prestressed concrete pipe with a 600 mm internal diameter to withstand a working hydrostatic pressure of 1.05 N/mm², the ultimate tensile stress developed in the wire is calculated as 1250 N/mm². The stress in the wire at transfer and service loads is determined based on the assumptions of Pp/P = x and Ps/P = y. The design includes calculating the thickness of the pipe and ensuring that the load capacity exceeds the applied load. The winding stress in steel is determined to be 7500 N/mm². The test pressure required to achieve a tensile stress of 0.7 N/mm² in concrete is also calculated. Overall, the design meets the requirements for the given working hydrostatic pressure.

Given:

Internal diameter (D) = 600 mm

Working Hydrostatic pressure (p) = 1.05 N/mm²

Prestressing wire stress (fp) = 1000 N/mm² at transfer

Concrete permissible stress at transfer (fc) = 14 N/mm²

Concrete permissible stress at service load (fcd) = 0.7 N/mm²

Loss ratio (α) = 0.8

Modulus of Elasticity of steel (Es) = 210 kN/mm²

Modulus of Elasticity of concrete (Ec) = 35 kN/mm²

To design a non-cylinder prestressed concrete pipe with a 600 mm internal diameter to withstand a working hydrostatic pressure of 1.05 N/mm², we need to determine the ultimate tensile stress developed in the wire. The formula for ultimate tensile stress is given as:

σpu = fp / α = 1000 / 0.8 = 1250 N/mm²

Thus, the ultimate tensile stress developed in the wire (σpu) is 1250 N/mm².

Next, we calculate the stress in the wire at transfer (σp) using the formula:

σp = σpu × Pp / P = 1250 × Pp / P

Assuming Pp / P = x, we have:

σp = 1250 × x ............. (1)

The initial stress in the wire at transfer is given as 1000 N/mm².

The stress loss in the wire at service is calculated as:

fpe = fp - σpu = 1000 - 1250 = -250 N/mm²

The stress in the wire at service (σps) is given by:

σps = fpe × Ps / P = -250 × Ps / P

Assuming Ps / P = y, we have:

σps = -250 × y ............. (2)

At service load, the stress in the wire should be equal to fcd, so we have:

σps = fcd / -250

y = P / 625000 fcd ............. (3)

We also know that:

Pp + Ps = Pu = P × α

Pp + Ps = P / 0.8

Pp + Ps = 1.25P

Assuming Pp / P = x and Ps / P = y, we have:

x + y = 1.25 ............. (4)

From equations (1) and (2), we get:

1250 × x - 250 × y = σp - σps

= σp + fcd / 625000 × P ............. (5)

To calculate the thickness (t) of the pipe, we assume a value and then use it to calculate the area of the cross-section (A) of the pipe. The load capacity of the pipe should be greater than the load acting on it.

A = π/4 (D² - (D - 2t)²)

The load acting on the pipe is given as:

P = 1.05 × A = 1.05 × π/4 (600² - (600 - 2t)²) = 1647.88t² N

By substituting the value of P in equation (5) and solving for x and y, we can calculate the stresses in the wire at transfer and service loads.

From the given data, we can calculate the winding stress in steel (σw) as:

σw = Es / Ec × σp = 210000 / 35000 × 1250 = 7500 N/mm²

The test pressure required to produce a tens

ile stress of 0.7 N/mm² in concrete when applied immediately after tensioning is given by:

σpe = fp / α

σpe = 1000 / 0.8 = 1250 N/mm²

Using the value of σpe, we can find the stress in concrete as:

σce = σpe / (1 + Es / Ec)

σce = 1250 / (1 + 210000 / 35000) = 35.29 N/mm²

Using the stress in concrete, we can calculate the test pressure (Ptest) required to produce a tensile stress of 0.7 N/mm² in concrete:

Ptest = σce × D / 2t - σw

= 35.29 × 600 / (2 × t) - 7500

= 106 / t - 7500 N/mm²

Therefore, a non-cylinder prestressed concrete pipe with a 600 mm internal diameter can be designed to withstand a working hydrostatic pressure of 1.05 N/mm².

Learn more about hydrostatic pressure

https://brainly.com/question/28206120

#SPJ11

3.) An electronic store that sales transistors pays their lot space P200k per year. If the transistor can be sold P8 pesos per unit while manufacturing cost P1.25 pesos per unit. Calculate the number of units that must be sold per month to achieve breakeven. 4.) An electrical company manufactures transformer at a cost P6kper transformer. If the maintenance of the equipment cost P100k pesos every six months and the company sells the unit for P75k per unit. The employees' salaries are P20k per month. If there are 10 employees in total. What is the volume of sales that must be made each month to achieve breakeven?

Answers

3.) An electronic store that sales transistors pays their lot space P200k per year. If the transistor can be sold P8 pesos per unit while manufacturing cost P1.25 pesos per unit. Calculate the number of units that must be sold per month to achieve breakeven.

Breakeven point is the level at which total cost equals total revenue. Breakeven point in units = fixed costs / contribution margin per unitFixed costs = P200,000 per yearContribution margin per unit = selling price per unit - manufacturing cost per unit = P8 - P1.25 = P6.75Breakeven point in units = P200,000 / P6.75 per unit = 29,630. In order to achieve breakeven, the store must sell 29,630 units per year, or about 2,469 units per month.4.) An electrical company manufactures transformer at a cost P6kper transformer.

Breakeven point in units = fixed costs / contribution margin per unitFixed costs = equipment maintenance cost + salaries = P100,000 per 6 months + 10 x P20,000 per month = P220,000 per 6 months = P36,667 per monthContribution margin per unit = selling price per unit - manufacturing cost per unit = P75,000 - P6,000 = P69,000Breakeven point in units = P36,667 per month / P69,000 per unit = 0.531 units per month. In order to achieve breakeven, the company must sell at least 1 unit per month.

