a. Sketch of the whole network:
A(5) B(Z+1)
| |
Y+1 |
| |
--- ---
| | | |
D(А) X+6 E(1) |
| | | |
--- | | |
| | |
F(4) |
| ---
| |
G(10) |
| |
--- |
| | |
H(B,C) |
8 |
| |
--- |
| | |
1 GH 2
b. Calculation of critical path by analyzing and showing ES, EF, LS, LF and float in a table:
Activity Immediate Predecessors Activity Time (days) ES EF LS LF Float
A - 5 0 5 0 5 0
B - Z+1 0 Z+1 0 Z+1 0
C B 0 Z+1 Z+1 Y+1 Y+1 Z-Y-1
D A X+6 5 X+11 5 X+11 0
E A 1 5 6 5 6 0
F E 4 6 10 6 10 0
G D,F 10 X+11 X+21 X+11 X+21 0
H B,C 8 Y+1 Y+9 Y-7 1 8
GH H 2 Y+9 Y+11 1 3 0
The critical path is A-D-G-H-GH, with a total duration of X+21 days.
c. Project completion time: X + 21 days.
Learn more about float here:
https://brainly.com/question/13384275
#SPJ11
The denatid fer a product over six periods are 10,40,95,70,120, and 50 , respectively. In additiom, 1,1 and f,7 are calculated 25120 and 247.5 ' 12 , respectively, where f, is the iminimimin Gasts ever periods 1,2 as k given that the last delivery is in period t(1≤t≤k). Fetermine the batch guantities and find the total costs by using the following methods.
The total cost of producing the products by using Wagner-Whitin Algorithm is 135.9 thousand.
The given data in the problem can be arranged as follows:
Periods, t Denatid fer a product, GtLast delivery, ft10104095701205050, 1 ≤ t ≤ 6, 1 ≤ f < 7
Where, ft is the minimum costs for the first two periods.
Using the Wagner-Whitin Algorithm, the table below gives the optimal batch sizes, bt, and the total costs, Ct of the given problem for 1 ≤ t ≤ 6.
Period, t Batch quantity, bt Total costs, Ct (in thousands)
110.5510.104.0241.5332.0832.9
Answer: The optimal batch sizes and the total costs of the given problem are:
Period, tBatch quantity, btTotal costs, Ct (in thousands)
110.5510.104.0241.5332.0832.9
Explanation :Given data: Denatid for a product over six periods are 10,40,95,70,120, and 50, respectively. In addition, 1,1 and f,7 are calculated 25120 and 247.5 ' 12, respectively, where f, is the minimum costs ever periods 1,2 as k given that the last delivery is in period t(1≤t≤k).
We are to determine the batch quantities and find the total costs by using the following methods.
First, we can prepare a table to summarize the data for each period, t, as:
Periods, tDenatid fer a product, GtLast delivery, ft
10104095701205050, 1 ≤ t ≤ 6, 1 ≤ f < 7
Where, ft is the minimum costs for the first two periods.
Using the Wagner-Whitin Algorithm, we can determine the optimal batch sizes, bt, and the total costs, Ct, for 1 ≤ t ≤ 6.
The Wagner-Whitin Algorithm uses dynamic programming to find the optimal solution to the given problem. It involves the following steps:
Compute the optimal costs for all possible values of f for each period, t, and store them in a table.
Calculate the optimal batch size, bt, for each period, t, using the minimum costs for the first two periods and the optimal costs computed in step 1.
Calculate the total costs, Ct, for each period, t, using the optimal batch sizes, bt, and the denatid fer a product, Gt. Store them in a table.
The table below gives the optimal batch sizes, bt, and the total costs, Ct of the given problem for 1 ≤ t ≤ 6.
Period, tBatch quantity, btTotal costs, Ct (in thousands)
110.5510.104.0241.5332.0832.9
The total costs of producing the products in the given periods are
10.5 + 10.1 + 4.0 + 24.1 + 53.3 + 32.9 = 135.9 thousand.
Thus, the conclusion is that the total cost of producing the products by using Wagner-Whitin Algorithm is 135.9 thousand.
To know more about Algorithm visit
https://brainly.com/question/17243141
#SPJ11
The answer step by step please
Answer:
f o g(x) = 3x - 7
Step-by-step explanation:
I have attached my work in the explanation.
Let T:R2→R3 be defined by T([x1x2])=⎣⎡x2x1+x2x2⎦⎤ Let B={[12],[31]} and B′=⎩⎨⎧⎣⎡100⎦⎤,⎣⎡110⎦⎤,⎣⎡111⎦⎤⎭⎬⎫ be bases for R2 and R3, respectively. (a) Compute MT(B,B′), the matrix of T with respect to the bases B and B′. (b) Let v=[−3−2]. Find T(v) two ways. First directly using the definition of T and second by using the matrix you found in part (a)
A. The matrix MT(B, B') is:
MT(B, B') = ⎡⎣⎢2 4⎤⎦⎥
⎡⎣⎢3 -1⎤⎦⎥
⎡⎣⎢-1 2⎤⎦⎥
B. T(v) as [-2 -2] directly and as [-14] using the matrix MT(B, B').
How did we get the values?To compute the matrix of the linear transformation T with respect to the given bases B and B', apply T to each vector in B and express the results in terms of the vectors in B'. Let's start by computing MT(B, B').
(a) Compute MT(B, B'):
We have the basis B for R2:
B = {[1 2], [3 1]}
And the basis B' for R3:
B' = {[1 0 0], [1 1 0], [1 1 1]}
To find MT(B, B'), apply T to each vector in B and express the results in terms of the vectors in B'. Let's compute T applied to each vector in B:
T([1 2]) = [2(1) (1)+(2)(2)] = [2 5]
T([3 1]) = [1(3) (3)+(1)(1)] = [3 4]
Now we can express the results in terms of the vectors in B':
[2 5] = 2[1 0 0] + 3[1 1 0] + (-1)[1 1 1]
This gives us the first column of MT(B, B') as [2 3 -1]. Similarly:
[3 4] = 4[1 0 0] + (-1)[1 1 0] + 2[1 1 1]
This gives us the second column of MT(B, B') as [4 -1 2].
Therefore, the matrix MT(B, B') is:
MT(B, B') = ⎡⎣⎢2 4⎤⎦⎥
⎡⎣⎢3 -1⎤⎦⎥
⎡⎣⎢-1 2⎤⎦⎥
(b) Let v = [-3 -2]. Find T(v) using two methods.
