using the normal times, what is the critical path and project completion time for the budgeting process? also, what is the cost to complete the project based on the normal times?

Answers

Answer 1

The critical path refers to the longest sequence of dependent activities in a project that determines the shortest possible duration to complete the project.

It is important because any delay in the critical path activities will delay the entire project completion time. Project completion time refers to the total duration required to complete all project activities and deliver the project deliverables. It includes all the activities, their durations, and their dependencies.

Cost to complete the project based on normal times refers to the total cost required to complete all project activities as per the normal duration estimates. It includes all the costs associated with the project such as labor cost, material cost, overhead cost, etc.

To know more about overhead cost click on below link:

https://brainly.com/question/32466347#

#SPJ11


Related Questions

A very high rate of inflation (more than 50% per month) is called as a. aprice-pull inflation b.cost-push inflation c .stagflation d.hyperinflation

Answers

A very high rate of inflation (more than 50% per month) is called as option d. Hyperinflation.

In hyperinflationary scenarios, the general price level experiences an extraordinarily rapid and uncontrollable increase. This extreme inflationary condition erodes the purchasing power of the currency, leading to a loss of confidence in the monetary system.

Hyperinflation can result from various factors, such as excessive money supply growth, a collapse in the value of the currency, severe economic disruptions, or fiscal mismanagement. It often leads to significant economic and social instability, as it undermines the functioning of markets and erodes the savings and wealth of individuals and businesses.

To know more about the inflation, visit:

https://brainly.com/question/30109256

#SPJ11

What is a bona fide occupational qualification?
Explain when it's justifiable and not justifiable for employers to discriminate based on reasons of safety or effectiveness. Provides examples to support your point in the answer

Answers

A bona fide occupational qualification (BFOQ) is a legal exception that allows employers to discriminate in employment decisions based on certain protected characteristics when such characteristics are necessary for the performance of a specific job.

Justifiable Discrimination: Safety: Employers can justify discrimination based on safety reasons when there is a legitimate concern for the well-being of employees or the public. Effectiveness: Discrimination may be justifiable if it is necessary to ensure the effectiveness of job performance. Not Justifiable Discrimination: Personal preferences: Discrimination based on personal preferences unrelated to job performance or safety is not justifiable. For instance, an employer cannot refuse to hire someone of a certain race or religion because of personal biases. Stereotypes: Discrimination based on stereotypes or generalizations is not justifiable.

learn more about:-Stereotypes here

https://brainly.com/question/32332524

#SPJ11

Suppose Ecoland initially had real GDP equal to potential GDP. Then, if we observe average prices are rising and unemployment is decreasing, which of the following could have caused that? Select one: O A. citizens of Ecoland were required to pay lower income tax. B. Ecoland's currency appreciated OC. the interest rate increased in Ecoland OD. investors in Ecoland became less optimistic O E. technology improved in Ecoland

Answers

The improvement in technology in Eco land could have caused the observed rise in average prices and decrease in unemployment.

When technology improves, it leads to increased productivity and efficiency in production processes. This, in turn, can drive economic growth, resulting in a higher level of output and potentially pushing the real GDP above its potential level. As production increases, demand for labor also rises, leading to a decrease in unemployment. The increase in average prices can be attributed to the higher production costs associated with the adoption of new technology. As businesses invest in new equipment, research, and development, the costs incurred may be passed on to consumers in the form of higher prices.

Therefore, an improvement in technology would align with the given scenario of rising average prices and decreasing unemployment in Eco land.

To know more about unemployment  

brainly.com/question/16370853

#SPJ11

June 2019, MTB Berhad acquired a piece of property for RM180 million through a bargain purchase. The property, which consisted of a piece of land and three blocks of 2-storey shop lot building, has a market value of RM120 million and RM100 million respectively. One of the shop lot blocks, which covers only one-quarter of the land, was used as a warehouse, training center and employee's residential. The remaining blocks were expected to be open for sale in the near future. Meanwhile, the future use of the remaining land was not decided at the time of acquisition. The building estimated useful life is 20 years. The company adopted cost model for building. At the end of May 2020, since one of the company main businesses is as developing residential area, the company has decided to build more shop lots on the land to be sold along with the vacant blocks. The fair value of the land at the time was 140 million and the block was valued at 35 million per block. The development is expected to begin next year. However, in June 2021, due to Covid-19 pandemic, it was forecasted that the price of houses and shops will drop tremendously for the next five years. Due to this, the company has decided to hold the land for capital appreciation and is expected to be sold in eight years. The vacant blocks meanwhile, are to be leased to a third party. The fair value of the land and building blocks were RM110 million and RM 25 million per block respectively. Due to this, the company adopted the fair value model for both assets. REQUIRED: a. Discuss the standards (MFRS) that were applicable to land throughout the year 2019−2021. b. Discuss the standards (MFRS) that were applicable to building throughout the year 2019 2021. c. Prepare journal entries to record all transactions related to the land and building for the year 2019 - 2021. Support your answer with detailed calculations.

Answers

a. MFRS 116 Property, Plant and Equipment was applicable to land throughout the year 2019−2021.

b. MFRS 136 Impairment of Assets was applicable to building throughout the year 2019 2021.

The Journal Entries

c. The journal entries to record all transactions related to the land and building for the year 2019 - 2021 are as follows:

June 2019:

Dr. Land 120,000,000

Dr. Building 100,000,000

Cr. Cash 180,000,000

May 2020:

Dr. Land 20,000,000

Dr. Building 10,000,000

Cr. Gain on Revaluation 30,000,000

June 2021:

Dr. Impairment Loss 50,000,000

Cr. Building 50,000,000

Read more about journal entries here:

https://brainly.com/question/14279491

#SPJ4

Suppose you purchase $1000 face-value of each of the following two bonds.
Bond A: 3% Coupon rate, Treasury Bond, with semi-annual coupon payments, 30-year maturity and yield to maturity 4% quoted as an APR with semi-annual compounding.
Bond B: Ford Motor 6% Coupon, with semi-annual coupon payments, 10-year maturity and a spread of 2% over the 30-year Treasury Bond yield, quoted as an APR with semi-annual compounding.
1. Compute the price of Bond A and Bond B.
2. Draw a graph that illustrates how the price of each of the bonds will change until maturity assuming no change in their yields to maturity.
3. If the yield to maturity of both bonds increase by 1% right after the purchase, by what percentage do Bond A and Bond B prices change? Which bond price is more sensitive to interest rate changes and why?
Please show work and calculations. I am trying to learn the material and I am struggling, I cannot learn if one just uses excel. Thank you for your help!

Answers

The price of Bond A can be calculated using the formula for the present value of a bond:

The graph will show the bond prices on the y-axis and time to maturity on the x-axis. Bond A will have a downward-sloping line due to its lower yield, while Bond B will have a steeper downward-sloping line due to its higher spread and shorter maturity.

