In order to use earned value management technique to manage project performance, which of the following do you need

Answers

Answer 1

To use the earned value management technique for managing project performance, you will need the following:


Planned Value (PV): This is the authorized budget assigned to the work that is planned to be accomplished. It represents the value of the work that should have been completed at a specific point in time. Actual Cost (AC): This is the total cost incurred in completing the work performed up to a certain point in time. It includes direct and indirect costs associated with the project.. Earned Value (EV): This is the value of the work that has been completed at a specific point in time. It is derived from the physical progress of the project and is measured in terms of the budgeted cost of the work performed.


Cost Variance (CV) = EV - AC: This indicates whether the project is under or over budget. A positive value means the project is under budget, while a negative value means it is over budget. Schedule Variance (SV) = EV - PV: This shows whether the project is ahead or behind schedule. A positive value means the project is ahead of schedule, while a negative value means it is behind schedule.Cost Performance Index (CPI) = EV / AC: This represents the cost efficiency of the project. A value greater than 1 indicates the project is performing better than planned, while a value less than 1 indicates it is performing worse.

To know more about technique visit:

https://brainly.com/question/32713020

#SPJ11


Related Questions

the meeting notes state that the electrician could complete the wiring for both locations in two business days (or 16 hours). because the restaurants cannot close for a full day for the upgrade, the team estimates four business days (two half-days at each location) to complete the wiring. based on this information, what notes could you make to add context for this task in the project plan? select all that apply.

Answers

The electrician estimates completing the wiring for both locations in 2 business days, but the restaurants cannot close for a full day. The project plan accounts for this by allocating 4 business days with 2 half-days at each location.

To add context for the task in the project plan, the following notes could be made: the electrician estimates completing the wiring for both locations in two business days (16 hours), but the restaurants cannot close for a full day.



Therefore, the team estimates four business days, with two half-days allocated at each location. This approach minimizes disruption to restaurant operations. The project plan should consider specific half-day time slots for the electrician's work, ensuring continued service for customers during the upgrade.



In Summary   , The electrician estimates completing the wiring for both locations in 2 business days, but the restaurants cannot close for a full day. The project plan accounts for this by allocating 4 business days with 2 half-days at each location.

To learn more about electrician click here

brainly.com/question/27073052

#SPJ11

One of the most difficult issues associated with trying to structure a tax policy to satisfy horizontal equity is determining Group of answer choices whether or not a taxpayer falls within the highest income quintile. the level of transfer payments made to low-income groups.

Answers

Determining whether or not a taxpayer belongs in the highest income quintile is one of the most challenging problems involved in trying to develop a tax policy to fulfil horizontal equity.

The idea of horizontal fairness states that people with comparable financial circumstances should face the same tax obligations. It can be difficult to precisely classify taxpayers into income groups, particularly to identify individuals in the highest quintile. The determination is made more difficult by income measurement, categorization of different sources of income, and accounting for deductions and exemptions. Additionally, the assessment may become more challenging if income fluctuates over time. To ensure fair and equitable taxation, achieving horizontal equity necessitates careful study and accurate identification of taxpayers' income levels.

learn more about income here:

https://brainly.com/question/14732695

#SPJ11

Kellogg's Company and General Mills compete in the consumer packaged goods (CPG) sector. Refer to the following 2018 financial data for the two companies to answer the requirements S millions Total revenue Cost of sales and services Average accounts receivable Average inventory Average accounts payable GIS $13,140.6 515.2682 8,821.0 10.312.9 1,382.0 1.5572 1,273,5 1.5629 2.277.6 2.360.0 a. Compute the following measures for both companies Note: Do not round until your final answers, Round your final answers to two decimal places (for example, enter 6.78 for 6.775555). K GIS 0 1. Days sales outstanding (OSO) 2. Days inventory outstanding (DID) 3. Days payables outstanding (DPO) 4. Cash conversion cycle (CCC) 0 0 0 0 0 . b. Which company better manages its accounts receivable? c. Which company uses inventory more efficiently? d. Which company better manages its accounts payable? She

Answers

a. Compute the following measures for both companies: Days sales outstanding (DSO) can be calculated using the following formula: DSO = (Average Accounts Receivable / Net Credit Sales) * Number of Days.

K GIS Net Credit Sales $13,900.0 $13,140.6 Days in the year 365 365 DSO = (Average Accounts Receivable / Net Credit Sales) * Number of Days 0 30.59

Days inventory outstanding (DIO) can be calculated using the following formula: DIO = (Average Inventory / Cost of Goods Sold) * Number of Days

K GIS Cost of Goods Sold $9,030.0 $5152.682 Days in the year 365 365 DIO = (Average Inventory / Cost of Goods Sold) * Number of Days 0 68.68

Days payables outstanding (DPO) can be calculated using the following formula: DPO = (Average Accounts Payable / Cost of Sales) * Number of Days

K GIS Cost of Sales $6,727.8 $5152.682 Days in the year 365 365 DPO = (Average Accounts Payable / Cost of Sales) * Number of Days 38.04 66.73

The cash conversion cycle (CCC) can be calculated using the following formula: CCC = DSO + DIO – DPO

K GIS CCC 0 32.54

b. Kellogg's better manage its accounts receivable as its DSO is 0.

c. General Mills uses inventory more efficiently as its DIO is 68.68.

d. Kellogg's better manage its accounts payable as its DPO is 38.04.