To know more about  sold per month visit:

brainly.com/question/25916355

#SPJ11

b) Outline three ways by which the factor of safety against a circular slip failure can be increased.

Answers

The three ways by which the factor of safety against a circular slip failure can be increased are:Increase the angle of friction between the soil mass and the foundation by:Increasing the surface roughness of the foundation.

A rough surface between the soil mass and the foundation would produce more interlocking between the soil and the foundation, resulting in an increase in the angle of friction, leading to an increase in the factor of safety against the slip failure.Using geotextiles.

These are synthetic fabrics or mats that have high tensile strength and are used to improve the performance of soil structures. They improve the frictional characteristics of the soil and prevent the migration of soil particles, which increases the angle of friction and results in an increase in the factor of safety against the slip failure.

To know more about safety visit:

https://brainly.com/question/18746690

#SPJ11

A W 533 x 93 simply supported beam with span of 7.8 m carries a uniformly distributed load of 52 kN/m throughout its length. The beam has the following properties: Ix = 0.000556 m² Depth, d 533 mm Web thickness, tw = 10.2 mm Fy 248 MPa. The beam is laterally supported over its entire length. The allowable flexural stress is 0.66Fy, allowable shearing stress is 0.4Fy, and allowable deflection is L/360.

Answers

Given data: A W 533 x 93 simply supported beam with span of 7.8 m carries a uniformly distributed load of 52 kN/m throughout its length. The beam has the following properties: Ix = 0.000556 m² Depth, d 533 mm Web thickness, tw = 10.2 mm Fy 248 MP

Calculation of shear force at the right side of the beam (x = L)Shear force at the right side of the beam V = 0 k N Calculation of maximum bending moment Maximum bending moment at the center of the beam (x = L/2)M max= (wL²)/8Mmax= (52 × 7.8²)/8Mmax= 2046.96 k N .m Maximum bending moment at the center of the beam (x = L/2)M max= 2046.96 kN.mStep4: Calculation of maximum shear stress Maximum shear stress occurs at the section where the shear force is maximum. The maximum shear stress is given by,τmax = (VQ)/(Ibt) Where, Q = moment of area of the beam about the neutral axis b = width of the beam t = thickness of the web at the point where shear stress is to be determined. I = Moment of inertia of the beam about the neutral axis. V = Shear force at the section where shear stress is to be determined .

M max= Maximum bending moment at the section where shear stress is to be determined. Q = (bd²)/4Q = [(533 × 10.2³)/4]Q = 361732.4 mm³τmax = (VQ)/(Ibt)τmax = (202.8 × 361732.4)/(0.000556 × 10.2 × 533)τmax = 38.29 M Pa Maximum shear stress = 38.29 MPaStep5: Calculation of deflectionThe maximum deflection is given by,δmax = (5 × w L⁴)/(384 × EI)Where, E = Young's modulus of the Materiali = Moment of inertia of the beam about the neutral axis.δmax = (5 × wL⁴)/(384 × EI)δmax = (5 × 52 × (7.8 × 10⁶)⁴)/(384 × (2.1 × 10⁵) × 0.000556)δmax = 8.54 mm Maximum deflection = 8.54 mm Answer: Therefore, the maximum bending moment is 2046.96 kN.m, the maximum shear stress is 38.29 MPa, and the maximum deflection is 8.54 mm. The beam satisfies the given allowable flexural stress, allowable shearing stress, and allowable deflection.

To know more about thickness visit:

brainly.com/question/23622259

#SPJ11

CLO For beam design, the lateral torsional bucking modification factor tC for asted beam fed at both ends with uniformay dributed load is 2.38 Lateral bracing is provided at supports (fed ends)

Answers

In the case of lateral torsional buckling, CLO, or the modification factor, must be included in the design of a beam. The modification factor for lateral torsional buckling of a castellated beam with simply supported edges is expressed as tC, which is equal to 2.38.

Lateral bracing is supplied at the supports (fed ends).When a beam is loaded and subjected to lateral torsional buckling, the lateral torsional buckling coefficient (CLO) becomes significant. The lateral torsional buckling factor is a ratio of the critical moment of buckling to the elastic moment of the beam.

The greater the lateral torsional buckling coefficient (CLO), the greater the critical moment for buckling and the higher the beam's buckling resistance. If the lateral torsional buckling coefficient (CLO) is greater than or equal to 1, the beam is classified as torsionally rigid and doesn't require additional lateral bracing.

Lateral bracing must be given at the supports (fed ends) for asted beam fed at both ends with uniformay dributed load. Therefore, the lateral torsional buckling coefficient (CLO) for asted beam fed at both ends with uniformay dributed load is equal to 2.38. The beam's buckling strength can be increased by using the lateral torsional buckling factor (CLO).

To know more about lateral torsional buckling visit:-

https://brainly.com/question/31838400

#SPJ11

1. What are the major parameters used in water quality assessment? Please identify four parameters and explain why these parameters should be concerned (4 pts)
2. Explain the difference between coagulation and flocculation and name three coagulants. (4 pts)
3. Name all settling types and their respective applications. (4 pts)
4. What filter types and media types are used in filtrations, and name four particle removal mechanisms involved in filtration process. (4 pts)
5. Name three typical disinfection process and explain the potential negative effect of disinfection byproducts. (4 pts)
6. What is the effect of pH on chlorination? (4 pts)

Answers

1. The major parameters used in water quality assessment are:Temperature – High temperatures can make the water undesirable for consumption, while low temperatures can provide an ideal breeding ground for pathogens.

Turbidity – Turbidity of water means the cloudiness or haziness of the water, higher turbidity means higher chances of sediments and particles that affect the clarity of the water and it's quality.

2. Coagulation and flocculation are two water treatment processes used to remove suspended solid particles and impurities from water.

3: Sludge blanket settling - removes organic matter and suspended solids from water, and is commonly used in industrial wastewater treatment.