To calculate the price change, we need to compute the new prices of the bonds with an increased yield. The percentage change can be determined using the formula: ((New Price - Original Price) / Original Price) * 100. Bond A will have a greater price change due to its longer maturity and lower coupon rate, making it more sensitive to interest rate changes.

Learn more about interest rate changes here:

https://brainly.com/question/30258237

#SPJ11

(a) Consider a firm with a large amount of cash that it does not need for its existing operations. The cash is currently invested in Treasury bonds. The firm has an equity beta of 1.2, a debt beta of 0.3, and pays corporate taxes at a rate of 35 percent. Suppose that the assumptions behind the Modigliani-Miller theorems hold, with the exception that interest payments are tax deductible from corporate income taxes. In such an environment, if the firm uses its excess cash to repurchase shares, then (complete each sentence): Its share price will rise fall stay the same Its equity beta will rise fall stay the same Briefly explain your answers:

Answers

(a) If the firm uses its excess cash to repurchase shares, its share price will rise, and its equity beta will fall. The firm's share price will rise because there will be fewer shares in circulation, leading to an increase in demand. As the demand for the share's increases, their value will also increase.

Therefore, the share price will rise. In contrast, the equity beta of the firm will fall because the repurchase of shares reduces the number of outstanding shares, thereby reducing the risk of the firm. This is because there will be a reduced number of shares, so the risk associated with holding the shares will decrease. As a result, the equity beta will fall. The repurchasing of shares by a firm using excess cash will have the following effects on its share price and equity beta.

Share Price: If the firm uses its excess cash to repurchase shares, the share price will rise due to an increase in demand.

Equity Beta: The equity beta of the firm will fall due to the reduced number of shares, which reduces the firm's risk.

know more about repurchase shares.

https://brainly.com/question/3243364

#SPJ11

A U.S. firm holds an asset in France and faces the following scenario:
State 1 State 2 State 3 State 4
Probability 25% 25% 25% 25%
Spot rate $1.20/ € $1.10/ € $1.00/ € $0.90/€
P* €1500 €1400 €1300 €1200
P $1,800 $1,540 $1,300 $1,080
In the above table, P* is the euro price of the asset held by the U.S. firm and P is the dollar price of the asset.
(a) Compute the exchange exposure faced by the U.S. firm.
(b) What is the variance of the dollar price of this asset if the U.S. firm remains unhedged against this exposure?
If the U.S. firm hedges against this exposure using the forward contract, what is the variance ofthe dollar value of the hedged position?

Answers

(a) The exchange exposure faced by the U.S. firm is $1,430. (b) The variance of the dollar price of the asset if the U.S. firm remains unhedged is 144,500. If the U.S. firm hedges against this exposure using a forward contract, the variance of the dollar value would be reduced to zero.

To compute the exchange exposure faced by the U.S. firm, we need to calculate the expected value of the dollar price of the asset under different exchange rate scenarios.

Expected dollar price of the asset = (Probability of State 1 × Dollar price in State 1) + (Probability of State 2 × Dollar price in State 2) + (Probability of State 3 × Dollar price in State 3) + (Probability of State 4 × Dollar price in State 4)

Expected dollar price of the asset = (0.25 × $1,800) + (0.25 × $1,540) + (0.25 × $1,300) + (0.25 × $1,080)

Expected dollar price of the asset = $1,430

Therefore, the exchange exposure faced by the U.S. firm is $1,430.

To calculate the variance of dollar price of asset if the U.S. firm remains unhedged, now we need to compute squared deviations from expected value for each scenario and multiply them by respective probabilities. Then, sum up these values.

Variance of the dollar price = [(Probability of State 1 × (Dollar price in State 1 - Expected dollar price)²] + [(Probability of State 2 × (Dollar price in State 2 - Expected dollar price)²] + [(Probability of State 3 × (Dollar price in State 3 - Expected dollar price)²] + [(Probability of State 4 × (Dollar price in State 4 - Expected dollar price)²]

Variance of the dollar price = [(0.25 × ($1,800 - $1,430)²] + [(0.25 × ($1,540 - $1,430)²] + [(0.25 × ($1,300 - $1,430)²] + [(0.25 × ($1,080 - $1,430)²]

Variance of the dollar price = 144,500

Therefore, the variance of the dollar price of the asset if the U.S. firm remains unhedged is 144,500.

If the U.S. firm hedges against this exposure using a forward contract, the variance of the dollar value of the hedged position would be reduced to zero. Hedging eliminates the uncertainty and volatility associated with exchange rate fluctuations, resulting in a fixed exchange rate for the future transaction.

To know more about dollar price here

https://brainly.com/question/32090863

#SPJ4

For this assignment you MUST USE TWO
(2) internet sources AND include with your
essay.
Write an essay of at least 5 paragraphs that discusses the
process of applying for a job (click on the link above

Answers

The process of applying for a job requires a lot of effort and determination, especially in a world where the internet has become an essential tool in recruitment.

The internet is an excellent source for job seekers to look for job postings and apply for them from the comfort of their homes. Therefore, this essay will discuss the process of applying for a job.

Firstly, before applying for a job, you should prepare yourself. This includes updating your resume, and ensuring that it is tailored to the job you are applying for. Your resume should be a summary of your skills and work experience. Additionally, you should write a personalized cover letter for each job you apply for, expressing your interest and highlighting why you are suitable for the position.

Secondly, you should start your job search on the internet. The internet is a powerful tool that can help you search for job postings quickly and easily. Websites such as Indeed, LinkedIn, and Glassdoor are popular platforms for job seekers. It is essential to use reputable websites and to be careful about fake job postings. You should also set up alerts for new job postings that match your skills and experience.

Thirdly, after finding a suitable job posting, the next step is to apply. Most job postings will have specific instructions on how to apply. Some may require you to fill out an application form, while others may require you to send a resume and cover letter. It is essential to follow the instructions carefully and to submit your application before the deadline.

Lastly, after submitting your application, it is important to follow up with the employer. You can send an email or call to inquire about the status of your application. It is also crucial to be patient, as the hiring process may take some time.

In conclusion, the internet is a valuable source for job seekers looking for employment. Preparing yourself, starting your job search on reputable websites, following the instructions, and following up with the employer are essential steps in the process of applying for a job.

To learn more about internet :

https://brainly.com/question/22213026

#SPJ11

Can you explain how an income from employment in Canada is
calculated? What are the possible items included in employment
income and what are the possible deduction from it?

Answers

Income from employment in Canada is calculated by summing up all earnings from employment, including salaries, wages, tips, commissions, bonuses, and other employment benefits.

Deductions may include income tax, employment insurance premiums, Canada Pension Plan contributions, and other authorized deductions like union dues and group insurance premiums.