For more questions on: Days sales outstanding

https://brainly.com/question/30657095

#SPJ8  

The calculated market value added (MVA) for XYZ Inc. is positive. Which of the following is indicated by this result?
a. The amount of wealth the company has created.
b. The amount of debt the company has accumulated
c. The total amount of resources available to the company
d. The success of the company's efforts at sustainability

Answers

A positive MVA is an indication that a company is successful and that it is creating value for its shareholders and the community.

When the calculated market value added (MVA) for a company like XYZ Inc. is positive, it indicates the amount of wealth that the company has created. This means that the company has generated more value for its stakeholders than the sum of capital contributed to it.

Investment opportunities provided by the company must be exceeding the total amount of capital it requires to finance those opportunities.

Thus, it means that the company has created more wealth than the capital cost of its projects. As a result, it is attracting more investors who are interested in the value of their investments.

MVA (Market Value Added) is the difference between the total market value of a company and the capital contributed by all stakeholders.

It is calculated by subtracting the amount of capital invested in a company from the company's total market capitalization. Therefore, it reveals the amount of wealth created by the company over and above its cost of capital. MVA is an indicator of the success of the company.

A positive MVA indicates that the company has been successful in creating value for its shareholders. MVA takes into account the total amount of capital invested in the company and the rate of return on that investment.

If a company has a positive MVA, it means that the company's value is greater than the total amount of capital invested in it. It is an indication that the company is generating value for its shareholders and is a profitable company. MVA can also be used to measure the company's efforts at sustainability.

If a company has a positive MVA, it shows that the company is managing its resources efficiently and that it is using its resources to create value for its shareholders and the community. It shows that the company is sustainable and that it has a long-term view of its operations.

For more such questions on shareholders

https://brainly.com/question/28452798

#SPJ8

The risk-free rate is 3%, the required return on the market is 12%, and Omega's stock has a beta of 0.8. The risk premium on Omega stock is

Answers

To calculate the risk premium on Omega's stock, we first need to understand the relationship between the risk-free rate, the required return on the market, and the stock's beta.

The risk-free rate is the return an investor expects to receive from an investment with zero risk. In this case, the risk-free rate is 3%.

The required return on the market is the expected return from investing in the overall market. It represents the compensation investors require for taking on market risk. Here, the required return on the market is 12%.

The beta of a stock measures its sensitivity to market movements. A beta of 0.8 indicates that Omega's stock is less volatile than the market.

To calculate the risk premium on Omega's stock, we use the following formula:

Risk Premium = (Required Return on the Market - Risk-Free Rate) * Beta

Substituting the given values into the formula, we get:

Risk Premium = (12% - 3%) * 0.8
Risk Premium = 0.09 * 0.8
Risk Premium = 0.072

Therefore, the risk premium on Omega's stock is 0.072, or 7.2%.

To know more about relationship visit :-
https://brainly.com/question/33265151
#SPJ11

The need to study economics would cease to exist if:__________

A. the government stopped controlling people's actions.

B. people were free to make decisions on their own.

C. people put forth the effort required to attain the goods and services they wanted.

D. people earned more than they spent.

E. there were enough resources to produce all the goods and services people would like to obtain.

Answers

The need to study economics would not cease to exist based on any of the options provided (A, B, C, D, or E).

Economics is a social science that studies how individuals, businesses, and societies allocate scarce resources to meet unlimited wants and needs. It explores how choices, incentives, markets, and policies shape economic outcomes.

Let's examine each option:

A. The government stopped controlling people's actions: While reducing government control over people's actions may increase individual freedom and market efficiency, it would not eliminate the need to study economics. Economics encompasses a wide range of topics beyond government intervention, including supply and demand, production, distribution, consumption, and macroeconomic factors like inflation and unemployment.

B. People were free to make decisions on their own: Similar to the previous option, individual freedom in decision-making is an important aspect of economics, but it does not negate the need to study the subject. Economics examines the consequences of individual choices, market interactions, and the impact of various factors on economic outcomes.

C. People put forth the effort required to attain the goods and services they wanted: While individual effort and motivation are crucial for economic activity, economics goes beyond individual effort to analyze broader economic phenomena. It studies factors such as market dynamics, price mechanisms, resource allocation, income distribution, economic growth, and societal well-being.

D. People earned more than they spent: While personal financial stability is desirable, individual financial situations do not eliminate the need for economic analysis. Economics encompasses topics such as investment, savings, fiscal policy, monetary policy, and the broader implications of income and wealth distribution.

E. There were enough resources to produce all the goods and services people would like to obtain: This option assumes a scenario of unlimited resources, which is unrealistic. Economics is fundamentally concerned with scarcity, which means that resources are limited relative to unlimited wants and needs. The study of economics helps understand how societies allocate scarce resources efficiently and make choices in the face of scarcity.

In summary, the need to study economics is not contingent on any single factor listed in the options. Economics examines complex interactions, choices, trade-offs, and decision-making processes that occur at individual, business, and societal levels, regardless of specific circumstances or conditions.

for more questions on economics

https://brainly.com/question/780900

#SPJ8

Greta is the new HR Manager of a small company. The previous HR Manager kept every document he had access to in the past 10 years of his job at the firm, but Greta is determined to clear out the unnecessary documents. In the context of Equal Employment Opportunity Commission (EEOC) requirements, Greta should keep all applications and hiring-related documents and records for _____ before they can be discarded.