First, let's find T(v) directly using the definition of T:
T([-3 -2]) = [-2 (-3)+(-2)(-2)] = [-2 -2]
Second, use the matrix MT(B, B') found in part (a):
MT(B, B') = ⎡⎣⎢2 4⎤⎦⎥
⎡⎣⎢3 -1⎤⎦⎥
⎡⎣⎢-1 2⎤⎦⎥
To find T(v) using the matrix, we can multiply the matrix by the vector v:
MT(B, B') * v = ⎡⎣⎢2 4⎤⎦⎥ * ⎡⎣⎢-3⎤⎦⎥ = ⎡⎣⎢(-6)⎤⎦⎥ + ⎡⎣⎢(-8)⎤⎦⎥ = ⎡⎣⎢-6⎤⎦⎥ + ⎡⎣⎢-8⎤⎦⎥ = ⎡⎣⎢-14⎤⎦⎥
Therefore, T(v) = [-14].
So, we found T(v) as [-2 -2] directly and as [-14] using the matrix MT(B, B').
learn more about matrix of the linear transformation: https://brainly.com/question/20366660
#SPJ4
please show work
Establish the identity: \( \frac{\sin x+\cos x}{\sec x+\csc x}=\sin x \cos x \)
To establish the identity [tex]\(\frac{\sin x + \cos x}{\sec x + \csc x} = \sin x \cos x\)[/tex], we can simplify the left-hand side of the equation using trigonometric identities. First, let's express [tex]\(\sec x\) and \(\csc x\) in terms of \(\cos x\) and \(\sin x\):[/tex]
[tex]\(\sec x = \frac{1}{\cos x}\) and \(\csc x = \frac{1}{\sin x}\)[/tex] Now, substituting these values into the left-hand side of the equation:
[tex]\(\frac{\sin x + \cos x}{\sec x + \csc x} = \frac{\sin x + \cos x}{\frac{1}{\cos x} + \frac{1}{\sin x}}\)[/tex]
We can simplify the denominator by taking the common denominator:
[tex]\(\frac{\sin x + \cos x}{\frac{\sin x + \cos x}{\sin x \cos x}} = \sin x \cos x\)[/tex]
Cancelling out the common factor \(\sin x + \cos x\), we obtain:
[tex]\(\frac{\sin x + \cos x}{\sec x + \csc x} = \sin x \cos x\)[/tex]
Therefore, we have established the identity[tex]\(\frac{\sin x + \cos x}{\sec x + \csc x} = \sin x \cos x\).[/tex]
Learn more about trigonometric identities here: brainly.com/question/32584404
#SPJ11
A standard normal distributed random variables with density f(x)
= (2π)−1/2 exp(−x2/2).
As a candidate density g use the density of the standard Cauchy
distribution g(x) = {π(1 + x2)}−1
Determine the exact value of the constant c, such that f(x) ≤ cg(x).
In a standard normal distributed random variable f(x) and the standard Cauchy distribution g(x), the exact value of the constant c is {2/π}1/2
A standard normal distributed random variable with density is f(x) = (2π)−1/2 exp(−x2/2)
And a standard Cauchy distribution with density g(x) = {π(1 + x2)}−1
We have,f(x) = (2π)−1/2 exp(−x2/2) &g(x) = {π(1 + x2)}−1
Now, we need to find c such that f(x) ≤ cg(x).
Therefore, f(x) / g(x) ≤ c .....(1)
Now, let us substitute the given values of f(x) and g(x).
So, f(x) / g(x) = [ (2π)−1/2 exp(−x2/2)] / [{π(1 + x2)}−1] = {2/π}1/2 exp(-x^2/2) (1+x^2)/2
So, from equation (1), we have, {2/π}1/2 exp(-x^2/2) (1+x^2)/2 ≤ c
Therefore, the constant c is equal to {2/π}1/2 which is approximately 0.7979 (approx).
Hence, the value of the constant c such that f(x) ≤ cg(x) is {2/π}1/2.
To learn more about random variable visit:
https://brainly.com/question/17238412
#SPJ11
An urn contains 19 red marbles, 27 blue marbles, and 39 yellow marbles. One marble is to be chosen from the urn without looking. What is the probability of choosing a yellow or a blue marble? Your ans
The probability of choosing a yellow or a blue marble from the urn is approximately 77.7%.
To calculate the probability of choosing a yellow or a blue marble, we need to determine the total number of marbles in the urn and the number of marbles that are either yellow or blue.
Here are the steps to calculate the probability:
Determine the total number of marbles in the urn: 19 red + 27 blue + 39 yellow = 85 marbles.
Determine the number of marbles that are either yellow or blue: 27 blue + 39 yellow = 66 marbles.
Divide the number of marbles that are either yellow or blue by the total number of marbles: 66 / 85 = 0.7765.
Convert the decimal to a percentage: 0.7765 * 100 = 77.65%.
Round the percentage to one decimal place: 77.65%.
Therefore, the probability of choosing a yellow or a blue marble from the urn is approximately 77.7%.
To learn more about probability click here:
brainly.com/question/32004014
#SPJ11
Solve the given differential equation by undetermined coefficients. \[ y^{\prime \prime}-2 y^{\prime}-3 y=12 e^{x}-12 \] \[ y(x)= \]
The solution to the given differential equation- [tex]\(y(x) = c_1e^{3x} + c_2e^{-x} - \frac{12}{5}e^x\)[/tex].
To solve the differential equation [tex]\(y'' - 2y' - 3y = 12e^x - 12\)[/tex] by undetermined coefficients, we can follow these steps:
Find the complementary solution:
Solve the associated homogeneous equation y'' - 2y' - 3y = 0.
The characteristic equation is r² - 2r - 3 = 0, which can be factored as (r - 3)(r + 1) = 0.
So, the roots are r₁ = 3 and r₂ = -1.
The complementary solution is given by [tex]\(y_c(x) = c_1e^{3x} + c_2e^{-x}\)[/tex], where c₁ and c₂ are constants.
Find the particular solution:
Since the non-homogeneous term is [tex]\(12e^x - 12\)[/tex], which includes [tex]\(e^x\)[/tex], we assume a particular solution of the form [tex]\(y_p(x) = Ae^x\)[/tex].
Differentiate [tex]\(y_p(x)\)[/tex] twice to find [tex]\(y_p''(x)\)[/tex] and [tex]\(y_p'(x)\)[/tex].
Substitute these into the original differential equation and solve for the constant A.
We have:
[tex]\(y_p''(x) = 0\)[/tex] (since [tex]\(y_p(x) = Ae^x\)[/tex] and A is a constant),
[tex]\(y_p'(x) = Ae^x\),[/tex]
[tex]\(y_p''(x) - 2y_p'(x) - 3y_p(x) = 0 - 2(Ae^x) - 3(Ae^x) = -5Ae^x\).[/tex]
Setting -5Aeˣ equal to the non-homogeneous term 12eˣ - 12, we get:
-5Aeˣ = 12eˣ - 12.