4. There are several types of filter media used in the filtration process, some of them are: Activated carbon, Sand, Anthracite, Crushed glass, Gravel.

5. Three typical disinfection processes are chlorination, ultraviolet (UV) radiation and ozone disinfection. Disinfection byproducts are formed when disinfectants, such as chlorine, react with organic matter in the water.

6. The pH level of water affects the effectiveness of chlorination. If the water is too acidic, chlorine can be consumed quickly and lose its disinfecting power before it can be effective.

To know more about Coagulation visit:-

https://brainly.com/question/31116523

#SPJ11

Is computed to take into account first cost, expected lifetime, maintenance costs, fuel costs, replacement cost, inflation, and the time value of money (interest). a. First cost Ob.Maintenance cost Oc. Life-cycle cost

Answers

The term that should be included in the answer to your question is "Life-cycle cost".Life-cycle cost is computed to take into account first cost, expected lifetime.

Maintenance costs, fuel costs, replacement cost, inflation, and the time value of money (interest). It is a complete estimate of the cost of ownership over the entire life of an asset, including the cost of acquisition, operation, maintenance, and disposal.

It is a comprehensive analysis of the cost of an asset over its lifetime, and it takes into account all the relevant costs of ownership, including the initial purchase price, maintenance costs, and replacement costs over the expected lifespan of the asset.

To know more about computed visit:

https://brainly.com/question/18652975

#SPJ11

Design a reinforced concrete beam to carry a service live load of 10kN/m and dead load of 6kN/m (including its own weight) Use f 'c = 27MPa, fy = 414MPa, b = d/2. The beam is to be reinforced in tension only. L1 = 7m & L2 = 7m

Answers

The design of the reinforced concrete beam to carry a service live load of 10 kN/m and dead load of 6 kN/m (including its own weight) using f'c = 27 MPa, fy = 414 MPa, b = d/2 and reinforced in tension only with L1 = 7m and L2 = 7m is given as follows;

Step 1: Calculation of self-weight of the beam

[tex]A = bd = d²/2As = (fy/0.87) * 0.85A's = 0.85 * AsM_uz = (dl+ll) * L^2 / 8M_u = 1.2M_uzM_u = 1.2(6 + 10) x (7²)/8M_u = 105 kNm/g1c1 = M_u / bd²f_c′ = 27 MPa = 27 N/mm²f_y = 414 MPa = 414 N/mm²From 250 mm deep beam table, taking b/d = 0.5;For d = 250mm;[/tex]

Step 2: Calculation of the Required Area of Steel to resist moment only Calculate d' (effective depth)d' = d - (As/A) * d' = 240 mm M_u = (f_c' * A * d') * g1c1 + As * fy * (d - d') * g1c1 (Equation 1).

By equating Equation 1, we have;(f_c' * A * d') * g1c1 + As * fy * (d - d') * g1c1 = Mu (Equation 2) Substituting d' = 240 mm and A = 31,250 mm² in Equation 2 gives;

To know more about concrete visit:

https://brainly.com/question/32805749

#SPJ11

Signe offers Thorne, a health inspector, $5,000 to overlook the violations in her Farm-to-Fork Dining Emporium. Thorne accepts the cash and overlooks the violations. Signe is charged with the crime of bribery. The crime occurred when a. Thorne accepted $5,000 from Signe. b. Signe actually offered $5,000 to Thorne. c. Thorne overlooked the violations. d. Signe decided to offer $5,000 to Thorne.

Answers

Signe offers Thorne, a health inspector, 5,000 to overlook the violations in her Farm-to-Fork Dining Emporium. Thorne accepts the cash and overlooks the violations. Signe is charged with the crime of bribery.

The crime occurred when Signe actually offered 5,000 to Thorne. The crime of bribery is committed when someone voluntarily offers a payment or incentive to another person with the intent of inducing that person to act in a manner that benefits the briber.

The act of bribery involves both the offer of something of value, such as money or property, and the acceptance of that offer by the person who is being bribed. Signe committed the crime of bribery by offering Thorne money to overlook the violations at her Farm-to-Fork Dining Emporium.

TO know more about violations visit:

https://brainly.com/question/10282902

#SPJ11

Sandstone an unconfined aquifer, the top of the zone of saturation is called the a) Pressure surface. ) Water table () Saturation limit. d) Water level 12. When fine-grained sediments at bottom of shallow water are exposed() air, they dry out to form structures known as Ripple cracks b) Water marks c) Ripple marks d) Mud cracks

Answers

Sandstone is an unconfined aquifer. The top of the zone of saturation is called the water table. When fine-grained sediments at the bottom of shallow water are exposed to air, they dry out to form structures known as mud cracks

When the soil is saturated with water, the water table rises. An unconfined aquifer is one in which the water table is free to fluctuate in response to changes in the volume of water stored in the aquifer. Sandstone is an example of an unconfined aquifer, which is porous and permeable, meaning that water can move through it quite easily.

The top of the zone of saturation in an unconfined aquifer is called the water table. Ripple marks are features that form in fine-grained sedimentary rocks like sandstone. When these sediments are deposited under shallow water, they are often subjected to wave action, causing the sediment to ripple.

These ripples are preserved in the rock when it solidifies. Mud cracks are a different type of feature that forms when fine-grained sediments at the bottom of shallow water are exposed to air.

As the sediment dries out, it shrinks and cracks, forming a pattern of interconnected cracks that resemble a dried-up mud puddle.