Answers

According to Equal Employment Opportunity Commission (EEOC) requirements,

Greta should keep all applications and hiring-related documents and records for at least 1 year before they can be discarded.

This includes resumes, job applications, interview notes, and any other documents related to the hiring process.

learn more about Equal Employment Opportunity Commissionon :

https://brainly.com/question/14774625

#SPJ11

a 6.35 percent coupon bond with 30 years left to maturity is priced to offer a 5.7 percent yield to maturity. you believe that in one year, the yield to maturity will be 6.2 percent.

Answers

The bond's price will decrease as its yield to maturity increases, causing the value to decline. This is because the bond's coupon rate is lower than the expected yield to maturity, making it less attractive.

When a bond's yield to maturity exceeds its coupon rate, the bond's price tends to decrease. In this case, the bond has a 6.35 percent coupon rate, but it is currently priced to offer a lower yield to maturity of 5.7 percent. Since you believe that the yield to maturity will increase to 6.2 percent in one year, the bond's price is expected to decline to align with the higher yield. Investors will demand a lower price for the bond due to the expectation of a better return on their investment.

Learn more about price here:

https://brainly.com/question/19091385

#SPJ11

Using the medium you chose in response to the last question above (email, memo, or face-to-face meeting), prepare your communication to Natalie. Explain to her why videoconferencing is not a suitable medium for announcing a layoff decision.

Answers

Subject: Regarding Layoff Announcement: Video conferencing Not Recommended
Dear Natalie,
I hope this email finds you well. I wanted to discuss the recent inquiry regarding the suitability of videoconferencing as a medium for announcing a layoff decision. After careful consideration, I would like to explain why videoconferencing may not be the most appropriate choice for this purpose.
Firstly, videoconferencing lacks the personal touch and sensitivity that is crucial when delivering difficult news such as a layoff decision. Face-to-face communication allows for better non-verbal cues, such as facial expressions and body language, which can help convey empathy and support during challenging conversations. These cues can be missed or misinterpreted through videoconferencing, potentially leading to misunderstandings or increased emotional distress for the individuals involved.
Secondly, the impact of a layoff decision is often deeply personal and can generate a wide range of emotional reactions. In-person meetings provide a safer and more controlled environment where employees can express their concerns, ask questions, and receive immediate feedback. The lack of physical presence in videoconferencing may hinder open and honest communication, leading to a less effective and satisfactory experience for all parties involved.
Lastly, the delivery of sensitive news requires privacy and confidentiality to ensure the well-being and dignity of the individuals affected. Videoconferencing platforms may not guarantee the same level of security as a face-to-face meeting, potentially putting sensitive information at risk of unauthorized access or unintentional leaks.
Considering these factors, I would recommend exploring alternative mediums such as face-to-face meetings or carefully crafted memos to ensure a more compassionate and effective delivery of the layoff announcement.
I hope this explanation clarifies our perspective on the matter. Should you have any further questions or require additional information, please feel free to reach out. We are here to support you throughout this process.
Thank you for your understanding.
Best regards,
[Your Name]

To know more about Layoff visit:

https://brainly.com/question/1357989

#SPJ11

rodriguez company pays $326,430 for real estate with land, land improvements, and a building. land is appraised at $247,500; land improvements are appraised at $110,000; and the building is appraised at $192,500. 1. allocate the total cost among the three assets. 2. prepare the journal entry to record the purchase.

Answers

1.The allocated cost of land is Land is  $146,893.50, Land improvements is   $65,286, Building is  $114,250.50. 2. The journal entry are  Debit land A/c $146,893.50, Land improvements A/c $65,286, Building A/c  $114,250.50 and credit Cash A/c $326,430

To allocate the total cost among the three assets, we need to determine the proportionate value of each asset in relation to the total appraised value of all the assets.

1. Calculate the total appraised value of all the assets:

Total appraised value = Land + Land improvements + Building

Total appraised value = $247,500 + $110,000 + $192,500

Total appraised value = $550,000

ii) Calculate the proportionate value of each asset:

Land proportion = Land appraised value / Total appraised value

Land proportion = $247,500 / $550,000

Land proportion = 0.45

Land improvements proportion = Land improvements appraised value / Total appraised value

Land improvements proportion = $110,000 / $550,000

Land improvements proportion = 0.2

Building proportion = Building appraised value / Total appraised value

Building proportion = $192,500 / $550,000

Building proportion = 0.35

iii) Allocate the total cost among the three assets:

Land cost = Total cost * Land proportion

Land cost = $326,430 * 0.45

Land cost = $146,893.50

Land improvements cost = Total cost * Land improvements proportion

Land improvements cost = $326,430 * 0.2

Land improvements cost = $65,286

Building cost = Total cost * Building proportion

Building cost = $326,430 * 0.35

Building cost = $114,250.50

Therefore, the allocated cost for each asset is as follows:

Land: $146,893.50

Land improvements: $65,286

Building: $114,250.50

2. Prepare the journal entry to record the purchase:

Assuming the company paid in cash, the journal entry would be as follows:

Land (Asset)        $146,893.50

Land Improvements (Asset)   $65,286

Building (Asset)    $114,250.50

To Cash (Asset)        $326,430

To record the purchase of real estate with land, land improvements, and a building at an allocated cost.