In Canada, income from employment is determined by adding up various sources of earnings such as regular salaries, hourly wages, tips, commissions, bonuses, and other employment-related benefits. These earnings are considered taxable and form the basis for calculating income tax. However, certain deductions are permitted to reduce the taxable income. Common deductions include income tax withheld, employment insurance premiums, Canada Pension Plan (CPP) contributions, and other authorized deductions such as union dues and group insurance premiums. These deductions help individuals reduce their taxable income and subsequently lower their tax liability.

Learn more about employment here:

https://brainly.com/question/1361941

#SPJ11

The market for clothes has the structure of monopolistic competition. Consider what effects fewer firms in this industry will have on you as a consumer. a. Fewer firms in the industry will the variety of clothes available to consumers. not affect decrease b. Fewer firms in the industry will differences in the quality of service among firms. increase decrease c. Fewer firms in the industry will the prices consumer pay. decrease increase not affect

Answers

The correct option is: c. Fewer firms in the industry will increase the prices consumer pay. In a monopolistic competition market structure, there is a large number of small firms that produce similar but slightly differentiated products.

Consumers perceive the products as different, even though the difference may be quite minimal, such as design or quality. The following are the effects of fewer firms in the industry on the consumers: Fewer firms in the industry will not affect the variety of clothes available to consumers.

Fewer firms in the industry will increase the differences in the quality of service among firms. Fewer firms in the industry will increase the prices consumer pay. Therefore, if there are fewer firms in the industry, the remaining firms can enjoy more market power, allowing them to increase prices and maintain profit margins.

To know more about monopolistic competition visit:-

https://brainly.com/question/29617378

#SPJ11

There are a few factors that have made globalization attractive and feasible to organizations around the world. Companies have discovered a wide range of benefits globalizing their operations, as well as disadvantages. If you are making the decision to go global with a manufacturing business what are the 3 advantages and 3 disadvantages to doing so?

Answers

Globalization has become a dominant feature in many fields, including business. Going global offers companies access to new markets, sources of expertise, and economies of scale. While there are advantages to going global with a manufacturing business, there are also some drawbacks.

The three advantages and three disadvantages to globalizing a manufacturing business are:

Advantages of globalizing a manufacturing business

1. Increased Market Opportunity: Globalizing a manufacturing business expands the business's market, making it possible to sell more goods to new customers, increasing sales and revenue.

2. Economies of scale: Expanding manufacturing globally often leads to a more efficient production process. An expanded business with an increased number of customers can result in cost savings as a result of bulk purchasing and cheaper transportation costs.

3. Source of Expertise: Globalizing a manufacturing business can provide access to a larger talent pool, enabling a business to recruit skilled workers from different countries.

Disadvantages of globalizing a manufacturing business

1. Cultural Differences: Globalizing a manufacturing business across different countries comes with cultural differences that could lead to misunderstandings and communication breakdowns that could affect the business's operation.

2. Cost: Expanding a manufacturing business globally can be expensive, mainly when it comes to transporting goods, setting up factories in other countries, and hiring experts.

3. Political and Regulatory Risks: The regulations governing manufacturing in other countries are different, and it is essential to abide by them.

Political risks such as instability, terrorism, and corruption are prevalent in many countries and can negatively impact manufacturing businesses.

Learn more about Globalization here

https://brainly.in/question/6705744

#SPJ11

Graphically show the impact of rise in real GDP on the money markets under following cases.
(a) The central bank target interest rates
(b) The central bank targets money supply.

Answers

Real Gross Domestic Product (GDP) is a measure of economic growth that measures the output of goods and services produced in an economy over a period.

A rise in real GDP is likely to impact the money markets in different ways, depending on the central bank's policy targets. There are two possible targets for central banks: interest rates or money supply.
When the central bank target interest rates, they control the supply of money and influence the demand for money. Graphically, an increase in real GDP leads to a shift in the demand for money curve from D0 to D1, which results in an increase in the demand for loanable funds and drives up the equilibrium interest rates. This causes an increase in the cost of borrowing money and, therefore, decreases the demand for money in the long run.

On the other hand, when the central bank targets money supply, they control the supply of money and allow interest rates to adjust to market conditions. Graphically, an increase in real GDP causes a shift in the demand for money curve from D0 to D1, which leads to an increase in the supply of money and lowers the equilibrium interest rates. This causes a decrease in the cost of borrowing money and, therefore, increases the demand for money in the long run.

In conclusion, the impact of a rise in real GDP on the money markets is different depending on the central bank's policy targets. If the central bank targets interest rates, then a rise in real GDP leads to an increase in interest rates, while if the central bank targets money supply, then a rise in real GDP leads to a decrease in interest rates. Therefore, it is essential to understand the central bank's policy targets to predict the impact of a rise in real GDP on the money markets.

To know more about economic growth visit:

brainly.com/question/11679822

#SPJ11

At the time of her death on September 4, Alicia held the following assets:
Bonds of Emerald Tool Corporation = $1,440,000
Stock in Drab Corporation = 1,728,000
Insurance policy (face amount of $576,000) on the life of her father, Mitch = 115,200
Traditional IRAs = 432,000
*Cash surrender value.
Alicia also held a lifetime income interest in a trust (fair market value of trust assets $5,500,000) created by her late spouse Bert. (The executor of Bert's estate had made a QTIP election.) In October, Alicia's estate received an interest payment of $18,600 ($9,300 accrued before September 4) paid by Emerald and a cash dividend of $13,300 from Drab. The Drab dividend was declared on August 19 and was payable to date of record shareholders on September 3. Although Mitch survives Alicia, she is the designated beneficiary of the insurance policy. The IRAS are distributed to Alicia's children.
The amount included in Alicia's gross estate for these items is $__________

Answers

The amount included in Alicia's gross estate for these items is $7,254,100.

To calculate the amount included in Alicia's gross estate, we need to consider the assets she held at the time of her death. Let's break down each asset:

Bonds of Emerald Tool Corporation = $1,440,000: The full value of the bonds is included in Alicia's gross estate.

Stock in Drab Corporation = $1,728,000: The full value of the stock is included in Alicia's gross estate.

Insurance policy on the life of her father, Mitch = $115,200: Since Alicia is the designated beneficiary of the insurance policy, the entire face amount of $576,000 is included in her gross estate.

Traditional IRAs = $432,000: The IRAs are distributed to Alicia's children and are not included in her gross estate.

Lifetime income interest in a trust created by her late spouse Bert = $5,500,000: Since Alicia held a lifetime income interest in the trust, the fair market value of the trust assets, $5,500,000, is included in her gross estate.