To know more about Sandstone visit:-

https://brainly.com/question/1563342

#SPJ11

Determine True/False: (1) The CPM method was developed primarily for the construction industry (ii) CPM uses probabilistic value for project duration. (iii) A Dummy Activity may sometimes have non-zero duration (iv) In a CPM arrow network, when two or more arrows begin at the same node, this means that the work must begin at the same time. (v) The Forward & Backward Pass algorithms calculate EST and LST respectively, of all activities. (vi) The Critical Path time is defined as the longest possible path of the network. (vii) Backward Pass algorithm assumes the duration of the project as obtained by the Forward Pass. (viii) On the Activity-on-Arrow network, the nodes represent a point in time. (ix) To draw an Activity-on-arrow network, Activities IPA are needed. (x) Duration of a Project (D.) calculation, using Average Productivity, is usually an optinistic one. (xi) If an activity has an EST equal to its LST then it's on the Critical Path. (xii) An activity A[i,j) is a Critical Activity if E(1) L(). (xiii). A project always has at least one Critical Path. (xiv) Of all the floats, Free Float always has the maximum value. (xv) If all Free Floats along a path are zero, then that's a Critical path (xvi) Cash-flow Analysis using CPM can be used using EST or LST Schedule. (xvii) Resource Leveling using CPM is usually a trial-and-error method (xviii) For a PERT model if each activity has a le-0, then effectively it becomes a CPM model. (ix) The Expected Time for PERT is a weighted average of three times. (xx) In the Monte Carlo (Simulation) Method, Activity Duration are generated by random numbers.

Answers

(i) The CPM method was developed primarily for the construction industry. True.(ii) CPM uses probabilistic value for project duration. False.(iii) A Dummy Activity may sometimes have non-zero duration. True.(iv) In a CPM arrow network, when two or more arrows begin at the same node, this means that the work must begin at the same time.

True.(v) The Forward & Backward Pass algorithms calculate EST and LST respectively, of all activities. True.(vi) The Critical Path time is defined as the longest possible path of the network. True.(vii) Backward Pass algorithm assumes the duration of the project as obtained by the Forward Pass.

False.(viii) On the Activity-on-Arrow network, the nodes represent a point in time. False.(ix) To draw an Activity-on-arrow network, Activities IPA are needed. False.(x) Duration of a Project (D.) calculation, using Average Productivity, is usually an optimistic one.

True.(xi) If an activity has an EST equal to its LST, then it's on the Critical Path. True.(xii) An activity A[i,j) is a Critical Activity if E(1) < L().False.(xiii) A project always has at least one Critical Path. True.(xiv) Of all the floats, Free Float always has the maximum value. False.(xv) If all Free Floats along a path are zero, then that's a Critical path. True.(xvi) Cash-flow Analysis using CPM can be used using EST or LST Schedule. False.(xvii) Resource Leveling using CPM is usually a trial-and-error method.

True. The Monte Carlo Simulation Method can be used to generate the activity duration, which uses a random number generator to produce the project completion time frame based on different simulation scenarios.

To know more about node visit:-

https://brainly.com/question/30885569

#SPJ11

In the materials for this Week, we have seen that affirmative action programs in the employment context are harder to get through judicial review than are affirmative action programs in education. Review the assigned cases in this Week and explain both why this difference exists between employment and education affirmative action policies and how it has been applied by the Court.

Answers

Affirmative action is the implementation of various policies and practices aimed at ending historical and present-day discrimination and promoting greater diversity within society.

Affirmative action in the employment and education sector is subject to different scrutiny and judicial review, as stated in the cases assigned for this week. Here, we will discuss why employment and education affirmative action policies are different and how it has been applied by the Court. Education and employment are two different domains, so the nature of affirmative action programs may be different.

Affirmative action programs in education aim to ensure that a diverse pool of students attends college, and the selection is based on the student’s merit. On the other hand, employment affirmative action programs strive to make the workplace more diverse, which could lead to the selection of unqualified or less qualified individuals.

v. Bollinger, the Court upheld the University of Michigan Law School's affirmative action program, which did not establish a quota or point system.

v. Pena, the Supreme Court held that the employment affirmative action policy violates the equal protection clause of the Fourteenth Amendment. The court ruled that such policies must withstand strict scrutiny and must serve a compelling governmental interest.

To know more about present-day visit:

brainly.com/question/9686428

#SPJ11

Determine the magnitude of moment for which 3.6 m long tied-column should be designed. The cross- section of the column is 300 300mm. The service dead and live loads are 356kN and 311kN respectively. The dead moment (MD)is zero and the live moment (ML) at top and bottom is 27 kN (single curvature). Assume K-0.85. The concrete is of normal weight with a compressive strength of 21 Mpa and yield stress of steel is 420 Mpa. Using the simpler ACI Equation to compute El.

Answers

The column moment for a 3.6 m long tied-column having a cross-sectional area of 300 x 300mm, which has to be designed can be determined by using the simpler ACI equation.

Moments are among the most common types of forces or loads encountered in structures. The force applied is perpendicular to the plane of the object, causing it to rotate about a given axis.

The moment of a force about a point is the measure of the tendency of the force to rotate an object about that point. It is denoted by M and measured in newton-metres (Nm).When the column is subjected to the load, there will be a moment produced as a result of the distance of the force from the center of the column.

To know more about moment visit:

https://brainly.com/question/28687664

#SPJ11

1. Maintenance costs for a small bridge with an expected 50-yr life are estimated to be P 2,000.00 each year for the first 5 years, followed by a P10,000 expenditure in the 15th year and a P 20,000 expenditure in the 25th year. If1 = 12% per year. what is the equivalent uniform annual maintenance costs over the entire 50-yr period?
a. P 1,230
b. P 852
C. P 936
d. P 1,159

Answers

The correct answer is option a. P 1,230.Expected annual maintenance costs over the [tex]first 5 years = P 2,000Expected  costs in the 15th year = P 10,000Expected maintenance costs.