To know more about cost  here

https://brainly.com/question/33042929

#SPJ4

Which of the following transactions would have no effect on total assets, total liabilities, or owner's equity? O A. purchasing supplies on account B. purchasing supplies for cash O C. payment of a liability D. borrowing cash by issuing a note payable

Answers

Option B: Buying supplies for cash has no impact on total assets, liabilities, or owner's equity.

Option B: Buying supplies for cash is the transaction that has no impact on total assets, total liabilities, or owner's equity.

When a company pays cash for supplies, it is exchanging one asset, cash, for another, supplies. Because the business is only converting one type of asset (cash) into another type of asset (supply), this transaction has no impact on overall assets. Due to the absence of liabilities (debts) or owner's equity (capital or retained earnings) in this transaction, the total liabilities and owner's equity are unchanged.

In conclusion, paying cash for supplies has no effect on the company's overall financial situation in terms of total assets, total liabilities, or owner equity.

Learn more about transactions  here:

https://brainly.com/question/24730931

#SPJ11

how
could a committee ensure the success of a employee program that was
developed & implemented that encompassed motivation
andempowerment?

Answers

To ensure the success of an employee program that was developed and implemented that encompassed motivation and empowerment, the committee could take the following steps:

1. Set clear and achievable goals and objectives: To ensure the success of the employee program, the committee should set clear and achievable goals and objectives that align with the organization's vision, mission, and values. These goals and objectives should be specific, measurable, achievable, relevant, and time-bound.

2. Involve employees in the program development and implementation: Employees should be involved in the program development and implementation process. They should be given an opportunity to provide feedback on the program, offer suggestions, and make recommendations. This will help to create a sense of ownership and commitment towards the program.

3. Provide adequate resources: The committee should ensure that the necessary resources, including funds, technology, and equipment, are available to implement the program successfully.

4. Communicate effectively: The committee should communicate the program's purpose, goals, and objectives clearly to all employees. This will help employees understand the program's importance and how it will benefit them.

5. Provide necessary training and development: The committee should provide necessary training and development to employees to ensure they have the skills and knowledge required to participate in the program successfully.

6. Monitor and evaluate the program: The committee should regularly monitor and evaluate the program to ensure it is achieving its goals and objectives. This will help identify areas that need improvement and allow for adjustments to be made as necessary.

Learn more about motivation at

https://brainly.com/question/14290345

#SPJ11

Concrete measures of various aspects of marketing performance are called ________.

Answers

Concrete measures of various aspects of marketing performance are called key performance indicators (KPIs). KPIs are specific metrics used to evaluate the effectiveness and success of marketing activities. They provide a quantifiable way to assess marketing performance and track progress towards goals.

There are various types of KPIs that can be used to measure different aspects of marketing performance. Some examples include:
1. Conversion Rate: This KPI measures the percentage of website visitors or leads that take a desired action, such as making a purchase or filling out a form. It helps assess the effectiveness of marketing campaigns in driving conversions.

2. Customer Lifetime Value (CLV): CLV measures the predicted net profit a business expects to earn from a customer over their entire relationship. It helps evaluate the long-term value of acquiring and retaining customers.

3. Return on Investment (ROI): ROI measures the financial return on marketing investments. It calculates the ratio of the revenue generated from marketing activities to the cost of those activities, indicating the profitability of marketing efforts.

4. Brand Awareness: This KPI measures the level of recognition and familiarity consumers have with a brand. It can be assessed through surveys, social media mentions, or website traffic, and helps evaluate the effectiveness of brand-building initiatives.

5. Customer Satisfaction: This KPI measures the level of customer satisfaction with a product or service. It can be assessed through surveys, reviews, or customer feedback, and helps gauge the success of marketing efforts in meeting customer expectations.
By monitoring and analyzing these KPIs, marketers can gain insights into the performance of their marketing strategies and make data-driven decisions to optimize their campaigns. Overall, KPIs are essential tools for evaluating marketing performance and driving continuous improvement in marketing activities.

to know more about key performance indicators visit:

https://brainly.com/question/28283165

#SPJ11

During the month-end close process, on Dec 31, you find a transaction for $5,000 prepayment for rent ($2,500 for upcoming Jan and Feb of the following year). It was recorded as a Debit to Rent Expense and Credit to Cash. Question: Is the journal entry correct

Answers

During the month-end close process, on Dec 31, you find a transaction for $5,000 prepayment for rent ($2,500 for upcoming Jan and Feb of the following year). It was recorded as a Debit to Rent Expense and Credit to Cash. Is the journal entry correct?

The journal entry for the prepayment of rent is not correct. Here's the correct journal entry:1. Debit Prepaid Rent for $5,000: This represents the asset created for the prepayment of rent.2. Credit Cash for $5,000: This represents the outflow of cash for the prepayment.


The original journal entry recorded a Debit to Rent Expense, which would have immediately recognized the expense in the current period. However, since the payment was made for future months, it should have been recorded as a Prepaid Rent, which is an asset account. By recording the transaction as a Debit to Rent Expense, the expense was recognized too soon.

To know more about month-end close process visit:

https://brainly.com/question/32954944

#SPJ11

The springfield bank has total deposits of $13.5 million and total reserves of $2.2 million. the required reserve ratio is 12 percent. the springfield bank has excess reserves of?

Answers

To calculate the excess reserves of the Springfield Bank, we need to find the required reserves first. The required reserve ratio is 12 percent. The Springfield Bank has excess reserves of $0.58 million.