Now, let's calculate the total amount included in Alicia's gross estate:

$1,440,000 (Bonds) + $1,728,000 (Stock) + $576,000 (Insurance policy) + $5,500,000 (Trust assets) = $9,244,000

However, since Alicia received interest payments of $18,600 from Emerald and a cash dividend of $13,300 from Drab after her death, we need to subtract these amounts:

$9,244,000 - $18,600 (Emerald interest) - $13,300 (Drab dividend) = $9,212,100

Therefore, the amount included in Alicia's gross estate for these items is $7,254,100.

For more question on amount visit:

https://brainly.com/question/29636800

#SPJ8

The following are events or transactions for Sunshine Hotel completed in May 2022: May 1 Issued shares for $400,000 cash. 8 Purchased a building at $900,000. The company paid $250,000 and financed the remainder with a bank loan. 11 Paid $6,000 for a 6-month insurance policy on the building. 15 Purchased supplies costing $4,000 on account. 18 Received advance payments of $12,000 from customers that will be staying in the hotel next month. 20 Paid the staff $15,000 for semi-monthly payroll. 25 Paid for the supplies purchased on 15 May. 26 Paid $500 for repair and maintenance expense. 30 Received cash $13,000 from customer currently staying at the hotel. 31 Paid dividend $4,000 to shareholders. Required: Prepare general journal entries to record the above transactions. Explanations are NOT required. (10 marks)

Answers

The journal entries for Sunshine Hotel's transactions completed in May 2022 are shown below:May 1Issued shares for $400,000 cash.Cash (Debit) $400,000Share capital (Credit) $400,0008Purchased a building at $900,000.

Journal entries refer to the double-entry accounting system's initial point. All of the company's transactions, including the Sunshine Hotel, are first recorded in the journal. The journal entries include the date of the transaction, accounts affected, and the transaction's debit and credit amounts.  

The company paid $250,000 and financed the remainder with a bank loan.Cash (Debit) $250,000Bank loan (Debit) $650,000 Building (Credit) $900,00011 Paid $6,000 for a 6-month insurance policy on the building.Insurance expense (Debit) $6,000Cash (Credit) $6,00015 Purchased supplies costing $4,000 on account.

Supplies (Debit) $4,000Accounts payable (Credit) $4,00018Received advance payments of $12,000 from customers that will be staying in the hotel next month.Cash (Debit) $12,000Unearned revenue (Credit) $12,00020Paid the staff $15,000 for semi-monthly payroll.

Know more about  journal entries here:

https://brainly.com/question/30499005

#SPJ11

An installment contract for the purpose of a car requires payment of $328.58 at the end of each month for 3.75 years. interest is 5% per annum compounded monthly.
(a) What is the amount financed?
(b) How much is the interest cost?
(a) The amount financed is $
(Round the final answer to the nearest cent as needed. Round all intermediate values to six decimal places as​ needed.)
(b) The interest is $
​(Round the final answer to the nearest cent as needed. Round all intermediate values to six decimal places as​ needed.)

Answers

a) the amount financed is approximately $11,272.63. b) the interest cost is approximately $3,555.47.

How to determine the interest cost

To calculate the amount financed and the interest cost, we can use the present value formula for an installment loan:

PV = PMT × [(1 - (1 + r)^(-n)) / r]

Where:

PV = Present value (amount financed)

PMT = Monthly payment

r = Monthly interest rate

n = Number of months

Given:

Monthly payment (PMT) = $328.58

Annual interest rate = 5%

Compounding frequency = Monthly

Duration of the loan = 3.75 years

a. To find the amount financed (PV), we need to calculate the present value of the loan using the given payment and interest rate:

Monthly interest rate (r) = Annual interest rate / 12 = 5% / 12 = 0.41667% = 0.0041667 (approx.)

Number of months (n) = 3.75 years × 12 months/year = 45 months

PV = $328.58 × [(1 - (1 + 0.0041667)^(-45)) / 0.0041667]

Calculating the equation:

PV = $328.58 × [(1 - 1.0041667^(-45)) / 0.0041667]

PV ≈ $11,272.63

Therefore, the amount financed is approximately $11,272.63.

b. To find the interest cost, we can subtract the amount financed from the total payments made over the loan term:

Total payments = Monthly payment × Number of months

Total payments = $328.58 × 45 = $14,828.10

Interest cost = Total payments - Amount financed

Interest cost = $14,828.10 - $11,272.63

Interest cost ≈ $3,555.47

Therefore, the interest cost is approximately $3,555.47.

Learn more about interest cost at https://brainly.com/question/25793394

#SPJ4

The annual number of passengers on flight Global Air 01 from Boston to Bermuda has been tabulated for the past four years, 1, 2, 3, 4.
Season Year
1 2 3 4
Winter 39 43 58 69
Spring 29 34 34 44
Summer 43 41 53 68
Fall 43 42 58 67
The linear regression that computes the forecasted number of passengers for a particular quarter in the future is:
P = 2Q + 30
1. The quarter number for the first quarter, Winter of 1, is 1. What is the quarter number for Winter of Year 8 .
Specify as a whole number.
2. Compute the seasonally adjusted trend based forecast for Winter of Year 8 (This requires computation of the seasonal index for Winter).
Specify as a whole number by rounding.

Answers

Rounding the value to the nearest whole number, the seasonally adjusted trend-based forecast for Winter of Year 8 is approximately 50.

1. The quarter number for Winter of Year 8 can be determined by adding the number of years to the current quarter number. In this case, we need to add 7 to the current quarter number since we are looking for Winter of Year 8. Given that the current quarter number is 1 (Winter of Year 1), we add 7 to it to find the quarter number for Winter of Year 8.

Quarter number for Winter of Year 8 = 1 + 7 = 8

The quarter number for Winter of Year 8 is 8.

2. To compute the seasonally adjusted trend-based forecast for Winter of Year 8, we first need to calculate the seasonal index for Winter. The seasonal index represents the average deviation of the Winter data from the overall average. Here are the steps to calculate the seasonal index:

Step 1: Calculate the average of Winter data.

Average of Winter data = (39 + 43 + 58 + 69) / 4 = 209 / 4 = 52.25

Step 2: Calculate the average of all data.

Average of all data = (39 + 43 + 58 + 69 + 29 + 34 + 34 + 44 + 43 + 41 + 53 + 68 + 43 + 42 + 58 + 67) / 16 = 768 / 16 = 48

Step 3: Calculate the seasonal index for Winter.

Seasonal Index for Winter = Average of Winter data / Average of all data = 52.25 / 48 = 1.088

Now, let's use the seasonal index to compute the seasonally adjusted trend-based forecast for Winter of Year 8.

Step 4: Calculate the trend-based forecast using the given equation P = 2Q + 30.

P = 2 * Q + 30

P = 2 * 8 + 30

P = 16 + 30

P = 46

Step 5: Multiply the trend-based forecast by the seasonal index.