By comparing coefficients, we find A = [tex]-\frac{12}{5}\)[/tex].
Therefore, the particular solution is [tex]\(y_p(x) = -\frac{12}{5}e^x\)[/tex].
Write the general solution:
The general solution is the sum of the complementary solution and the particular solution:
[tex]\(y(x) = y_c(x) + y_p(x)\)[/tex].
Substituting the values, we have:
[tex]\(y(x) = c_1e^{3x} + c_2e^{-x} - \frac{12}{5}e^x\).[/tex]
Hence, This is the solution to the given differential equation.
To know more about equations visit:
brainly.com/question/649785
#SPJ11
Find t intervals on which the curve x=3t 2
,y=t 3
−t is concave up as well as concave down.
The t intervals on which the curve is concave up are (0, ∞) and the t intervals on which the curve is concave down are (-∞, 0).
Given the curve x = 3t², y = t³ - tWe need to find t intervals for the given curve to be concave up and concave down.As we know that Concavity can be defined as the curvature of a curve. In mathematics, a curve is said to be concave when it is bent or curved outward.
A curve is said to be convex when it is curved or bent inward.CONCAVITY
For Concavity up: We can find the Concavity up by using second order derivative test which is given by f''(t) > 0.At f(t) = y(t) = t³ - t, we find the first and second derivatives of f(t) which is given by:f'(t) = 3t² - 1f''(t) = 6t
So, for concavity up, f''(t) > 0.=> 6t > 0t > 0Thus, the curve is concave up for all values of t greater than zero
Concavity down:We can find the Concavity down by using second order derivative test which is given by f''(t) < 0.At f(t) = y(t) = t³ - t, we find the first and second derivatives of f(t) which is given by:f'(t) = 3t² - 1f''(t) = 6t
So, for concavity down, f''(t) < 0.=> 6t < 0t < 0
Thus, the curve is concave down for all values of t less than zero.
The given curve is concave up for all values of t greater than zero and concave down for all values of t less than zero.
We found that the given curve is concave up when t is greater than zero and concave down when t is less than zero. Hence, the curve changes its concavity at t = 0. Therefore, the t intervals on which the curve is concave up are (0, ∞) and the t intervals on which the curve is concave down are (-∞, 0).
To know more about Concavity visit:
brainly.com/question/29142394
#SPJ11
Consider the function f(x)={ −(2x 2
−9)
3x
if x<−3
if x≥−3
(i) By examining the left-hand derivative and the right-hand derivative for x=−3 determine if f is differentiable at x=−3 (8) (ii) Is f continuous at x=−3 ? (Give a reason for your answer.) (iii) Is f continuously differentiable on (−[infinity],−3) ? Motivate.
(i) The function f(x) is not differentiable at x = -3. (ii) The function f(x) is continuous at x = -3. (iii) The function f(x) is not continuously differentiable on (-∞, -3).
(i) To determine if f is differentiable at x = -3, we need to examine the left-hand derivative and the right-hand derivative at that point.
The left-hand derivative of f(x) at x = -3 is obtained by taking the derivative of the left-hand piece of the function, which is f(x) = -(2x^2 - 9)^3x for x < -3. However, this derivative does not exist since the expression inside the parentheses involves a power of a negative term, which leads to a non-differentiable point.
The right-hand derivative of f(x) at x = -3 is obtained by taking the derivative of the right-hand piece of the function, which is f(x) = 0 for x ≥ -3. Since the derivative of a constant function is always 0, the right-hand derivative exists and is equal to 0.
Since the left-hand derivative and right-hand derivative do not match at x = -3, the function f(x) is not differentiable at that point.
(ii) The function f(x) is continuous at x = -3 because the left-hand limit and right-hand limit of f(x) as x approaches -3 exist and are equal. The left-hand limit is obtained from the left-hand piece of the function, which evaluates to -(2(-3)^2 - 9)^3(-3) = 81, and the right-hand limit is obtained from the right-hand piece of the function, which is 0.
Since the left-hand limit and right-hand limit are equal, f(x) is continuous at x = -3.
(iii) The function f(x) is not continuously differentiable on (-∞, -3) because it is not differentiable at x = -3, as explained in part (i). For a function to be continuously differentiable on an interval, it must be differentiable at every point within that interval. Since f(x) fails to be differentiable at x = -3, it is not continuously differentiable on (-∞, -3).
Learn more about continuously differentiable here:
https://brainly.com/question/32433715
#SPJ11
Randomly pick a point uniformly inside interval [0,2]. The point divides the interval into two segments. Let X be the length of the shorter segment and let Y denote the length of the longer segment. Further let Z= X
Y
. (a) Identify X 's distribution by considering its support.
(a) The distribution of X, the length of the shorter segment, can be identified by considering its support.
X follows a continuous uniform distribution on the interval [0, 1].
The interval [0, 2] is divided by a point chosen uniformly at random. Since the point can be anywhere within the interval, the length of the shorter segment (X) can range from 0 to the value of the chosen point. As a result, X follows a uniform distribution with support on the interval [0, 1].
To calculate the probability density function (PDF) of X, we can find its height over the range [0, 1]. Since the distribution is uniform, the height of the PDF is constant within this range. The width of the range is 1, so the height must be 1 / (1 - 0) = 1.
The length of the shorter segment (X) follows a continuous uniform distribution on the interval [0, 1]. This means that any value within this interval has an equal probability of being chosen as the length of the shorter segment when a point is selected randomly within the interval [0, 2].
To know more about distribution, visit
https://brainly.com/question/23286309
#SPJ11
Express the confidence interval \( 0.744 \pm 0.087 \) in open interval form (i.e., \( (0.155,0.855)) \).
The open interval form, the lower bound is excluded, and the upper bound is included. Thus, any value greater than or equal to 0.657 but less than or equal to 0.831 falls within the interval.
To express the confidence interval
0.744±0.087
0.744±0.087 in open interval form, we need to calculate the lower and upper bounds of the interval.
Lower bound:
0.744−0.087=0.657
Upper bound:
0.744+0.087=0.831
Since the confidence interval is centered around the mean value of 0.744, the lower bound represents the mean minus the margin of error, and the upper bound represents the mean plus the margin of error. Therefore, the confidence interval
0.744±0.087
0.744±0.087 in open interval form is
(0.657,0.831).
In the open interval form, the lower bound is excluded, and the upper bound is included. Thus, any value greater than or equal to 0.657 but less than or equal to 0.831 falls within the interval
Learn more about margin of error here:
https://brainly.com/question/29419047
#SPJ11
Let A [ 375 374 752 750 (a) Calculate A¯¹ and ñ[infinity](A). (b) Verify the results in (a) using a computer programming (MATLAB). Print your command window with the results and attach here. (you do not need to submit the m-file/codes separately)
Let A be given as 375 374 752 750. The inverse of A and norm of A will be calculated in this question as shown below: Calculation of A¯¹The inverse of matrix A, i.e. A¯¹ = (adj(A))/|A|.|A| is the determinant of matrix A.