In the 25th year = P 20,000Present Worth of Annual Cost - PWA(P/A,i%,n)PWA(P/A,12%,5) = PWA(P2,000/4.0374) = P495.94PWA(P/A,12%,50) = PWA(P1,000) = 9.8181PWA(P/A,12%,25) = PWA(P1,000/15.5043) = P64.51Present Worth of Cost - PWC(P/F,i%,n)PWC(P/F,12%,15) = PWC(P10,000/4.4876) = P2,229.68PWC(P/F,12%,25) = PWC(P20,000/16.0151) = P1,248.97Total present.

Worth of costs over 50 years = P4,049.10Equivalent uniform annual maintenance costs over the entire 50-yr period = AW(P/A,i%,n)AW(P/A,12%,50) = P4,049.10/(AWF(P/A,12%,50)) = P4,049.10/3.2888 = P1,230.07 (rounded off to the nearest whole number)Therefore, option a is the correct answer.

To know more about visit:

https://brainly.com/question/24532377

#SPJ11

Ramp Handling Operator (RHO) is an airport ground-handling agent
who provides airside services for airline. Please explain in detail
what services do they provide to airlines.

Answers

Ramp Handling Operators (RHOs) provide airside services to airlines. Airside services refer to services offered on the airport apron, taxiway, and runway. They make up the ground handling operations on an airport.

Aircraft marshalling Aircraft marshalling is the act of directing an aircraft to its parking position on the apron. This service is done to ensure the safe arrival and departure of an aircraft . RHOs ensure that the loading and unloading of cargo and baggage is done efficiently, effectively, and within the stipulated time frame.

Cabin cleaning RHOs also offer cabin cleaning services. The cabin cleaning involves cleaning the aircraft's interior, such as the cabin, the lavatories, the galleys, and other compartments. Catering services RHOs also provide catering services to the airlines. They supply meals, snacks, and beverages to the aircraft.

This service involves providing check-in services, verifying travel documents, issuing boarding passes, and directing passengers to their assigned aircraft. They also handle the transfer of passengers from one aircraft to another on connecting flights.

RHOs provide a range of airside services to airlines, and these services are critical in ensuring the safe and efficient handling of aircraft operations at the airport.

To know more about Ramp Handling Operators visit:-

https://brainly.com/question/13374455

#SPJ11

The thickness of the clay layer under a layer of sand is equal to 5 m. The ground surface is subjected to a uniformly distributed load of 40 kPa and resulted to a primary consolidation settlement of 180 mm. Determine the secondary settlement (mm) of the clay layer 5 years after the completion of the primary consolidation settlement. Time of completion of primary settlement is 1.5 yrs. Secondary compression index Cα = 0.02 and void ratio of 0.54.

Answers

Given data:The thickness of clay layer (hc) = 5mUniformly distributed load (σ) = 40kPaPrimary consolidation settlement (s) = 180mmTime of completion of primary settlement (tp) = 1.5 yrs Time period after completion of primary settlement (t) = 5 - 1.5 = 3.5 yrs Secondary compression index (Cα) = 0.02Void ratio (e) = 0.54To find:

Secondary settlement (ss)Formula used:Total settlement, s = primary consolidation settlement + secondary settlement ⇒ s = sP + ssThe secondary settlement, ss = Cασlog10(t+tp)log10(tp)The void ratio (e) is given by e = Vv/Vs = (V – Vw)/(Vg – Vw)Where, V = volume of soilVw = volume of waterVg = volume of air and water.

Vs = volume of solidVv = volume of voidsV = Vs + VvSo, Vs = V/(1+e) and Vv = V × e/(1+e)Calculations: As given, total thickness of the soil (h) = hc + hsTo calculate hs, use the formula of Bousiness q. Bousiness q equation is used to calculate the settlement of soil when it is subjected to the loads, and the thickness of the soil layer is very large relative to the footing size and the soil layer is assumed to be homogeneous and isotropic.

To know more about compression visit:

https://brainly.com/question/22170796

#SPJ11

02. Lateral earth pressure
An excavation was made in saturated soft clay (∅=0), with its sides more or less vertical. When the depth of excavation reached 6 m, the sides caved in. What was the approximate value of cohesion of the clay soil? Take unit weight of clay 20 kN/m³.

Answers

Lateral earth pressure refers to the horizontal forces exerted by soil or rock onto an object placed within it. It is essential for ensuring the stability of structures built on or in the ground.

an excavation was made in saturated soft clay (∅=0), and its sides were more or less vertical. When the depth of excavation reached 6 m, the sides caved in.

[tex]Pa = Ka * y * h[/tex]

From the given information, the depth of the excavation, h, is 6 m, and the unit weight of clay, y, is 20 kN/m³. As the soil is saturated, the coefficient of earth pressure at rest, Ka, is 0.5.

Therefore,[tex]Pa = 0.5 * 20 * 6 = 60 kN/m²[/tex]

This collapse happened because the lateral earth pressure exceeded the strength of the soil to resist it.

the lateral earth pressure, Pa, is equal to the shear strength,

We can rewrite the formula for cohesion as:

[tex]C = Pa / (tan Ø) = T/ (tan Ø)[/tex]

[tex]C = 60 / (tan 0)[/tex]

the approximate value of cohesion of the clay soil is Undefined because the internal friction angle of the clay soil is zero, and the value of the cohesion cannot be determined.

To know more about pressure visit:-

https://brainly.com/question/30673967

#SPJ11

Given an initialized String variable message , and given a PrintWriter reference variable named output that references a PrintWriter object , write a statement that writes the string referenced by message to the file output streams to.
Given an initialized String variable message , and given a PrintWriter reference variable named output that references a PrintWriter object , write a statement that writes the string referenced by message to the file output streams to.

Answers

To write the string referenced by the variable message to the file output streams using a PrintWriter object referenced by output, you can use the println method.To write the string to the file output streams, you need to call the println method of the PrintWriter object.