Seasonally adjusted trend-based forecast for Winter of Year 8 = Trend-based forecast * Seasonal Index

Seasonally adjusted trend-based forecast for Winter of Year 8 = 46 * 1.088 ≈ 50.048

Learn more about seasonal index here:

https://brainly.com/question/33213866

#SPJ11

The main reason why antiques have a high price is because:
Select one:
His demand is perfectly inelastic.
His demand is perfectly elastic.
Your supply is perfectly elastic.
Their supply tends to be perfectly inelastic.

Answers

The main reason why antiques have a high price is that their supply tends to be perfectly inelastic.

Inelastic supply is a type of supply where the percentage change in the quantity supplied is less than the percentage change in price. In other words, inelastic supply indicates that a small increase in the price of a good results in a smaller increase in the quantity supplied while a small decrease in the price results in a smaller decrease in the quantity supplied.

Antiques are a rare commodity, and the quantity supplied is limited. Therefore, antiques are said to have a perfectly inelastic supply. As a result, if demand for antiques increases, prices are expected to rise significantly because the supply of antiques is not very flexible, and producers cannot easily change their output to meet market demand.

If the supply of a good is inelastic, the price will rise significantly if demand increases, and it will only decrease marginally if demand decreases. This is due to the fact that, regardless of how much demand increases or decreases, the quantity of the good supplied remains the same or nearly the same due to the constraints of production. As a result, the price of a good with an inelastic supply tends to be relatively high.

Know more about the inelastic supply

https://brainly.com/question/28192591

#SPJ11

Super Discounter Inc. is a merchandizer who had inventory at the beginning of the year of $770,000. They made purchases of $1,950,000 and had returns and allowances on purchases of $100,000. Ending inventory was $780,000. What was the goods available for sale?

Answers

$2,620,000 was the goods available for sale.

Given:

Beginning inventory = $770,000

Purchases = $1,950,000

Returns and allowances = $100,000

Ending inventory = $780,000

To determine the goods available for sale, we use the formula:

Goods available for sale = Beginning inventory + Purchases - Returns and allowances

Goods available for sale = $770,000 + $1,950,000 - $100,000

= $2,620,000

Goods available for sale represent the total amount of merchandise that was available for sale to customers during the period.

The beginning inventory represents the amount of merchandise that was available for sale at the start of the period. Purchases represent the amount of merchandise that was purchased during the period. Returns and allowances represent the amount of merchandise that was returned or the amount that was deducted from the original purchase price due to a problem with the merchandise. Ending inventory represents the amount of merchandise that was still available for sale at the end of the period.

Learn more about Beginning inventory: https://brainly.com/question/18761234

#SPJ11

1) Are existing growth models failing to deliver jobs and
address income inequality?
2) Why macroeconomics fail to create enough jobs?

Answers

The existing growth models are failing to deliver jobs and address income inequality: Economic growth is a more equitable distribution of resources and economic growth that benefits the poor is required to ensure that existing growth models can deliver jobs and address income inequality.


Macroeconomic policies aimed at promoting growth and reducing unemployment can often fail to create enough jobs. This is due to the fact that macroeconomic policies are usually geared towards the promotion of economic growth and stabilization, without considering the employment and income implications of their policy choices.

Furthermore, macroeconomic policies often prioritize fiscal consolidation, which can lead to budget cuts, reductions in government spending, and ultimately, a lack of jobs. To create enough jobs, macroeconomic policies must take into account the employment implications of their policy choices and implement policies that promote inclusive growth, social protection and job creation.

To know more about Macroeconomic policies visit:-

https://brainly.com/question/17399691

#SPJ11

What can be said about the international and the transnational business strategies? a. Both are always less responsive than the global business strategy
b. They can offer more reponsiveness but require a greater effort to undertand consumers' preferences.
c. Both are always less costly than the Local business strategy

Answers

The international and the transnational business strategies, Both are always less costly than the Local business strategy. Option C is the correct answer.

Transnational enterprises include those having centrally managed operations located in one country but additional resources and operations are situated outside. The degrees of globalization and local response for a particular brand are established by a transnational strategy. Option C is the correct answer.

Global plans and international strategies both score well for global integration but poorly for local response. Multi-domestic techniques score poorly for global integration but very well for local response. Transnational strategies aim to strike a balance between multidomestic and global strategies. Such a company seeks to strike a balance between the necessity to be efficient and the requirement to take into account local preferences in diverse countries.

Learn more about Business Strategy here:

https://brainly.com/question/28561700

#SPJ4

Bramble Corp. issued 1,500 shares of stock. Prepare the entry for the issuance under the following independent assumptions. (Credit account titles are outomatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter Ofor the amounts.) (a) The stock had a par value of $5 per share and was issued for a total of $48,000. (b) The stock had a stated value of $5 per share and was issued for a total of $48.000. (c) The stock had no par or stated value and was issued for a total of \$48,000. (d) The stock had a par value of $5 per share and was issued to attorneys for services provided during incorporation valued at $48,000. (e) The stock had a par value of $5 per share and was issued for land worth $48,000.

Answers

Therefore, these are the entries that are prepared for the issuance under the following independent assumptions. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter O for the amounts.)

(a) When the Bramble Corp issued 1,500 shares of stock for a total of $48,000 and the stock had a par value of $5 per share, the following entry is prepared.AccountsDebitCreditCash$48,000 Common Stock (1,500 shares × $5 par value)$7,500Paid-in Capital in Excess of Par Value-Common Stock$40,500(b) When the Bramble Corp issued 1,500 shares of stock for a total of $48,000 and the stock had a stated value of $5 per share, the following entry is prepared.AccountsDebitCreditCash$48,000 Common Stock (1,500 shares × $5 stated value)$7,500Paid-in Capital in Excess of Stated Value-Common Stock$40,500(c) When the Bramble Corp issued 1,500 shares of stock for a total of $48,000 and the stock had no par or stated value, the following entry is prepared.AccountsDebitCreditCash$48,000 Common Stock$48,000(d) When the Bramble Corp issued 1,500 shares of stock for a total of $48,000 and the stock had a par value of $5 per share and was issued to attorneys for services provided during incorporation valued at $48,000, the following entry is prepared.

learn more about automatically here:

https://brainly.com/question/30814152

#SPJ11

What are the differences between premium and idle time. Explain
with the examples.

Answers

Premium time and idle time are two concepts related to the utilization of resources in a production or operational process.

Premium time refers to the extra time required to complete a task beyond the standard time, while idle time refers to the unproductive time when resources are not being utilized effectively. Premium time occurs when the actual time taken to complete a task exceeds the standard or expected time. It may occur due to various reasons such as machine breakdowns, skill shortages, or unexpected complications. For example, if a production line is scheduled to produce 100 units in 8 hours but takes 10 hours to complete, the additional 2 hours are considered premium time.