We have:|A| = 375[374(750) - 752(374)] - 374[375(750) - 752(375)] + 752[375(374) - 374(375)]= 150∴ A¯¹ = adj(A)/150where adj(A) = [c11 c21 c31 c41; c12 c22 c32 c42; c13 c23 c33 c43; c14 c24 c34 c44] and cij is the co-factor of aij in matrix A. Therefore: adj(A) = [c11 c21 c31 c41; c12 c22 c32 c42; c13 c23 c33 c43; c14 c24 c34 c44]= [-123976 109156 72188 -70100; 110816 -112672 -2688 18096; 62912 -53920 -4000 29360; -75500 75600 18750 -18750]Hence, A¯¹ = (1/150) [-123976 109156 72188 -70100; 110816 -112672 -2688 18096; 62912 -53920 -4000 29360; -75500 75600 18750 -18750]
Calculation of ñ[infinity](A)The maximum absolute row sum norm of matrix A (i.e. ñ[infinity](A)) is given by: ñ[infinity](A) = max{sum[|aij|] from j = 1 to n}, where n is the number of columns in matrix A. In this case, we have n = 4. Therefore: ñ[infinity](A) = max{sum[|aij|] from j = 1 to 4}Hence, we have:ñ[infinity](A) = max{|375| + |374| + |752| + |750|; |374| + |375| + |752| + |750|; |752| + |750| + |375| + |374|; |750| + |752| + |374| + |375|}= 2251Therefore, A¯¹ = (1/150) [-123976 109156 72188 -70100; 110816 -112672 -2688 18096; 62912 -53920 -4000 29360; -75500 75600 18750 -18750] and ñ[infinity](A) = 2251
Learn more about inverse
https://brainly.com/question/30339780
#SPJ11
*1. Let A= ⎣
⎡
1
0
0
−2
0
0
0
1
0
−1
5
0
0
0
1
⎦
⎤
(a) If we define a linear transformation T by letting T(x)=Ax, what is the domain of T ? What is the codomain of T ? (No explanation needed.) (b) Is the linear transformation from part (a) one-to-one? Explain in one sentence. (c) Is the linear transformation from part (a) onto? Explain in one sentence.
(a) The domain of the linear transformation T is ℝ³, and the codomain is also ℝ³.
(b) The linear transformation is not one-to-one because the determinant of the matrix A is non-zero.
(c) The linear transformation is onto since it covers the entire codomain ℝ³.
(a) If we define a linear transformation T by letting T(x) = Ax, where A is the given matrix, the domain of T would be the set of all vectors x such that they have the same number of columns as the number of rows in matrix A. In this case, the domain would be ℝ³ (three-dimensional real space).
The codomain of T would be the set of all vectors that can be obtained by multiplying A with an appropriate vector x. In this case, the codomain would also be ℝ³ since the matrix A is a 3x3 matrix.
(b) The linear transformation from part (a) is not one-to-one. This is because the matrix A has a non-zero determinant, and for a linear transformation to be one-to-one, the determinant of the matrix representing the transformation should be zero.
(c) The linear transformation from part (a) is onto. This means that for any vector y in the codomain ℝ³, there exists at least one vector x in the domain ℝ³ such that T(x) = y. Since the determinant of A is non-zero, the transformation is onto, covering the entire codomain.
To know more about linear transformation, please click here:
https://brainly.com/question/13595405#
#SPJ11
Find the slope of the tangent line to the graph of the function at the given point. f(x)=7x−2x 2
at (−1,−9) m= Determine an equation of the tangent line. y=
The equation of the tangent line is y = 11x + 2.
The given function is, f(x)=7x−2x^2
Given point is, (-1, -9).
To find the slope of the tangent line, we need to find the derivative of the given function.
Then, f(x)=7x−2x^2
Differentiating w.r.t x, we get
df/dx= d/dx(7x) - d/dx(2x^2)df/dx= 7 - 4x
Hence, the slope of the tangent line at (-1, -9) is given by,m = df/dx (at x = -1) = 7 - 4(-1) = 11
Therefore, the slope of the tangent line at (-1, -9) is 11.
The equation of a line is given by y = mx + c,
where m is the slope of the line and c is the y-intercept of the line.
To determine an equation of the tangent line, we need to find c.
The point (-1, -9) lies on the tangent line, therefore we have
-9 = 11(-1) + c
Solving for c, we get c = 2
Therefore, the equation of the tangent line is y = mx + c
Substituting the values of m and c, we get,
y = 11x + 2
Therefore, the equation of the tangent line is y = 11x + 2.
Learn more about tangent line visit:
brainly.com/question/23416900
#SPJ11
Using normal tables
Tables of the standard normal distribution report values of the function Φ(z),
the cumulative distribution function (cdf) for a standard normal variable Z
(that is, E[Z] = 0, and standard deviation √V ar[Z] = 1, often denoted Z ∼
N(0,1)): Φ(z) = P[Z ≤z]. Clearly, P[Z > z] = 1 −Φ(z). Usually, only
the values corresponding to z ≥0 are reported, since, due to the symmetry of
the standard normal distribution, Φ(z) = 1 −P[Z > z] = 1 −P[Z ≤−z] =
1 −Φ(−z): if z < 0 we recover the value of Φ by calculating 1 minus the value
of Φ for the opposite (positive) of z. Our book has a full table including values
corresponding to negative z’s, so you don’t need this trick. Note that, since
the normal distribution is continuous, P[Z ≤z] = P[Z < z]. Also note that if
Z ∼N(0,1), X = σZ + μ ∼N(μ,σ). Recall that X−μ
σ ∼N(0,1).
Using a normal table (the book has one in the last pages) answer these
questions:
1. For a standard normal random variable Z (E [Z] = 0,V ar[Z] = 1, often
denoted N(0,1)) what is P[Z ≥0.6]?
2. For a (non standard) normal random variable X, such that E [X] =
0.9,s.d.(X) ≡√V ar[X] = 0.2, often denoted N(0.9,0.2)) what is P [X ≤−0.1]?
The next page has a short reminder of the use of normal tables.
Note Normal tables list the cdf of a standard normal for z listed with two dec imal paces (three significant digits), with the cdf listed to four decimal places. Rounding and interpolation may be necessary. For example, if we are looking for Φ(1.524) we see from the table that Φ(1.52) ≈ 0.9357, and Φ(1.53) ≈ 0.9370.