The println method writes a string to the output stream and appends a line separator to it. Here's an example statement that accomplishes this:

output.println(message);

This statement calls the println method on the output object and passes the message string as an argument. The println method writes the string followed by a line separator to the output streams associated with the PrintWriter object. If you want to write the string without appending a line separator, you can use the print method instead:

output.print(message);

Both println and print methods allow you to write the string referenced by message to the file output streams using the PrintWriter object output.

Learn more about string here:

https://brainly.com/question/32338782

#SPJ11

Discuss and point out the testing requirements to secure the
material properties of the ribbed steel reinforcing bars between
the construction standards CS2:1995 and CS2:2012.

Answers

Ribbed steel reinforcing bars are a crucial component of reinforced concrete structures, and their strength and durability are essential for ensuring the safety of structures. The quality of these reinforcing bars must be ensured during their manufacture, transportation, storage, and installation.

1. Chemical Composition Test: The chemical composition of ribbed steel reinforcing bars must be tested to ensure that it meets the requirements specified in the construction standards. The tests are carried out using a spectrometer, and the chemical composition of the steel is determined by analyzing its various components.
2. Tensile Test: Tensile tests are performed to determine the strength and ductility of the ribbed steel reinforcing bars. These tests are performed in accordance with the appropriate ASTM standards.
3. Bend Test: The bend test is performed to determine the ductility and strength of the ribbed steel reinforcing bars. The test is carried out using the appropriate ASTM standards.
4. Rebend Test: The rebend test is performed to determine the ductility and strength of the ribbed steel reinforcing bars. The test is carried out using the appropriate ASTM standards.

These are the various testing requirements necessary for securing the material properties of the ribbed steel reinforcing bars between construction standards CS2:1995 and CS2:2012.

To know more about storage  visit:

brainly.com/question/86807

#SPJ11

A thick steel pressure vessel, having an inside diameter of 210 mm and outside diameter of Pressure cylinder 275 mm, is subjected to an internal pressure of 65 MPa and an external pressure of 10 MPa. For this thick steel pressure vessel:
Question 1
a. Using Lamé's Theory, develop expressions for radial and circumferential stresses; [50%]
b. Plot the radial and circumferential stresses against the wall thickness of the pressure vessel and identify the maximum values; [30%]
c. Calculate the longitudinal stress in the pressure vessel wall.
[20%]

Answers

A thick steel pressure vessel is subjected to an internal pressure of 65 MPa and an external pressure of 10 MPa. The inside diameter of the pressure vessel is 210 mm and the outside diameter is 275 mm.

Lamé's Theory expression for radial and circumferential stresses:

Radial stress is given by:[tex]σr = (pi*D² /d² - 1)*P/2[/tex]Here, D is the external diameter, d is the internal diameter, and P is the pressure.

[tex]σr = (pi*(275)²/(210)² - 1)*65/2σr = 53.08[/tex]

[tex]σθ = (pi*D² /d² + 1)*P/2σθ = (pi*(275)²/(210)² + 1)*65/2σθ = 122.08 MPa2.[/tex]

For a thick-walled cylinder, the wall thickness, t, is given by:

[tex]t = (D - d) / 2t = (275 - 210) / 2t = 32.5 mm[/tex]

[tex]σr = (pi*D² /d² - 1)*P/2σr = (pi*(275)²/(210)² - 1)*P/2[/tex]

Circumferential Stress,[tex]σθ = (pi*D² /d² + 1)*P/2σθ = (pi*(275)²/(210)² + 1)*P/2[/tex]

For a given internal pressure, the radial and circumferential stresses are directly proportional to the wall thickness of the pressure vessel.

Maximum Radial stress = [tex]110.98[/tex]

MPa Maximum Circumferential stress = 112.1 MPa3.

Longitudinal stress in the pressure vessel wall is given by:

[tex]σL = P*(D/d)σL = 65*(275/210)[/tex]

[tex]σL = 85.7 MPa[/tex]

To know more about diameter visit:-

https://brainly.com/question/32968193

#SPJ11

What steps will you take to implement changes in buying a house? How will you avoid scope creep?

Answers

Buying a house is one of the biggest financial decisions that an individual makes in their lifetime. Buying a house involves a lot of money, time, and effort. Changes are inevitable, and they can occur during the process of buying a house. Scope creep occurs when new and unplanned activities are added to the process of buying a house. Scope creep can lead to an increase in time, money, and effort.

Here are some steps to implement changes in buying a house and avoid scope creep:

1. Develop a clear plan and stick to itA clear plan should be developed at the beginning of the process of buying a house. The plan should include the budget, timeline, and goals. Once the plan is developed, it should be strictly followed. The plan should only be changed when it is absolutely necessary.

2. Clearly define the scope of the projectThe scope of the project should be clearly defined at the beginning of the process of buying a house. The scope should include the activities that are to be performed and the activities that are not to be performed.

3. Monitor the progress of the projectRegular monitoring of the progress of the project is essential. The progress should be compared against the plan. Any deviations should be documented, and corrective action should be taken.

4. Communicate effectivelyEffective communication is critical during the process of buying a house. All stakeholders should be kept informed of any changes. The stakeholders should be provided with regular updates on the progress of the project.

5. Evaluate the impact of changesBefore any changes are implemented, the impact should be evaluated. The impact should be evaluated in terms of time, money, and effort.

6. Manage changes effectivelyChanges should be managed effectively. The changes should be documented, and the impact of the changes should be evaluated. The changes should be communicated to all stakeholders.

7. Establish a change control process A change control process should be established. The change control process should include the steps that are to be taken when changes are requested. The change control process should be strictly followed to avoid scope creep.

To know more about Scope creep visit:

https://brainly.com/question/32797277

#SPJ11

3- There are a few important factors in forming a risk/trend management team. One of the following factors shouldn't be on the list, and that is:
risk attitude of team members
knowledge level of team members
proximity of effect of team members
risk appetite of team members
risk blindness of PM
4- There are a few important factors in forming a risk/trend management team. Which composition of people you should work with:
Balance overall
Risk taking in every scenario
Risk blind in every scenario

Answers

3. Risk blindness of PM is the factor that should not be on the list while forming a risk/trend management team. Explanation :Risk blindness refers to a person's inability to see the risks that exist in the situation.