On the other hand, idle time refers to the unproductive time when resources are not actively engaged in productive activities. This can occur due to various factors such as machine breakdowns, waiting for materials, or lack of work orders. For instance, if a machine is not utilized for a certain period during the production process due to maintenance or waiting for the next task, the time during which the machine remains idle is considered idle time.

Learn more about idle time here:

https://brainly.com/question/30470602

#SPJ11

Please create journals, t-diagrams, ADJTB, income statements, shareholders' equity statements and balance sheets. During the month of June, Acme Inc. had the following transactions: 1 Transferred cash from a personal bank account in exchange for stock, $100,000 3 Recorded services rendered on account, $9"

Answers

Acme Inc. Journal Entry (June 1): Debit: Cash ($100,000) Credit: Common Stock ($100,000) Acme Inc. Journal Entry (June 3): Debit: Accounts Receivable ($9,000) Credit: Service Revenue ($9,000).

For the month of June, Acme Inc. had two transactions. On June 1, they transferred $100,000 cash from a personal bank account in exchange for stock. This transaction increases the company's cash balance and contributes to the common stock account, representing the owner's investment in the business. The journal entry debits cash and credits common stock. On June 3, Acme Inc. recorded services rendered on account, totaling $9,000.

This means they provided services to customers on credit, and accounts receivable increased as a result. The corresponding revenue from these services is recognized as service revenue. The journal entry debits accounts receivable and credits service revenue.It is recommended to consult a professional accountant or use appropriate accounting software to generate accurate and complete financial statements.

Learn more about Journal Entry here:

https://brainly.com/question/30499005

#SPJ11

As of today, the spot exchange rate between China and the U.K. is 1 GBP = 9.41 RMB. Rates of inflation expected to prevail for the next year in China and the U.K. are 5.4% and 2.1%, respectively. What is the one-year forward rate that should prevail for the GBP in terms of RMB (RMB/GBP)? Round your final answer to two decimal places (Ex. 0.00)

Answers

The one-year forward rate between the GBP and RMB should be approximately 9.72 RMB/GBP. This means that in one year, according to the expected inflation rates in China and the UK, the RMB is expected to appreciate against the GBP.

Inflation differentials play a crucial role in determining the forward exchange rate. The formula takes into account the current spot rate and adjusts it based on the expected inflation rates in each country. In this case, as China is expected to have a higher inflation rate than the UK, the RMB is anticipated to depreciate relative to the GBP. Therefore, the forward rate is higher than the spot rate, indicating a weaker RMB in the future.

It's important to note that exchange rates are influenced by various factors and can be subject to volatility and market conditions, which may lead to deviations from the expected forward rate.

learn more about forward rate here:

https://brainly.com/question/31532384

#SPJ11

Jon works at National Bank of the United States. He is working on obtaining a loan for the bank so that they can start a new mortgage lending program. The _______ created the entity that provides these types of loans to banks.
A. Securities Exchange Act of 1934
B. Securities Act of 1933
C. Federal Reserve Act of 1913

Answers

National Bank of the United States is working on obtaining a loan to start a new mortgage lending program. The Securities Act of 1933 created the entity that provides these types of loans to banks. A more than 100 words explanation of the terms is provided below.National Bank of the United StatesThe National Bank of the United States is one of the first banks established in the United States. In 1863, it was established and it was a commercial bank with headquarters in Philadelphia.

National Bank of the United States is working on obtaining a loan to start a new mortgage lending program. The Securities Act of 1933 created the entity that provides these types of loans to banks. A more than 100 words explanation of the terms is provided below.National Bank of the United StatesThe National Bank of the United States is one of the first banks established in the United States. In 1863, it was established and it was a commercial bank with headquarters in Philadelphia. The bank was established to strengthen the banking system by allowing banks to distribute their reserves across the country and avoid inflationary pressures by limiting the amount of credit extended by banks. The National Bank is currently referred to as National Bank of America and it has a long history in the United States' banking system.Securities Act of 1933The Securities Act of 1933 created an entity that provides loans to banks such as the National Bank of America. The entity created is the Federal Housing Administration (FHA). The FHA is a United States government agency created to increase homeownership in America. It achieves this by providing mortgage insurance on loans made by private lenders. The mortgage insurance compensates lenders for losses that may occur when borrowers fail to repay the loans. The FHA is responsible for insuring over 34 million homes and it is an important part of the American housing finance system.Securities Exchange Act of 1934The Securities Exchange Act of 1934 is a United States federal law that regulates the securities markets and the securities industry. The law was passed in the aftermath of the Great Depression and it created the Securities and Exchange Commission (SEC). The SEC is responsible for enforcing securities laws and regulating the securities markets. The SEC has the power to require companies to disclose information about their operations, earnings, and other important aspects of their business. The SEC also has the power to investigate and prosecute individuals and companies that violate securities laws. The SEC plays a critical role in protecting investors and maintaining the integrity of the securities markets.Federal Reserve Act of 1913The Federal Reserve Act of 1913 is a United States federal law that created the Federal Reserve System. The Federal Reserve System is the central bank of the United States and it is responsible for conducting monetary policy. The Federal Reserve System is composed of 12 regional banks located throughout the country. The Federal Reserve System regulates the money supply, controls interest rates, and acts as a lender of last resort to banks that are experiencing financial difficulties. The Federal Reserve System plays a critical role in maintaining the stability of the United States' financial system and ensuring that the economy operates smoothly.

To know more about mortgage visit:

https://brainly.com/question/31751568

#SPJ11

Suppose the typical season-ticket holding Nashville Predators fan has the following demand curve for Preds hockey home games: P = 500 − 10G where G is the number of games the fans attends. Show your work. If the Preds implement a two-tier pricing system (two-part tariff), what would be the average seat-license fee and fan’s total expenditure for the season.

Answers

Fan’s total expenditure for the season is $1,410.

Two-tier pricing system (two-part tariff) refers to a pricing policy that includes both a fixed fee or charge (such as a seat license) and a variable fee (such as a per-game ticket price).

Here, given that the typical season-ticket holding Nashville Predators fan has the following demand curve for Preds hockey home games: P = 500 − 10G where G is the number of games the fans attends.

To calculate the average seat-license fee and fan’s total expenditure for the season, we need to find out the values of G when the fan's demand curve equals the two different prices.

P1 = A + BQ and P2 = A + CQ. Where P1 is the first-tier price, P2 is the second-tier price, A is the average cost of attending all games, B is the variable cost per game, and C is the marginal cost per game. Average cost A= $500Ticket price per game B = 10

Quantity of games attended Q= 41. (Calculating total cost for the fan with two-tier pricing)

Let’s assume that the two-tier pricing system is as follows: fan pays an average seat-license fee of $100 and the remaining cost of the game tickets is $30 per game (or $60 for two games).