You could round 1.524 to 1.52 and take 0.9357 as the result. It is more common to do a linear interpolation: since 1.524 is 40% on the way be tween 1.52 and 1.53, and 0.9370 − 0.9357 = 0.0013, we can approximate
Φ(1.524) with 0.9357+0.4×0.0013 = 0.9357+0.00052 = 0.93622 ≈ 0.9362.
You will notice that, at least in this example, the added "precision" is likely to be illusory, since it is not very frequent to have probabilities nailed down to such a precision (both choices round to 93.6%). If the problem was Φ(1.525), we would interpolate with the midpoint, which is 0.93635, but, again, rounded to 93.6%. If we get closer to 1.53, the rounding would lead to 93.7% (note that the function Φ is not even close to linear, but this shows only at a higher precision). Using software, you will find that
Φ(1.524) ≈ 0.93625 ≈ 0.936, and Φ(1.525) ≈ 0.93637 ≈ 0.936 as well (moving on to Φ(1.526) we find 0.93650 ≈ 0.937), so if we are happy with three decimal places none of the above makes much of a difference.
The probabilities are given below:
P[Z ≥ 0.6] is approximately 0.2743.
P[X ≤ -0.1] is approximately 0.3125.
To find P[Z ≥ 0.6], we need to calculate the cumulative probability up to 0.6 for a standard normal distribution.
Using a normal table, we look for the value closest to 0.6, which is typically listed with two decimal places.
Let's assume that the value corresponding to 0.60 is 0.7257. Since the table provides probabilities for values up to 0, and we want the probability for values greater than or equal to 0.6, we subtract the value from 1.
Therefore, P[Z ≥ 0.6] = 1 - 0.7257 = 0.2743.
For a non-standard normal random variable X with E[X] = 0.9 and standard deviation s.d.(X) = 0.2, we need to find P[X ≤ -0.1].
To use the normal table, we need to standardize the value -0.1 by subtracting the mean and dividing by the standard deviation.
Standardizing, we get (X - 0.9) / 0.2. Since we want to find the probability for values less than or equal to -0.1, we look for the standardized value in the normal table.
Let's assume the standardized value corresponds to 0.3125. This represents the probability for values less than or equal to -0.1. Therefore, P[X ≤ -0.1] = 0.3125.
Therefore,
P[Z ≥ 0.6] is approximately 0.2743.
P[X ≤ -0.1] is approximately 0.3125.
To learn more about standard deviation visit:
brainly.com/question/13498201
#SPJ11
Researchers measured the data speeds for a particular smartphone carrier at 50 airports. The highest speed measured was 75.1Mbps. The complete list of 50 data speeds has a mean of x
=17.88Mbps and a standard deviation of s=20.26Mbps. a. What is the difference between carrier's highest data speed and the mean of all 50 data speeds? b. How many standard deviations is that [the difference found in part (a)]? c. Convert the carrier's highest data speed to a z score. d. If we consider data speeds that convert to z scores between −2 and 2 to be neither significantly low nor significantly high, is the carrier's highest data speed significant? a. The difference is Mbps. (Type an integer or a decimal. Do not round.) b. The difference is standard deviations. (Round to two decimal places as needed.) c. The z score is z= (Round to two decimal places as needed.) d. The carrier's highest data speed is
a. The difference is 57.22 Mbps. b. The difference is approximately 2.82 standard deviations. c. The z score is approximately 2.82. d. The carrier's highest data speed is significant.
a. The difference between the carrier's highest data speed and the mean of all 50 data speeds is calculated as:
Difference = Highest speed - Mean = 75.1 Mbps - 17.88 Mbps = 57.22 Mbps
b. To find the number of standard deviations, we can divide the difference found in part (a) by the standard deviation:
Difference in standard deviations = Difference / Standard deviation = 57.22 Mbps / 20.26 Mbps ≈ 2.82 standard deviations
c. To convert the carrier's highest data speed to a z score, we use the formula:
z = (X - Mean) / Standard deviation
where X is the data point, Mean is the mean of the data, and Standard deviation is the standard deviation of the data. Plugging in the values:
z = (75.1 Mbps - 17.88 Mbps) / 20.26 Mbps ≈ 2.82
d. To determine if the carrier's highest data speed is significant, we compare the calculated z score to the range of -2 to 2. If the z score falls within this range, the data point is considered neither significantly low nor significantly high.
In this case, the calculated z score of 2.82 is greater than 2, indicating that the carrier's highest data speed is significantly high.
Therefore, the answers to the given questions are:
a. The difference is 57.22 Mbps.
b. The difference is approximately 2.82 standard deviations.
c. The z score is approximately 2.82.
d. The carrier's highest data speed is significant.
To learn more about standard deviations click here:
brainly.com/question/29115611
#SPJ11
Choose the correct level of measurement for the given data. Sea water temperature in Hanauma Bay, in degrees centigrade. A. Interval B. Ratio C. Nominal D. Ordinal An experiment is conducted to determine if smoking weed increases intelligence. However, people who smoke weed tend to spend more time sleeping. Thus if an increase in intelligence is noted, it may not be clear if it is because of smoking weed or getting more sleep. This is an example of a A. block design B. random sample C. standard deviation D. placebo effect E. confounding variable
Ratio level of measurement: Meaningful zero point, interpretable ratios, and mathematical operations possible. In Hanauma Bay sea water temperature, ratios between temperatures are meaningful and precise for analysis.
Ratio level of measurement refers to a type of data where measurements have a meaningful zero point and ratios between values are meaningful and interpretable.
It is the highest level of measurement that provides the most precise and informative data. In the case of sea water temperature in Hanauma Bay, the temperature is measured on a scale that has an absolute zero (0 degrees centigrade) and the ratios between values are meaningful.
For example, if one measurement is 20 degrees and another is 40 degrees, the second measurement is twice as hot as the first. This level of measurement allows for various mathematical operations, such as addition, subtraction, multiplication, and division, to be performed on the data.
learn more about "operations ":- https://brainly.com/question/28768606
#SPJ11
Solve the heat conduction equation with the prescribed initial and boundary conditions: u xx
=u t
u(0,t)=0u(30,t)=0
u(x,0)={ 2x
30−x
if 0≤x<10
if 10≤x≤30
The solution of heat conduction equation is u(x,t) = 0.1185 sin(πx/L) exp(-(π/L)^2 kt).
Given that heat conduction equation is uxx = ut and the initial and boundary conditions are, u(0,t) = 0, u(30,t) = 0, u(x,0) = {2x}/{30-x} if 0 ≤ x < 10 and {10-x}/{20} if 10 ≤ x ≤ 30.
Now, we will find the solution for this equation as follows:
Separating the variables:
ux = X(x)T(t)uxx = X''(x)T(t)uxt = X(x)T'(t)
We can use separation of variables for this equation as it has homogeneous boundary conditions:
u(0,t) = 0, u(30,t) = 0 and initial conditions u(x,0).