The required reserves would be 12 percent of the total deposits.
Total deposits = $13.5 million
Required reserve ratio = 12%
Required reserves = Total deposits * Required reserve ratio
Required reserves = $13.5 million * 0.12
Required reserves = $1.62 million
Now, to find the excess reserves, we subtract the required reserves from the total reserves.
Total reserves = $2.2 million
Required reserves = $1.62 million
Excess reserves = Total reserves - Required reserves
Excess reserves = $2.2 million - $1.62 million
Excess reserves = $0.58 million
Therefore, the Springfield Bank has excess reserves of $0.58 million.

To know more about Excess reserves, visit:

https://brainly.com/question/31633083

#SPJ11

BCD Corporation has an inventory turnover of 16 and an accounts payable turnover of 11. The accounts receivable period is 36 days. What is the length of the cash cycle?
This is the answer (25.63 days)

Answers

The length of the cash cycle for BCD Corporation is 25.63 days.

The cash cycle is calculated by subtracting the accounts payable turnover from the sum of the inventory turnover and the accounts receivable period.

Inventory turnover = 16

Accounts payable turnover = 11

Accounts receivable period = 36 days

Cash cycle = (Inventory turnover + Accounts receivable period) - Accounts payable turnover

Cash cycle = (16 + 36) - 11

Cash cycle = 52 - 11

Cash cycle = 41 days

Therefore, the length of the cash cycle for BCD Corporation is 41 days.

Learn more about Accounts here:

https://brainly.com/question/14138124

#SPJ11

a soup manufacturer encouraged its customers to share their ideas for new soup flavor combinations on a public forum on its website. then, the company asked these customers to vote on the ideas to determine which ones it should invest in developing. which characteristic of digital marketing does this scenario best describe?'

Answers

The characteristic of digital marketing that best describes this scenario is "crowdsourcing."

Crowdsourcing is when a company solicits ideas or feedback from a large group of people, usually through an online platform. In this case, the soup manufacturer encouraged its customers to share their ideas for new soup flavors on its website and asked them to vote on the ideas to determine which ones to develop.

This approach allows the company to engage its customers, gather valuable insights, and involve them in the product development process. By leveraging the power of the crowd, the company can benefit from diverse perspectives and potentially create products that align with customer preferences. This is an effective way to generate ideas, build customer loyalty, and drive innovation.

Learn more about digital marketing here:

https://brainly.com/question/29993752

#SPJ11

If there are two parties to the contract, there would be at least three identical executed contracts. One for the buyer, one for the seller, and one for: the office. the title company. the lender. the appraiser. PREVIOUS NEXT 7 of 75 Who does a licensee need consent from in order to disclose any information? The broker The principal The title company The appraiser PREVIOUS NEXT

Answers

A licensee requires the principal's consent to disclose information due to their duty of loyalty and confidentiality.

A licensee normally needs the principal's permission before disclosing any information. The entity or person that the licensee is representing or performing services for in the transaction is referred to as the principle. The buyer or seller who has hired the licensee's services is often the principal. The licensee has a duty of loyalty and confidentiality to the principle because they are acting as their representative. Therefore, in order to make sure they are working in accordance with their agreement and safeguarding the secrecy of the information, the licensee would need the principal's permission before exposing any information collected during the course of their professional relationship.

Learn more about licensee here:

https://brainly.com/question/29804028

#SPJ11

michael's hardware purchased merchandise on account from hardware supply for $690. the journal entry for michael's hardware to record this transaction is

Answers

The journal entry can be made by Michael's Hardware to record this transaction:

Debit: Merchandise Inventory for $690

Credit: Accounts Payable for $690

When a company purchases goods on credit from a supplier, it is considered an account payable, which is a liability. Michael's Hardware acquired merchandise on account from Hardware Supply for $69.

Debit is the increase in the value of an asset account, whereas Credit is the increase in the value of a liability account.

Here, as Merchandise Inventory is an asset account, it is debited for $690 to reflect the increase in its value, while Accounts Payable, a liability account, is credited for the same amount to reflect the increase in the value of the company's obligation to pay back its debt to Hardware Supply.

Learn more about journal entry https://brainly.com/question/33045014

#SPJ11

what are the key strengths and weaknesses of the internal rate of return method of assessing capital projects?

Answers

Advantages of IRR: Considers time value of money, easy to understand (% return on investment).Disadvantages of IRR: Assumptions about reinvestment, issues with mutually exclusive or non-traditional cash flows, doesn't consider project size.

The internal rate of return (IRR) approach has a number of significant advantages. By discounting future cash flows, it first takes into account the time value of money and calculates the project's profitability over its whole life. Second, because IRR shows the % return on investment, it is simple to understand. IRR does, however, have some restrictions. It presumes that cash flows will be reinvested at the project's internal rate, which might not be practical. It also runs into problems with projects that are mutually exclusive or non-traditional cash flows, leading to many IRRs or no genuine answer. Additionally, because IRR doesn't take the project's size into consideration, results could be misinterpreted. IRR should therefore be used in conjunction with other evaluation techniques to help investors make wise investment decisions.

Learn more about IRR here:

https://brainly.com/question/31393609

#SPJ11

Which of the following best describes international financial reporting standards?
a. IFRS describe the generally accepted accounting principles that are currently used by all companies in the United States.
b. IFRS consist only of standards that have been issued since the IASB was formed in 2001.
c. IFRS are considered to be more concept-based than U.S. GAAP.
d. IFRS will be required to be used in the United States beginning in 2020.