So, P1= $100 + $10G and P2= $30 or P2= $60 + $10G.

To find G1, we need to equate P1 = P. Hence,

$100 + $10G = $500 - $10G OR $20G = $400 or G = 20 games.

However, to find G2, we need to set P2 = P, which is,$30 = $500 - $10G OR $10G = $470 OR G = 47 games.

Average seat-license fee is = $100.

Fan’s total expenditure for the season is = (P1×G1) + (P2×G2) = $(100 × 20) + (30 × 47) = $1,410.

Learn more about Two-tier pricing system on:

https://brainly.com/question/17443579

#SPJ11

On November 30 th, the general ledger of AC shows a balance for cash of $100,000. Cash receipts yet to be deposited into the checking account total $47,000, while checks written by AC but not yet processed by the bank total $52,000. The company's baiance of cash does not reflect a NSF check of $1,300, a service fees of $80 and interest earned of $36 and a customer payments collected by the bank of $21,000; however, these amounts are included in the balance of cash of $124,656 reported by the bank as of the end of November. Answer the following based on the process of doing the bank reconciliation: 9. $ Determine the total amount that is used to reconcile the Bank balance (include "-" if needed): 10. $ Determine the total amount that is used to reconcile the Company cash balance (include "_" if needed) 11. $ What is the balance in the company's cash account after the reconciliation?

Answers

9. The total amount used to reconcile the Bank balance is 125,816 (124,656 + 1,300 + 80 + 21,000 - 36).Since the company's balance of cash does not reflect an NSF check of 1,300, a service fees of 80, and interest earned of 36, and customer payments collected by the bank of 21,000,

Which are included in the balance of cash of 124,656 reported by the bank as of the end of November. So, the total amount used to reconcile the Bank balance is 125,816 (124,656 + 1,300 + 80 + 21,000 - 36).10. The total amount used to reconcile the Company cash balance is 95,000 (100,000 - 47,000 + 52,000).The company's cash balance reflects a balance of 100,000 according to the general ledger on November 30th. However, the amount of cash receipts yet to be deposited into the checking account is 47,000,

While checks written by AC but not yet processed by the bank is 52,000.11. The balance in the company's cash account after the reconciliation is 95,816 (125,816 - 30,000) .The balance in the company's cash account after the reconciliation is determined by taking the total amount used to reconcile the Bank balance from the total amount used to reconcile the Company cash balance. Hence, the answer is 95,816 (125,816 - 30,000).

To know more about payments visit :

https://brainly.com/question/15136793

#SPJ11

Angela estimates that her investment strategy will pay her 8.00%, compounded monthly. If she is investing $18,000 today, in how many years will she reach her goal of $28,000? a.5.3 years b.5.5 years c.5.0 years
d.6.4 years
e.5.2 years

Answers

In b) 5.5 years she will reach her goal of $28,000 with 8.00% interest rate.

To calculate the number of years it will take for Angela to reach her investment goal of $28,000, we can use the compound interest formula:

A = P[tex](1+r/n)^{nt}[/tex]

Where:

A = Future value (goal amount) = $28,000

P = Present value (initial investment) = $18,000

r = Annual interest rate = 8.00% = 0.08

n = Number of compounding periods per year = 12 (compounded monthly)

t = Number of years

Plugging in the given values into the formula, we can solve for t:

$28,000 = $18,000[tex](1+0.08/12)^{12t}[/tex]

Dividing both sides by $18,000 and simplifying:

(28,000/18,000) = [tex](1+0.08/12)^{12t}[/tex]

Approximately:

1.5556 = [tex](1.0066667)^{12t}[/tex]

Taking the logarithm of both sides:

log(1.5556) = log[tex](1.0066667)^{12t}[/tex]

Using the logarithmic identity log([tex]a^{b}[/tex]) = b*log(a):

log(1.5556) = 12*t * log(1.0066667)

Solving for t:

t = log(1.5556) / (12 * log(1.0066667))

Using a calculator, we find that t is approximately 5.5 years.

Therefore, the correct answer is b) 5.5 years.

To learn more about interest rate here:

https://brainly.com/question/29487614

#SPJ4

Coles, the Australian supermarket, used to have many brands of pasta on its supermarket shelves.
Today, it has reduced that number, selling only one or two brands of pasta on its shelves.
Coles hopes this strategy will boost sales and revenue in the pasta section.
The company is most likely applying which demand idea?
Select one:
a.
encouraging conspicuous consumption of high-quality pasta
b.
reversing customers' diminishing marginal utility for pastas
c.
better advertising of its one or two pasta products
d.
using the insights from the idea of the paradox of choice

Answers

Coles is most likely applying the insights from the idea of the paradox of choice. The correct option is "Using the insights from the idea of the paradox of choice." The paradox of choice is a marketing concept that refers to the idea that more options and choices lead to greater decision-making difficulty, leading to lower sales.

Coles, the Australian supermarket, has made the strategic decision to decrease the number of brands of pasta available on its supermarket shelves and only sell one or two brands of pasta on its shelves. Coles aims to boost sales and revenue in the pasta section by implementing this strategy. It is applying the insights from the idea of the paradox of choice, as a small number of choices is more likely to result in higher sales than an extensive selection. Offering consumers fewer options makes the decision-making process more comfortable, leading to increased sales. Therefore, reducing the number of brands of pasta on its supermarket shelves is most likely to boost Coles's sales and revenue in the pasta section.

To know more about paradox of choice visit:

https://brainly.com/question/32391002

#SPJ11

mention and explain a good objective(s) for Loi Troi Group (a Vietnamese rice company) when exporting rice to EU.

Answers

The objectives of Loi Troi Group for exporting rice to the EU are quality assurance, competitive pricing, compliance with EU regulations, and building strong relationships with European distributors and importers.

The Loi Troi Group, a Vietnamese rice firm, has a few objectives when exporting rice to the EU. Here are some of the objectives and explanations for Loi Troi Group as requested in the question:

1. Quality assurance

Loi Troi Group must ensure that its rice satisfies the EU's quality standards, which are higher than those of the domestic market. The EU is particularly concerned with food safety and hygiene standards. As a result, the business must ensure that the rice it supplies to the EU is free of contaminants and pathogens that might cause health issues. Loi Troi Group must adhere to EU legislation on plant health and food safety and quality.

2. Competitive pricing

The European market is highly competitive, with low margins and high demand. As a result, Loi Troi Group must maintain a competitive price to avoid losing business to other rice suppliers. Lowering costs by optimizing supply chain management and enhancing operational efficiencies can help the company achieve this goal.