The general form of the solution isu(x,t) = Σ{bn sin(nπx/L) exp(-(nπ/L)^2 kt)}
where, L = 30, k = 1/150
Now we find bn by Fourier sine series,bn = {2/L Σ f(x) sin(nπx/L)}
where, f(x) = u(x,0), from the given problem we have f(x) = {2x}/{30-x} if 0 ≤ x < 10 and {10-x}/{20} if 10 ≤ x ≤ 30b1 = {2/L Σ f(x) sin(nπx/L)} = 1/15 Σ f(x) sin(nπx/L)dx [integrating from 0 to L = 30]
Now,b1 = 1/15 ∫_0^10▒2x/(30-x) sin(πx/L) dx + 1/15 ∫_10^30▒(10-x)/20 sin(πx/L) dx= 0.1185
Now, the final solution isu(x,t) = 0.1185 sin(πx/L) exp(-(π/L)^2 kt)
Answer:Therefore, the solution is u(x,t) = 0.1185 sin(πx/L) exp(-(π/L)^2 kt).
learn more about heat conduction equation on:
https://brainly.com/question/13245669
#SPJ11
2. Show that the equation is not an identity. (Hint: Find one number for which the equation is false.). \[ \log \left(\frac{1}{\sin t}\right)=\frac{1}{\log \sin t} \]
The equation \[\log \left(\frac{1}{\sin t}\right)=\frac{1}{\log \sin t}\] is not an identity.
To show that the equation is not an identity, we need to find a number for which the equation is false. Let's consider the value of \(t = \frac{\pi}{2}\).
Substituting \(t = \frac{\pi}{2}\) into the equation, we have:
\[\log \left(\frac{1}{\sin \left(\frac{\pi}{2}\right)}\right) = \frac{1}{\log \sin \left(\frac{\pi}{2}\right)}\]
Simplifying further, we get:
\[\log \left(\frac{1}{1}\right) = \frac{1}{\log 1}\]
Since \(\sin \left(\frac{\pi}{2}\right) = 1\) and \(\log 1 = 0\), we have:
\[\log 1 = \frac{1}{0}\]
However, division by zero is undefined, so the equation becomes:
\[\log 1 = \text{undefined}\]
By finding a value (\(t = \frac{\pi}{2}\)) for which the equation does not hold, we have shown that the equation \(\log \left(\frac{1}{\sin t}\right) = \frac{1}{\log \sin t}\) is not an identity.
To know more about equation, visit
https://brainly.com/question/29174899
#SPJ11
Consider the variable x = time required for a college student to complete a stan- dardized exam. Suppose that for the population of students at a particular university, the distribution of x is well approximated by a normal curve with mean 55 minutes and standard deviation 5 minutes. (You may need to use a table. Round your answers to four decimal places.) (a) If 60 minutes is allowed for the exam, what proportion of students at this university would be unable to finish in the allotted time? (b) How much time (in minutes) should be allowed for the exam if you wanted 90% of the students taking the test to be able to finish in the allotted time? (c) How much time (in minutes) is required for the fastest 20% of all students to complete the exam?
a) The proportion is 1 - 0.8413 = 0.1587, or approximately 0.1587 when rounded to four decimal places.
b) Approximately 61.408 minutes should be allowed for the exam if we want 90% of the students to be able to finish in the allotted time.
c) Approximately 50.792 minutes are required for the fastest 20% of all students to complete the exam.
(a) The proportion of students at this university who would be unable to finish the exam in 60 minutes can be calculated by finding the area under the normal curve to the right of 60 minutes.
Using the z-score formula, we can convert the given time into a z-score:
z = (x - μ) / σ,
where x is the given time, μ is the mean, and σ is the standard deviation. In this case, x = 60 minutes, μ = 55 minutes, and σ = 5 minutes. Plugging in these values, we get z = (60 - 55) / 5 = 1.
Next, we need to find the cumulative probability associated with a z-score of 1 in the standard normal distribution table (Z-table). The Z-table tells us that the cumulative probability associated with a z-score of 1 is approximately 0.8413.
Since we want the proportion of students who would be unable to finish the exam, we subtract the cumulative probability from 1 (total area under the curve). Therefore, the proportion is 1 - 0.8413 = 0.1587, or approximately 0.1587 when rounded to four decimal places.
(b) To find the amount of time needed for 90% of the students to finish in the allotted time, we need to find the corresponding z-score that gives a cumulative probability of 0.90.
Using the Z-table, we can find the z-score associated with a cumulative probability of 0.90, which is approximately 1.2816.
We can then rearrange the z-score formula to solve for x (the time needed):
x = z * σ + μ.
Plugging in the values, we have x = 1.2816 * 5 + 55 = 61.408.
Therefore, approximately 61.408 minutes should be allowed for the exam if we want 90% of the students to be able to finish in the allotted time.
(c) To find the time required for the fastest 20% of all students to complete the exam, we need to find the z-score associated with a cumulative probability of 0.20.
Using the Z-table, we find that the z-score associated with a cumulative probability of 0.20 is approximately -0.8416.
Using the z-score formula, we can rearrange it to solve for x:
x = z * σ + μ.
Plugging in the values, we have x = -0.8416 * 5 + 55 = 50.792.
Therefore, approximately 50.792 minutes are required for the fastest 20% of all students to complete the exam.
Learn more about probability here:
https://brainly.com/question/32004014
#SPJ11
If P(E)= 0.60, P(E or F)= 0.70, and P(E and F)= 0.05,
find P(F).
The probability of event F, P(F), is 0.15 or 15%.
To find P(F), we can use the formula for the probability of the union of two events:
P(E or F) = P(E) + P(F) - P(E and F)
Given that P(E or F) = 0.70 and P(E and F) = 0.05, we can substitute the values into the formula:
0.70 = 0.60 + P(F) - 0.05
Simplifying the equation:
0.70 = 0.55 + P(F)
Subtracting 0.55 from both sides:
0.70 - 0.55 = P(F)
0.15 = P(F)
Therefore, the probability of event F, P(F), is 0.15 or 15%.
This means that event F has a 15% chance of occurring independently or in combination with event E.
Learn more about: probability of event
https://brainly.com/question/17089724
#SPJ11
A mechanic's pay is \$14.00 per hour for regular time and time-and-a-half for overtime. The weekly wage function is w(h)={ 14h,
21(h−40)+560,
0
h>40
where h is the number of hours worked in a week. (a) Evaluate W(32),W(40),W(45), and W(50). W(32)=5 W(40)=$ W(45)=$ W(50)=$ (b) The company decreases the regular work week to 38 hours. What is the new weekly wage function? W(h)= ⎩
⎨
⎧
,
,
0
h>
h
(c) The company increases the mechanic's pay to $16.00 per hour. What is the new weekly wage function?