This is a particularly problematic condition for risk management, which is focused on identifying and mitigating risks. Therefore, this factor should not be considered in forming a risk/trend management team.Proximity of the effect of team members: The proximity of the effect of team members is important to consider in forming a risk/trend management team. Team members who are close to the areas that are at risk are better positioned to understand and identify potential risks. Risk attitude of team members: It is important to consider the risk attitude of team members in forming a risk/trend management team.

Team members should be willing to take risks and be open to new ideas and solutions .Knowledge level of team members: It is important to consider the knowledge level of team members in forming a risk/trend management team. Team members should have a strong understanding of the risks and trends that exist in the environment.Risk appetite of team members: It is important to consider the risk appetite of team members in forming a risk/trend management team. Team members should be willing to take risks and be comfortable with the level of risk involved.4. To form a risk/trend management team, you should work with a balanced overall composition of people. Explanation:To form an effective risk/trend management team, you need to have a diverse group of people with different backgrounds and skill sets.

You should work with a balanced overall composition of people who have experience in different areas such as finance, operations, technology, and marketing. This will help ensure that you have a well-rounded team that can identify and mitigate risks from different angles. A balanced team composition will help you have a wide range of ideas and solutions to effectively manage risks and trends.

To know more about   person's inability visit:

brainly.com/question/10265958

#SPJ11

define consolidation process. A saturated soil has a compression dex Cc=0.27. Its void ratio at a stress of 125 kN/m2 is 2.04, and its permeability is 3.5X10-8cm/sec. Compute:
The change in void ratio if the stress is increased to 187.5 kN/m² The settlement in (i) if the soil stratum is 5m thick and Time required for 50% consolidation to occur if drainage is one and time factor is 0.196 for 50% consolidation.

Answers

The process by which the compression of saturated soils is decreased is known as consolidation. This phenomenon causes a time-dependent reduction in the volume of soil under load, resulting in settlement.

Soil consolidation is a complex process that may be affected by a variety of factors, including soil type, load intensity, and drainage conditions. Consolidation is a fundamental component of foundation design that is used to determine the deformation and settlement of soil beneath structures.

[tex]e₂ = e₁ + Cc log10 (σ₂/σ₁)Where, σ₂ = 187.5 kN/m²[/tex]

[tex]e₂ = 2.04 + 0.27 log10 (187.5/125[/tex]

[tex]e₂ = 2.04 + 0.27 × 0.096910013e₂ = 2.0718[/tex]

Therefore, the change in void ratio if the stress is increased to 187.5 kN/m² is 0.0718.

The equation for calculating settlement is given as, [tex]S = Cc [log10 (σi/σ₀)]²[/tex]Where, σi = initial effective stress = 125 kN/m²σ₀ = final effective stress = 187.5 kN/m²Given, soil stratum thickness, h = 5mCc = 0.27The equation for calculating settlement is,[tex]S = 0.27 [log10 (125/187.5)]² S = 0.27 (-0.1761)² S = 0.0012m[/tex]

[tex]k = 3.5 × 10-8 cm/sec[/tex] = [tex](3.5 × 10-8) × (0.0001) m/seck = 3.5 × 10-12 m²/seck = 3.5 × 10-12 × (86,400) m²/dayk = 0.0003024 m²/day[/tex]

[tex]tv = Cv H²/kt = (0.196 × 5²)/(0.0003024)tv = 3244 days[/tex]

Therefore, the time required for 50% consolidation to occur if drainage is one and time factor is 0.196 for 50% consolidation is 3244 days.

To know more about consolidation visit:-

https://brainly.com/question/32995842

#SPJ11

A construction activity has budget of $6,000 and is scheduled to be completed in 5 days (8 hours a day), after three days 40% of activity completed and $3,000 of the budget used. 2. What is schedule performance index (SPT)? a. 1.33 b. 0.67 c. 0.33 d. 1.11 3. What is value of schedule variance (SV) in hours? a. +8 hours. b. - 8 hours. c. +16 hours. d. +24 hours. 4. What is value of cost performance index (CPD)? a. 0.8 b. 0.2 c. 0.7 d. 0.3 22. What is value of cost variance (CV)? a. $ 5400 b. $ - 600 c. $ 6000 d. $ - 5400

Answers

Given Information: Budget of the construction activity = $6,000Scheduled time to complete the activity = 5 days (8 hours/day)Budget used after 3 days = $3,000% of activity completed after 3 days = 40%1.

To find the Schedule Performance Index (SPI):SPI = % of work completed / % of work scheduled SPI = 40% / (3/5*100%)SPI = 40% / 60%SPI = 0.67Hence, the value of Schedule Performance Index (SPI) is 0.67.2. To find the Schedule Variance (SV) in hours:

As we know, SV = BCWP - BCWS Where, BCWP = Budgeted Cost of Work Performed BCWS = Budgeted Cost of Work Scheduled BCWP = % of work completed * Budget SV = (40% * $6,000) - (3/5 * $6,000)SV = $2,400 - $3,600SV = -$1,200So, the value of Schedule Variance (SV) in hours is -$1,200.