Answers

The correct answer is: c. IFRS are considered to be more concept-based than U.S. GAAP.

International Financial Reporting Standards (IFRS) are a set of accounting standards developed by the International Accounting Standards Board (IASB). Unlike option a, IFRS is not currently used by all companies in the United States. Option b is incorrect because IFRS includes standards that were issued before the formation of the IASB in 2001. Option d is also incorrect as of the knowledge cutoff in 2021, as there is no specific requirement for the use of IFRS in the United States starting in 2020. Option c is the best description as IFRS is known for being more principle-based and focused on conceptual frameworks compared to the more rules-based U.S. Generally Accepted Accounting Principles (GAAP).

Learn more about considered here;

https://brainly.com/question/30746025

#SPJ11

the fixed and variable costs to produce an item are given along with the price at which an item is sold. fixed cost: variable cost per item: price at which the item is sold:

Answers

The price at which the item is sold represents the amount at which customers purchase the product. It is essential to compare the selling price to the total costs to assess the profitability .

The fixed cost refers to the costs that remain constant regardless of the quantity produced, such as rent, salaries, or equipment maintenance. Variable costs, on the other hand, change in relation to the quantity produced, including costs for raw materials, labor, or utilities.The price at which the item is sold represents the amount at which customers purchase the product. It is essential to compare the selling price to the total costs to assess the profitability of the item and make informed business decisions.profitability of the item and make informed business decisions.

learn more about purchase here:

https://brainly.com/question/32463125

#SPJ11

A firm just paid a dividend of $4.56. The dividend is expected to grow at a constant rate of 2.84% forever and the required rate of return is 13.43%. What is the value of the stock

Answers

To calculate the value of the stock, we can use the Gordon Growth Model. This model states that the value of a stock is equal to the dividend divided by the difference between the required rate of return and the growth rate.

In this case, the dividend is $4.56, the growth rate is 2.84%, and the required rate of return is 13.43%.

Using the Gordon Growth Model, we can calculate the value of the stock as follows:

Value of stock = Dividend / (Required rate of return - Growth rate)

Value of stock = $4.56 / (0.1343 - 0.0284)

Value of stock = $4.56 / 0.1059

Value of stock = $43.07 (rounded to two decimal places)

Therefore, the value of the stock is approximately $43.07.

To know more about Gordon Growth Model visit:

https://brainly.com/question/30355598

#SPJ11

All else constant, an increase in the discount rate will have what effect on the present value of a future cash flow received from a customer?

Answers

An increase in the discount rate will have a negative effect on the present value of a future cash flow received from a customer. The discount rate is used to determine the present value of future cash flows by accounting for the time value of money.



When the discount rate increases, it means that the rate of return required to justify an investment also increases. This implies that the value of money today is worth more than the value of money in the future, as the discount rate represents the opportunity cost of investing in a certain project rather than in other alternatives.  The higher the discount rate, the greater the reduction in present value. An increase in the discount rate decreases the present value of a future cash flow received from a customer. This is due to the higher required rate of return and the reduced value of money in the future compared to the present.

To know more about discount visit:

brainly.com/question/28304734

#SPJ11

Information about a company’s executive compensation practices can be found in a company’s:
Multiple Choice
A. annual report.
B. form 10-K.
C. proxy statement.
D. form 10-Q.

Answers

Information about a company's executive compensation practices can be found in the company's proxy statement. The proxy statement is a document that publicly traded companies are required to provide to shareholders before an annual meeting.

It contains important information about corporate governance matters, including executive compensation.Within the proxy statement, companies disclose details about the compensation packages and practices for their executives, such as the salaries, bonuses, stock options, and other forms of compensation awarded to top-level executives. It also includes information about any performance-based incentives, retirement plans, and other benefits provided to executives.The proxy statement is filed with the Securities and Exchange Commission (SEC) and is made available to shareholders to help them make informed decisions during the annual meeting, including voting on matters related to executive compensation While annual reports (option A) and form 10-K (option B) also provide information about a company's financial performance and operations, they may not necessarily include detailed information about executive compensation. Form 10-Q (option D) is a quarterly report that provides updates on a company's financial performance but is less likely to contain comprehensive information on executive compensation practices compared to the proxy statement.

learn more about compensation here:

https://brainly.com/question/28250225

#SPJ11

which of the following is true of a crisis situation in an organization? group of answer choices while responding to a crisis, a common message should be communicated to both internal and external audiences. a potential crisis situation cannot be determined in terms of areas of vulnerability. an accident crisis includes accidents or harm caused by human error as well as organizational misdeeds. the type of crisis should be identified during crisis response in order to better develop communication messages.

Answers

Among the given options, the statement that is true of a crisis situation in an organization is: "While responding to a crisis, a common message should be communicated to both internal and external audiences." Option A is the correct answer.

During a crisis situation in an organization, effective communication becomes crucial. In order to manage the situation and mitigate potential negative impacts, it is important to communicate a consistent and unified message to both internal and external audiences. Here's why:

Consistency and Clarity: Communicating a common message ensures that all stakeholders, both internal (employees, management, etc.) and external (customers, shareholders, media, etc.), receive consistent and clear information about the crisis. Transparency and Trust: When all stakeholders are provided with the same information, it demonstrates that the organization is taking the crisis seriously and is committed to addressing the situation responsibly.Managing Perception: By providing a common message, the organization can have more control over the narrative and manage the perception of the crisis.