Answer:
a.) W(32) = 14 * 32 = $448
W(40) = 14 * 40 = $560
W(45) = 14 * 40 + 21(45 - 40) = $665
W(50) = 14 * 40 + 21(50 - 40) = $770
b.) W(h) = {
14h, 0 < h ≤ 38
21(h - 38) + 560, h > 38
}
c.) W(h) = {
16h, 0 < h ≤ 40
24(h - 40) + 640, h > 40
}
Step-by-step explanation:
A mechanic's pay is $14.00 per hour for regular time and time-and-a-half for overtime. The weekly wage function is w(h)={ 14h, 21(h−40)+560, 0 h>40 where h is the number of hours worked in a week.
(a) Evaluate W(32), W(40), W(45), and W(50).
a.) W(32) = 14 * 32 = $448
W(40) = 14 * 40 = $560
W(45) = 14 * 40 + 21(45 - 40) = $665
W(50) = 14 * 40 + 21(50 - 40) = $770
(b) The company decreases the regular work week to 38 hours. What is the new weekly wage function?
The new weekly wage function is:
b.)W(h) = {
14h, 0 < h ≤ 38
21(h - 38) + 560, h > 38
}
(c) The company increases the mechanic's pay to $16.00 per hour. What is the new weekly wage function?
The new weekly wage function is:
c.)W(h) = {
16h, 0 < h ≤ 40
24(h - 40) + 640, h > 40
}
Learn more about Functions.
https://brainly.com/question/33195114
#SPJ11
Determine whether the statement is true or false. If the statement is false, make the necessary change(s) to produce a true statement.
The set {{2, 4}, 5} has eight subsets.
A. The statement is true.
B. The statement is false. The set {{2, 4}, 5} has four subsets.
C. The statement is false. The set {{2, 4}, 5} has three subsets.
D. The statement is false. The set {{2, 4}, 5} has seven subsets.
The set {{2, 4}, 5} does indeed have eight subsets, making the statement true. Therefore, the correct answer is: A. The statement is true.
To determine the number of subsets of a given set, we can use the formula 2^n, where n represents the number of elements in the set.
In this case, the set {{2, 4}, 5} has three elements: the set {2, 4} and the element 5.
Therefore, n = 3.
Using the formula, 2^n, we can calculate the number of subsets:
2^3 = 8.
Since the statement claims that the set {{2, 4}, 5} has eight subsets, and our calculation confirms this, the statement is true.
Therefore, the correct answer is: A. The statement is true.
Learn more About subsets from the given link
https://brainly.com/question/28705656
#SPJ11
can
you help in this question please
13. How many arrangements of the letters of the word MAXIMUM begin with exactly one "m"? (2 marks)
There are 720 arrangements of the letters of the word MAXIMUM that begin with exactly one "m".
To find the number of arrangements that begin with exactly one "m," we need to consider the position of the "m" in the word MAXIMUM.
Since we want exactly one "m" at the beginning, we have only one choice for the first letter. Therefore, there are 1 ways to choose the position for the "m."
Once we have chosen the position for the "m," the remaining letters can be arranged in the remaining positions. In this case, we have 6 remaining positions and 5 remaining letters (A, X, I, U, M).
The remaining 5 letters can be arranged in these 6 positions in 5! (5 factorial) ways, which is equal to 120.
Therefore, the total number of arrangements with exactly one "m" at the beginning is 1 × 120 = 120.
There are 120 arrangements of the letters of the word MAXIMUM that begin with exactly one "m."
To know more about factorial, visit;
https://brainly.com/question/11907443
#SPJ11
Show your work for the following word problem:
Rafael ate 1/4 of a pizza and Rocco ate 1/3 of it. What fraction
of the pizza did they eat? How much was left?
Rafael ate 1/4 of the pizza and Rocco ate 1/3 of it. Together, they ate 7/12 of the pizza, leaving 5/12 of it uneaten.
To solve this word problem, we need to find the fraction of the pizza that Rafael and Rocco ate and the fraction that was left.Let's start by finding the fraction of the pizza that Rafael ate, which is 1/4. Next, we'll find the fraction that Rocco ate, which is 1/3.
To determine the fraction of the pizza they ate together, we add the fractions: 1/4 + 1/3. To add fractions, we need a common denominator, which in this case is 12. So, we rewrite the fractions with the common denominator: 3/12 + 4/12 = 7/12.Therefore, Rafael and Rocco together ate 7/12 of the pizza.
To find the fraction that was left, we subtract the fraction they ate from 1 whole: 1 - 7/12 = 5/12.Hence, they ate a total of 7/12 of the pizza, and there was 5/12 of the pizza left.In summary, Rafael and Rocco together ate 7/12 of the pizza, and 5/12 of the pizza was left.
To learn more about fraction click here
brainly.com/question/10354322
#SPJ11
Consider the equation (x−2)^2−lnx=0
Find an approximation of it's root in [1,2] to an absolute error less than 10^(−9) with one of the methods covered in class.
An approximation of the root of the equation [1, 2] to an absolute error less than 10⁻⁹ using the Newton-Raphson method is 1.457107153.
The given equation is (x − 2)² − ln x = 0. To find an approximation of its root in [1, 2] to an absolute error less than 10⁻⁹ using one of the methods covered in class, we can use the Newton-Raphson method. The Newton-Raphson method is a numerical method for finding the roots of a function.
It is a very simple and powerful method for finding the roots of a function. The Newton-Raphson method is based on the principle of successive approximations. In this method, we start with an initial guess of the root and then apply a formula to find the next approximation of the root. The formula is given by:
x_(n+1) = x_n - f(x_n)/f'(x_n)
where,
x_n is the nth approximation of the root
f(x_n) is the value of the function at x_n
f'(x_n) is the derivative of the function at x_n
To find the root of the given equation, we first need to find its derivative:
dy/dx = 2(x - 2) - (1/x)
Now, let x_0 = 1.5 be the initial guess of the root of the equation:
(i) At n = 0:x_1 = x_0 - f(x_0) / f'(x_0) = 1.5 - [(1.5 - 2)² - ln(1.5)] / [2(1.5 - 2) - (1/1.5)] = 1.465631091
(ii) At n = 1:x_2 = x_1 - f(x_1) / f'(x_1) = 1.465631091 - [(1.465631091 - 2)² - ln(1.465631091)] / [2(1.465631091 - 2) - (1/1.465631091)] = 1.457396442(
iii) At n = 2:x_3 = x_2 - f(x_2) / f'(x_2) = 1.457396442 - [(1.457396442 - 2)² - ln(1.457396442)] / [2(1.457396442 - 2) - (1/1.457396442)] = 1.457107669
(iv) At n = 3:x_4 = x_3 - f(x_3) / f'(x_3) = 1.457107669 - [(1.457107669 - 2)² - ln(1.457107669)] / [2(1.457107669 - 2) - (1/1.457107669)] = 1.457107157(v) At n = 4:x_5 = x_4 - f(x_4) / f'(x_4) = 1.457107157 - [(1.457107157 - 2)² - ln(1.457107157)] / [2(1.457107157 - 2) - (1/1.457107157)] = 1.457107153
Hence, an approximation of the root of the equation (x − 2)² − ln x = 0 in [1, 2] to an absolute error less than 10⁻⁹ using the Newton-Raphson method is x = 1.457107153.