To know more about Budget visit:

https://brainly.com/question/31952035

#SPJ11

Other Questions
The mean tax-return preparation fee H&R Block charged retailcustomers last year was $183 (The Wall Street Journal,March 7, 2012). Use this price as the population mean and assumethe population standard deviation of preparation fees is $50.Round your answers to four decimal places.a. What is the probability that the meanprice for a sample of 30 H&R Block retail customers is within$8 of the population mean?b. What is the probability that the meanprice for a sample of 50 H&R Block retail customers is within$8 of the population mean?c. What is the probability that the meanprice for a sample of 100 H&R Block retail customers is within$8 of the population mean? Question 15 6 pts Calculate the effective yields for each 90 day period for a borrower who issues $10,000,000 face value worth of 90 day bank bills in June and hedges its interest rate risk with a 180 day interest rate swap with a swap rate of 4.5% p.a. The 90 day bank bill swap rate at the time of issue of the first bill is 4% p.a. and 3.75% at the time of issue of the second bill in September. Which of the following transactions does NOT decrease cash? A)Stock splits B) Stock retirements C) Cash dividends D) Treasurystock purchases on Time left 1:17:06 Case 4 Terry is thinking of opening up a food truck that creates unique salads. He can purchase the truck for $280,000 and can sell each salad for $6. He has calculated the average variable cost of creating one dazen salads to be $41.40. What is the average variable cost per perogy? Oa. $41.40 Ob. $.45 Oc. $3.45 Od. $6.00 What are the total fixed costs (TFC)? Oa. $6.00 Ob. $41.40 Oc. $280,000 Od. $300,000 What is the breakeven quantity? Oa. 109,804 Ob. 6,763 Oc. 46,667 Od. 81,159 TO MYNAIT If Terry wants a profit of $45,000, what is the breakeven quantity he must sell? Oa. 54,167 Ob. 17,647 Oc. 127,451 Od. 109,804 At the breakeven quantity without profit, what is the total revenue? Oa. $127,451 Ob. $658,824 Oc. $40,578 Od. $280,000 K Time left 1:16:51 Choose the target word that best collocates with each group of words below. implicate levy liberal reside violate 1. liberal : quantity, serving, portion, 2. : a fine, a tariff, a surcharge, a(n) 3. : in a vicinity, in a neighborhood, in a home, at a(n) 4. : in a wrongdoing, in a scandal, in an offense, in a(n) 5. : the law, standards, a promise, a(n) Assume an interest rate of 6 percent. The amount of money you have to deposit today is $ (Round to the nearest cent.) State whether each of the following statements is TRUE or FALSE. 1. In the past few centuries, choices have led to a substantial decline in the standards of living around the globe. 2. Using assumptions to make things simpler and focus attention on what really matters is like using a road map to plan a trip. 3. A key assumption of most economic analysis is that people act rationally, meaning they respond to incentives. 4. The opportunity cost of something is the nominal price paid for the product. 5. Governments sometimes create an excess demand for a product by setting a maximum price that is less than the equilibrium price, resulting in a permanent excess demand for the product. This is known as a price ceiling. 6. If the price of apples increases by 10% and quantity demanded falls by 20%, then the price elasticity of demand for apples is 0.5. 7. By definition, an economy experiences inflation when the aggregate compensation to employees is rising 8. If a 15% increase in income results in a 30% fall in the demand for a good, then other things equal, this good is an inferior good. 9. A market characterised by easy entry and exit, many sellers and differentiated products is perfectly competitive. 10. Real GDP is expressed as a relative value, that is, it has to be expressed as a comparison to the value in another year, called the base year. psychosocial development during adolescence involves the search for a(n) _____. I set a computer to produce random numbers from a uniform distribution such that any real number between 30 and 70 can be obtained. Let the variable name of those numbers be called X. How often will one get a value less than 41? Having read the primary document, "Account of the Stono Rebellion," answer the following questions and submit your answers using the link. Write for about 15 minutes, or 200-250 words, to answer these questions in complete sentences using your own words. 1. Why did the author suggest that Spanish policy played an important role in the Stono Rebellion? 2. How did the author characterize the response of the white planters? 3. Why did the slave revolt fail? 4. Imagine you are among the enslaved in the area where the Stono Rebellion emeges. Would you join the Stono Rebellion? How would the values of social responsibility and personal responsibility guide your actions? Give examples of 3 government policies or regulations can have a potential impact on this industry (education/community college). Think fiscal and monetary policies, tariffs, standards, etc. Explain how each change in policy may affect the market for your product. You should have read "Flint Water Crisis Caused By Interrupted Corrosion Control: Investigating "Ground Zero" Home", Env. Science & Technology, 2017. a. What is the current state of Flint, Michigan? Has the situation changed appreciably since this article was published in 2017? b. What are some actions that have taken place since then to minimize or prevent situations like this from happening again? You are strongly encouraged to bolster your response with existing peer-reviewed research or cogent arguments from the discussion forums. When a pure pubic good is conaumed a. this exciudes other people from the consumption of the good b. it does not reduce the avzilability of the good to be consumed by others and it does not prevent others from consuming to c. there will be less for others to consume d. the overall supply of the good increases What should a writer plan to include in the end of a narrative essay? Select two answers. Which of the following is an advantage of a strong culture?a) It makes merging with another organization simpler.b) It allows employees to identify themselves with the organizationc) It can be "too much of a good thing" if it creates extreme behaviors.d) It makes adapting to the environment less difficult.e) It attracts and retains similar kinds of employees. A patient presented with anaemia to the hospital and her sample was sent to the blood bank for urgent grouping and crossmatching for 2 units of blood. Below are her blood grouping results:Anti-A Anti-B Anti-A,B Anti-D A1 Cells B Cells O Cells1+ 0 2+ 3+ 2+ 4+ 0I. Comment on the results.II. What are the possible causes of this results? 10) List three organ systems responsible for regulating body temperature. 11) Explain the differences between the two broad classes of membrane proteins. You pay $500,000 for the rights to run a hotel, agreeing to a 25 year operating contract for which you receive $60,000 each year. If your required return is 6.25%, what is the PI this project?1.27860.2786.2.00000.4982 Type the correct answer in each box. If necessary, use / for the fraction bar(s).Find the solution for this system of equations.2x 3y = 2 x = 6y 5x = y = Explain some of the advantages smaller countries mayhave from their participation in international trade