Therefore, Option A is the correct answer.

For such more question on organization:

https://brainly.com/question/29641668

#SPJ8

whether all recorded transactions and events have happened and pertain to the entity is the basis of the

Answers

whether all recorded transactions and events have happened and pertain to the entity" is the basis of the accounting concept of accuracy and completeness.

What is the basis of the accounting concept of accuracy and completeness?The basis of the accounting concept of accuracy and completeness is whether all recorded transactions and events have happened and pertain to the entity.What is the concept of accuracy and completeness?Accuracy and completeness are two fundamental concepts of accounting. The concept of accuracy in accounting requires that all information related to financial transactions be recorded accurately and without errors or misrepresentations. The concept of completeness, on the other hand, requires that all financial transactions be recorded in a timely and accurate manner.In general, accounting relies on a number of core concepts, including the concepts of going concern, materiality, consistency, relevance, reliability, and comparability.

These concepts help to ensure that financial statements are prepared in accordance with generally accepted accounting principles (GAAP) and that they accurately reflect the financial position of the entity at the end of the accounting period.

Read more about comparability here;https://brainly.com/question/1404938

#SPJ11

Each year, Tom and Cindy Bates (married filing jointly) normally have itemized deductions of $20,000 (which includes an annual $4,000 pledge payment to their church). Upon the advice of a friend, they do the following: In early January 2019, they pay their pledge for 2018; during 2019, they pay the pledge for 2019; and in late December 2019, they prepay their pledge for 2020.

a. What are the Bateses trying to accomplish?

b. What would the Bates' total itemized deductions be if all three church pledge payments were made in 2019? Assume that the itemized deductions of $20,000 already included one year of the church pledge payments.

What will be the Bates' tax saving if their marginal tax bracket is 24% for all three years? (Assume that the standard deduction amounts for 2019 and 2020 are the same.) By concentrating their charitable contributions, their tax savings becomes $____.

c. Complete a letter to Tom and Cindy Bates (8212 Bridle Court, Reston, VA 20194) summarizing your analysis.

Answers

a. The Bateses are trying to maximize their tax deductions by concentrating their charitable contributions in one year. By prepaying their church pledge for 2020 in late December 2019 and paying their pledge for 2018 and 2019 in 2019, they aim to increase their itemized deductions for the year 2019.

b. If all three church pledge payments were made in 2019, the Bates' total itemized deductions would be $28,000. This includes their normal itemized deductions of $20,000 plus the additional $8,000 from the church pledge payments made in 2019. To calculate the tax savings, we need to consider their marginal tax bracket of 24% for all three years. Assuming that the standard deduction amounts for 2019 and 2020 are the same, the Bates' tax savings would be 24% of the additional $8,000 in itemized deductions made in 2019, which is $1,920.

c. Dear Tom and Cindy Bates, After analyzing your situation, it appears that you are trying to maximize your tax deductions by concentrating your charitable contributions in one year. By prepaying your church pledge for 2020 in late December 2019 and paying your pledge for 2018 and 2019 in 2019, you aim to increase your itemized deductions for the year 2019.

To know more about Bateses visit:

https://brainly.com/question/20708972

#SPJ11

if+a+4-year+bond+with+a+7%+coupon+and+a+10%+yield+to+maturity+is+currently+worth+$904.90,+how+much+will+it+be+worth+1+year+from+now+if+interest+rates+are+constant?

Answers

The bond will be worth $932.80 one year from now if interest rates remain constant.

When a bond is issued, it has a face value, a coupon rate, and a maturity date. The coupon rate represents the interest payments made by the issuer to the bondholder, expressed as a percentage of the face value. The yield to maturity (YTM) is the total return anticipated by an investor if the bond is held until maturity, taking into account its purchase price, coupon payments, and face value.

In this case, the bond has a 4-year maturity, a 7% coupon rate, and a yield to maturity of 10%. The bond is currently worth $904.90. To calculate its future value one year from now, assuming constant interest rates, we need to consider the coupon payments and the change in value.

The annual coupon payment is 7% of the face value, which is equal to 0.07 * face value. Since the face value is not provided in the question, we can calculate it using the current value of the bond.

$904.90 = (0.07 * face value) / (1 + 0.10)

$904.90 * (1 + 0.10) = 0.07 * face value

$995.39 = 0.07 * face value

face value = $995.39 / 0.07

To determine the future value of the bond one year from now, we need to calculate the coupon payment for the next year and the change in bond value.

Coupon payment = 0.07 * face value = 0.07 * ($995.39 / 0.07) = $995.39

Change in bond value = face value - current value = $995.39 - $904.90 = $90.49

Future value = current value + coupon payment + change in bond value

Future value = $904.90 + $995.39 + $90.49 = $1,990.78

Rounding the future value to two decimal places, the bond will be worth $932.80 one year from now if interest rates remain constant.

Learn more about Bond

brainly.com/question/31994049

#SPJ11

If the average annual rate of return for common stocks is 11.7 percent, and 4.0 percent for U.S. Treasury bills, what is the average market risk premium? A. 15.7 percent B. 4.0 percent C. 7.7 percent D. Not enough information is provided. E. I choose not to answer

Answers

The average market risk premium is 7.7%, calculated as the difference between the average stock return and the risk-free rate. Option C is correct.

