Which of the followings statements is true when comparing double decining balance depreclation to straight-ine depreciation? a. Straight-line deductions will be greater than double declining balance deductions in all years of the asset's depreciable life. b. Double declining balance deductions will be less than straight-line deductions in early years of the asset's depreciable life but greater in later years. c. Double declining balance deductions will be greater than straight-line deductions in all years of the asset's depreciable life. d. Double declining balance deductions will be greater than straight-line deductions in early years of the asset's depreciable life but less in later years.

Answers

Answer 1

Double declining balance depreciation is an accelerated depreciation method in which an asset's book value is multiplied by a fixed depreciation rate.

The process is continued until the book value of the asset reaches zero, and it is frequently utilized to depreciate assets that lose value quickly over time. Straight-line depreciation is a method of depreciation in which the same amount of depreciation is applied every year over the life of the asset. The most significant difference between double declining balance and straight-line depreciation is that the former results in a more rapid write-off of the asset's book value.The correct answer to the given question is option (b) Double declining balance deductions will be less than straight-line deductions in early years of the asset's depreciable life but greater in later years. Double declining balance deductions will be less than straight-line deductions in the early years of the asset's depreciable life but greater in later years.

TO know more about book visit:

brainly.com/question/15113495

#SPJ11


Related Questions

Explain the trade-offs between repair, renewals and
replacements, and new construction?

Answers

When it comes to the construction industry, it's essential to know the differences and trade-offs between repair, renewals, replacements, new construction, and the situations under which each is required.

Repairing a damaged structure or equipment is less expensive than replacing it, but the repair may not last as long. This will cause future repair costs and equipment replacement in the long run. Renewals, on the other hand, are usually for structures that are still considered to be of high quality. These can include things such as roofing, piping, and flooring, which all wear out over time and require regular replacement. These types of upgrades are essential in maintaining a structure and keeping it in top condition. The trade-off between cost, quality, and durability is usually between the initial cost of the material and the quality of the finished product. New ConstructionNew construction is a term used for structures that have not yet been built. It is usually the most expensive option and has the highest potential for error.

The trade-off between cost and quality is usually between the initial cost of the materials and the quality of the finished product. The materials used in the replacement process should be of high quality, and the work should be performed by experienced professionals to ensure the finished product's quality. The trade-off is between cost, quality, and durability. In conclusion, the construction industry involves many different trade-offs when it comes to repairing, renewing, replacing, or constructing new structures. It is essential to take the time to weigh the options carefully and consider factors such as cost, durability, quality, and the overall lifespan of the finished product before making any decisions.

TO know more about situations under visit:

brainly.com/question/11897087

#SPJ11

Research on the impact of the earthquake in the ETABS
program after the passage of time on the buildings. With an
example

Answers

ETABS (Extended Three-dimensional Analysis of Building Systems) is a computer-aided structural analysis software that is commonly used by engineers for structural design and analysis of buildings. One of the crucial features of ETABS is its ability to model and simulate earthquakes.

The ETABS program provides real-time simulations and enables designers to estimate the impact of earthquakes on buildings. This feature is particularly useful in seismically active regions. The impact of earthquakes on buildings varies based on the severity of the earthquake and the time elapsed since the earthquake.

After the occurrence of an earthquake, buildings are subjected to different types of forces, including lateral loads, vertical loads, and torsion forces. For instance, consider the case of the 2015 Nepal earthquake. The earthquake had a magnitude of 7.8 and caused significant damage to the buildings in the region. The ETABS program was used to analyze the impact of the earthquake on different types of buildings in the region.

The ETABS program is a powerful tool that enables designers to analyze the impact of earthquakes on buildings. The software provides an accurate simulation of the forces acting on the buildings and enables designers to identify areas that are vulnerable to damage.

Therefore, it is essential to use the ETABS program to analyze the stability of the buildings after the earthquake.

To know more about earthquakes visit:-

https://brainly.com/question/30322293

#SPJ11

This sertence desserbes: Vacuum mold castang Stell mold casting Band cassing Lost foan casting
A. Moving to another quesson wial save this responte. (LO1) Shel molding process is done as in the following order: metal patiem is placed orer a box contaning sand maed wath thermosetting tesin sand resin mictare partialy cures and form hard shel two halves of the shel mold are aswerrbled finined casting is rotooved trom the shel AB Movirg to another quevion will itve this responie.