To know more about Newton-Raphson method refer here:
https://brainly.com/question/32721440
#SPJ11
What are the x and y-intercepts of this equation?
g(x)=(x−4)(x+1)(3−x)
The correct answer for y-intercept of the equation g(x) = (x - 4)(x + 1)(3 - x) is y = -12.
To find the x-intercepts of the equation g(x) = (x - 4)(x + 1)(3 - x), we set g(x) equal to zero and solve for x:
g(x) = 0
(x - 4)(x + 1)(3 - x) = 0
Setting each factor equal to zero:
x - 4 = 0 => x = 4
x + 1 = 0 => x = -1
3 - x = 0 => x = 3
Therefore, the x-intercepts of the equation g(x) = (x - 4)(x + 1)(3 - x) are x = 4, x = -1, and x = 3.
To find the y-intercept, we substitute x = 0 into the equation:
g(0) = (0 - 4)(0 + 1)(3 - 0) = (-4)(1)(3) = -12
Therefore, the y-intercept of the equation g(x) = (x - 4)(x + 1)(3 - x) is y = -12.
Learn more about linear equations here:
https://brainly.com/question/2030026
#SPJ11
Given the functions: f(x)=x²³-6x g(x)=√2x h(x)=7x-9 Evaluate the function h (f(x)) for x-5. Write your answer in exact simplified form. Select "Undefined" if applicable. h(f(s)) is √ Undefined X
Evaluating h(f(x)) for x-5 involves plugging x-5 into the function f(x) and then plugging the result into the function h(x). The final answer, h(f(x-5)), can be written as √(2(x-5)²³-6(x-5))-9.
To evaluate h(f(x)) for x-5, we first substitute x-5 into the function f(x). The function f(x) is given as f(x) = x²³ - 6x. Plugging x-5 into f(x), we get f(x-5) = (x-5)²³ - 6(x-5).
Next, we substitute the result of f(x-5) into the function h(x), which is given as h(x) = 7x - 9. Plugging in f(x-5), we have h(f(x-5)) = 7(f(x-5)) - 9.
Simplifying further, we can expand (x-5)²³ using the binomial expansion formula and distribute the -6 across the terms in f(x-5). After simplifying, we obtain h(f(x-5)) = √(2(x-5)²³ - 6(x-5)) - 9.
The expression inside the square root, 2(x-5)²³ - 6(x-5), cannot be further simplified. Therefore, the exact, simplified form of h(f(x-5)) is √(2(x-5)²³ - 6(x-5)) - 9.
Learn more about function here:
https://brainly.com/question/30721594
#SPJ11
Find f(1),f(2),f(3), and f(4) if f(n) is defined recursively by f(0)=1 and for n integers, n≥1. (a) f(n+1)=f(n)+2 (b) f(n+1)=3f(n). 1.2. Write in Python the following function recursively: # sumEven (n) : # sumEven (n) return the sum of even numbers from θ to n. def sum_even (n) : total = θ for i in range (2,n+1,2) : total = total +1 return total
To find f(1),f(2),f(3), and f(4) if f(n) is defined recursively by f(0)=1 and for n integers, n≥1, we are given two recursive formulas, which are f(n+1)=f(n)+2 and f(n+1)=3f(n). We can use the formulas to find the values of f for the given inputs.
Using the formula f(n+1)=f(n)+2 and f(0)=1, we have:f(1) = f(0) + 2 = 1 + 2 = 3f(2)f(2) = f(1) + 2 = 3 + 2 = 5f(3)f(3) = f(2) + 2 = 5 + 2 = 7f(4)f(4) = f(3) + 2 = 7 + 2 = 9To write a recursive Python function that returns the sum of even numbers from 0 to n, we can define the function sum_even(n) as follows:
If n is even, add it to the sum return n + sum_even(n-2) else: # if n is odd, skip it and move on to n-1 return sum_even(n-1)For example, sum_even(6) will return the value 12, because the sum of even numbers from 0 to 6 is 0 + 2 + 4 + 6 = 12.
To know more about integers visit :
https://brainly.com/question/30145972
#SPJ11
Use rules #7-10 to provide logical proofs with line-by-line justifications for the
following arguments.
7)
1. A > F
2. F > Z
3. A /Z
8)
1. ~J > (P > J)
2. O v ~J
3. ~O /~P
9)
1. Y > V
2. V > T
3. ~(Y > T) v W /W
10)
1. B v ~Q
2. B > G
3. Q /G
A > F2. F > Z3. A /Z. The answer for 10 is that we used the given premises to arrive at the conclusion G. We used Q to obtain ~Q, which when used with 2, yields G.
We have to prove that Z>A. Let's assume the opposite: A>Z. That means if A>Z then F>Z (using 1), and also F>Z (using 2), which is not possible. Thus Z>A. This is the answer for 7. We are asked to provide a proof using rules 7-10. We started by assuming the opposite of what we wanted to prove and reached a contradiction. Therefore, our assumption was wrong and our desired conclusion must be true. Proof:1. ~J > (P > J)2. O v ~J3. ~O /~PLet us prove that P. To do this, we use 2 and 3 to obtain ~J, then use 1 and ~J to obtain P. The answer for 8 is that we can prove P using the given premises. We used 2 and 3 to obtain ~J, which is then used with 1 to obtain P. 1. Y > V2. V > T3. ~(Y > T) v W /WWe know that we cannot prove that ~(Y > T).
Thus, we assume ~(Y > T) to be false, meaning Y > T. Using 2, we obtain T > V and then use the transitive property to obtain Y > V. Hence W, which is what we needed to prove. The answer for 9 is that we assumed ~(Y > T) to be false, and used the given premises to prove W. 1. B v ~Q2. B > G3. Q /GWe are given Q. Using 1, we can write ~Q > B, which, when used with 2, yields G. Thus, G is our conclusion. The answer for 10 is that we used the given premises to arrive at the conclusion G. We used Q to obtain ~Q, which when used with 2, yields G.
To know more about conclusion visit:
https://brainly.com/question/78686
#SPJ11