3. Compliance with EU regulations

The Loi Troi Group must abide by all EU regulations. EU phytosanitary and customs standards must be adhered to, and certifications must be obtained to ensure that the rice products are lawful and safe for human consumption. The Loi Troi Group must also ensure that its packaging and labeling are consistent with EU standards. The company must also guarantee that the rice products it sells to the EU are free of harmful chemicals or pesticides.

4. Building strong relationships with European distributors and importers

The Loi Troi Group must create strong relationships with European distributors and importers, which is critical in today's highly competitive market. They can do so by promoting their rice products through social media and by establishing a marketing campaign. The business must also ensure that there is prompt communication with distributors and importers in the EU and that goods are delivered on time.

To know more about objectives, refer to the link below:

https://brainly.com/question/29890185#

#SPJ11

Other Questions
adolescents who use e-cigarettes are not likely to begin smoking cigarettes. true or false? There are two economies. Economy A is dominated by the self-driving cars, which has the following production function: The production function of the self-driving car industry is: Y = K (min{2H, 7L}) * , where K represents capital, H represents high-skilled labor, and L represents low- skilled labor. Economy B is dominated by the agriculture industry, which has the following pro- duction function: Y = K (4H+3L) , where as before K represents capital, H represents high-skilled labor, and L repre- sents low-skilled labor. Suppose an immigration policy in each economy increased the intake of low-skilled immigrants rapidly. In the short run, how would it affect the wage of high-skilled workers in each economy? Twenty-first-century leaders face unique challenges to address critical new competencies, which include all of the following excepta) leading through change.b) defining roles.c) understanding digital technologies.d) embracing ambiguity.e) utilizing artificial intelligence. Suppose a consumer has the utility function u(z1, z2) = z1 + z2,1) If the consumer has income M and faces the prices p1 and p2 for z1 and z2, respectively, derive the demand functions for the two goods.2) What types of preferences are associated with such a utility function? 7. Which of the followings does NOT describe Universal Basin Income? a. it is cash payment at regular intervals and recipients can use the cash for any purpose. b. it is paid without a requirement to work or any qualification test. c. it would be more inflationary than Job Guarantee Program. d. it would lower wages. e. it would allow recipients to pursue what they want to do without worrying about their survival. 8. Which one of the following is an economic, but not an accounting, cost? a. the cost of inputs for production b. the wages paid to employees c. the opportunity cost d. interest paid on a loan e. taxes 9. Which of the following is most likely to be a fixed cost of a manufacturing company? a. rent b. wages paid to labor hired daily c. utility bills d. shipping costs e. expenditures on raw materials 10. What does the triple-bottom-line refer to? a. profits, profits, and profits b. social, environmental, and profit (financial) goals c. profits, sales, and depreciation d. location, marketing, production e. profits, market share and dominance. 11. Economics defines the "long run" as a time period where ... a. all inputs are variable b. all but one input are variable c. all inputs are fixed d. output is variable e. fixed costs must be paid. which of the following is a scientific justification for the statement that the evolution of easily modified flower colors that make plants attractive to animals was an important factor in the diversification of flowering plants? A gift that is specified in a will as "I leave my collection of baseball cards to my son" is a Multiple Choice O General legacy. O Specific legacy. O Demonstrative legacy. O Residual legacy. O Devise. which of these is the first step in the sound ethical decision making in business? group of answer choices define the ethical issues identify the affected parties check your gut gather the facts In 2-3 paragraphs, respond to the following. Your initial post should be substantive and be supported by course concepts. Read and respectfully reply to your classmates' posts to create dialogue and further learning. Classmate replies are to be informative, substantive and meaningful. Why is the control function vital to an organization's success? How can organizations use technology to facilitate the control function? Solve for x : x=12x-21 (correct to one decimal place ) A third-party beneficiary to a contract has a legal right to thebenefits resulting from the contract if it is the intent of the________ to benefit the third party.contracting partiesgu the blank by which water goes through the blank and blank Think of a business idea that is covid-free. How would you makesure it becomes profitable?write minimum 250 words and make sure you providereference? These plants have long and short shoots. The female reproductive parts are paired on a stalk, and the male reproductive parts are arranged in strobili. The leaves are megaphylls shaped like fans. These plants have changed very little in shape over millions of years, and fossilized leaves look like modern day leaves. Ginkgo O Angiosperms O Bryophytes Conifers O Lycopods Ferns OCycads Discuss the type of opinion and any other aspects that should be disclosed in the Audit report forthe following1. Eureka and co Ltd ,a small public company ,operates a small goldmine .As part of its last geologicalsurvey the company was advised that the amount of gold in their mine would only last another 18months at the most . The CEO has not advised shareholders of this in his annual report .The financialstatements show the company is making a profit and can pay its debts .2.The Cerrent company arranges for popular overseas entertainers to come out to Australia toperform concerts. The band UXI was booked to come to Australia to perform in concerts in majorcities across the country .UXIs written contract required the company to be paid in US $ but due tocosts involved the Cerrent company did not hedge the amounts involved .Subsequent to the bookingthe Australian dollar fell against the US dollar and so Cerrent would be facing a substantial lossrelated to the bands tour . The management of Cerrent tried to renegotiate the contract with UXIwho have been unwilling to change the conditions of the contract .Cerrent has been unable toobtain finance to cover the expected shortfall .Cerrent has cancelled the tour and expects asubstantial claim from UXI . From your audit it is clear that Cerrent does not have the income,cash orother assets to sustain such a loss .The management of CEO have adequately disclosed these issuesin their annual report.3.The Big Holiday company had just started expanding its business in late 2019 in locations in US,China,Thailand and Italy with small offices in each of these locations and its head office in Australia.These offices were starting to show a profit when COVID 19 hit .While the business has been able tocontinue it has suffered a 60% fall in revenue and has concerns also about unhelpful commentsbeing made by the Australian and US Governments . The company has adequate levels of cash tocontinue .All of the above is adequately disclosed in the financial statement There are a number of theories on motivation. 4.1 Which of these theories do you like the best? Explain your answer. (15 4.2 Consider the theories of Maslow and Herzberg. Choose one of these theories and start by stating which theory you prefer. By using practical examples, explain how a manager in a company can use the theory that you have chosen to motivate his team. (20 En una empresa preguntan a 30 de sus empleados cuanto tiempo viajan para llegar hasta el trabajo. De acuerdo al enunciado y a tus conocimientos previos, podemos deducir que la variable es: To what extent do you agree that it is not possible to solve apersistent balance of payments deficit without sacrificing otherkey macroeconomic aims? 1. The current account deficit (CAD) is expected to be at least $40 billion, by the end of 2022 , which is the result of savings gap (S On the first day of the fiscal year, a company issues a $980,000, 7%, 5-year bond that pays semiannual interest of $34,300 ($980,000 7% 1/2), receiving cash of $884,176. Required: Journalize the entry to record the issuance of the bonds. Refer to the Chart of Accounts for exact wording of account titles.