By deducting the risk-free rate of return from the average rate of return for common stocks, the average market risk premium is determined. In this instance, the average rate of return for common stocks is reported as 11.7 percent, while the risk-free rate of return for U.S. Treasury notes is given as 4.0 percent.

As a result, the formula for calculating the average market risk premium is: Average Market Risk Premium = Average Rate of Return for Common Stocks - Risk-Free Rate of Return.

= 11.7% - 4.0% = 7.7%

Therefore, the market risk premium is 7.7% on average. Option C is the right response, so.

Learn more about market risk here:

https://brainly.com/question/33015902

#SPJ11

Other Questions
Solomon's is a walk-in clinic serving both adults and children. It is staffed by one receptionist, one pediatrician (who sees the children) and one internist (who sees the adults). All patients check in with the receptionist. When the system operates at capacity, the receptionists utilization is 100%. Patients are then seen by the appropriate physician. When the system operates at capacity, the utilization of the pediatrician is 93% and utilization of the internist is 93%. On average 60% of the clinics arrivals are adults. When the system operates at capacity, there are on average three adult patients and four pediatric patients (i.e., children) in the waiting room between registration and seeing a physician.A) Who has a longer theoretical flow time, adults or children? Or are they the same?B) Consider the buffer between registration and the physicians. When the system operates at capacity, After checking-in, What is the ratio of the average waiting time for adults relative to the average waiting time for the children? The contribution margin ratio measures:_____.a. profit per dollar of sales. b. the ratio of variable to fixed costs. c. contribution margin per dollar of sales. d. profit per unit. if merced river reached record flood heights what are two potential problems that might cause in yosemite valley Junker Renovation completely overhauls junked or abandoned cars. Data shows their 1970's models hold their value quite well. The value F(x) of one of these cars is given by F(x)=70 12x / x+1 , where x is the number of years since repurchase and F is in hundreds of dollars. Step 3 of 3 : What is the long term value of one of these cars? Which of the following is a way that digestion and absorption of carbohydrates differs from that of proteins?A. Only carbohydrate absorption involves secondary active transport driven by Na^+ gradients.B. Only protein absorption involves secondary active transport driven by H^+ gradients.C. Only carbohydrates can be digested by brush border enzymes.D. Protein absorption involves facilitated diffusion transporters that allow the digested monomers to enter the interstitial fluid across the basolateral membranes of gut epithelial cells, but this does not occur during absorption of carbohydrates. use the internet to look up the sds for 2.0 m sodium hydroxide, naoh, to answer the following questions: a) list the potential acute and chronic health effects. b) identify the first aid measures for ingestion. c) identify whether or not it is flammable d) identify the chemicals that potentially produce a dangerous reaction with naoh. e) describe how to handle small spills and the personal protective required to work with naoh. Examine the performance of the mixer system providing detailed operation, establish the key facts and important issues in the system and make a valid conclusion about recommendations for system improvement. a) Describe the circumstances when the limit of a sequence exits, and when it does not exist. Document a well detailed fitness goal of walking 8000 steps a day(include set backs and how it was overcomed) By applying the concept learned in the full-adder lab, perform the following addition: F = 2X + 2Y where X and Y are 4-bits binary inputs. Design the problem in Quartus as block diagram schematic. Then, verify its functionality by using waveform. a. 57. Match the antimicrobial agent with its mode of action (Choices may be used more than once, or not at all) ISONIAZID Inhibition of cell wall synthesis b. Injury to plasma membrane Inhibition of nucleic acid synthesis d. Inhibition of enzymatic activity e. Inhibition of protein synthesis C. 1. why do you think it took so long for france and england to mobilize their armies? 2. list the advantages that the english had at the battle of britain. 3. how did america he in the fighting against germany? 4. why do you think it was a bad idea for germany to invade russia? Pick a type of food that you enjoy. Before you start researching, state a hypothesis about the nutritional content of this food. Remember a hypothesis is an educated guess (and may be wrong), and a good hypothesis is specific.Then summarize what you learned from your research. Include an image of at least one molecule found in this food and briefly describe that molecule in terms of the atoms it is made of and potentially the chemical bonds that keep the atoms together. Is this a beneficial molecule to consume? Explain why. Did your research support your hypothesis? what is the magnification and the length of an astronomical telescope withFo=985mmFe=5.0mma. -5,197mmb.-140,985mmc.-120,197mmd.-167,990mme.-197,990mm Theories based on life transitions propose that crises are followed by ______. Group of answer choices conscientiousness interpersonal growth ego development periods of relative stability. Solving the quadratic equation using completing the square method. x^2+6x+1=0 ow much does Mars appear to shift when viewed from opposite sides of Earth, when it is 1.0 x 108 km from Earth? Earth's diameter is 1.3 x 104 km. A. 0.0082 arcseconds B. 27 arcseconds C. 18 arcminutes D. 4.4 x 105 degrees Exchange patterns for meal planning define food portions according to energy content. were originally developed for people with renal disease. are highly recommended over the USDA food patterns. Ogroup foods without regard to micronutrient content. find the value of an investment that is compounded continuously that has an initial value of $6500 that has a rate of 3.25% after 20 months. which of the following cannot be deferred using the installment sale method? (select all that apply.) multiple select question. loss on the sale of investment land gain on the sale of land used in a business depreciation recapture on sale of business assets gain on the sale of inventory items