Answers

The given sentence describes four different types of casting processes, each with its unique way of casting metal parts.

The given sentence describes four types of casting processes; namely vacuum mold casting, steel mold casting, band casting, and lost foam casting. A brief description of each casting process is given below:

Vacuum Mold Casting:

It is a casting process in which a vacuum is used to draw the molten metal into the mold. This process is preferred for casting intricate and complex parts with high accuracy and surface finish.

Steel Mold Casting:

It is a casting process that uses a mold made up of steel. The molten metal is poured into the mold, and after solidification, the mold is removed, leaving behind the casting.

Band Casting:

It is a casting process that uses a mold made up of sand and clay. The molten metal is poured into the mold, and after solidification, the mold is broken to remove the casting.

Lost Foam Casting:

It is a casting process in which a foam pattern is used instead of a mold. The foam pattern is coated with a refractory material and heated to remove the foam. The molten metal is then poured into the cavity left behind by the foam pattern. This process is preferred for casting complex parts with high accuracy and surface finish.

Learn more about Steel:

https://brainly.com/question/30413534

#SPJ11

1. What is the net area in square inches? (round-off the final answer up to 2 decimal places) 2. What is the nominal available tensile rupture strength in kips? (round-off the final answer to the nearest whole number) 3. What is the available tensile rupture strength in kips? (round-off the final answer to the nearest whole number) 4. What is the required tensile strength in kips? (round-off the final answer to the nearest whole number) 5. What is the available tensile strength in kips? (round-off the final answer to the nearest whole number) 6. At what length in feet, this tension member would cease to satisfy the recommended slenderness limit? (round-off the final answer up to 1 decimal place) 7. What is the nominal available tensile yield strength in kips? (round-off the final answer to the nearest whole number) 8. What is the value of U for the computation of effective net area? (round-off the final answer up to 3 decimal places) 9. What is the available tensile yield strength in kips? (round-off the final answer to the nearest whole number) 10. What is the effective net area in square inches? (round-off the final answer up to 2 decimal places)

Answers

Given that, Net area = 0.70AgNominal diameter = 1-inch Nominal thickness = 0.375 inches Grade of steel = Fey = 36 Sifu = 58 saliva Load = 350 kips Dead Load = 200 kips.

The distance between the center of gravity of the tension member and the edge of the connected part shall not exceed 1-1/4 inches. Otherwise, additional reduction shall be made to the available strength of the tension member.

The diameter of a bolt hole shall be 1/16 inch greater than the nominal diameter of the bolt. To compute the effective net area (Ae), we must first compute the reduction factor for effective net area.

TO know more about diameter visit:

https://brainly.com/question/32968193

#SPJ11

S2 A new high speed automated palletizer is proposed to replace an existing obsolete unit. The
installed cost of the new unit is $3,000,000. The residual value after ten years is estimated at
$300,000. The unit would produce one million pallet loads per year for ten years. How much
cost saving per pallet is required in order to justify the project (i.e., for the present value of the
project to be positive). Use an interest rate of 20%.

Answers

The cost per unit can not be negative. It is concluded that the project cannot be justified and the savings required to justify the project can not be found using the given values.

Given that the installed cost of the new unit is $3,000,000 and the residual value after ten years is estimated at $300,000.The unit would produce one million pallet loads per year for ten years. We are supposed to find out how much cost saving per pallet is required to justify the project at an interest rate of 20%.Calculations:Savings required = PV cost of old method – PV cost of new methodPV cost of old method is 0 because there is no mention of it in the question.Now, we need to find the present value (PV) of the new method.PV = capital cost + present value of operating costPV of operating cost = annual operating cost * PVIFA20%, 10 yearsPVIFA20%, 10 years = (1 – 1/1.2¹⁰)/0.2= 3.49Cost of operating per unit = Total cost of operation / number of units= (3,000,000 – 300,000 + (1,000,000 × cost per unit))= 2,700,000 + 1(cost per unit)Now, we can rewrite our equation of PV as:PV = 3,000,000 + (1 × cost per unit × 3.49)Now we can substitute the given values to get:3,000,000 + (1 × cost per unit × 3.49) = 0Solving for cost per unit, we get:Cost per unit =  -857,874.64

Learn more about savings here :-

https://brainly.com/question/7965246

#SPJ11

3. What are the different parties involved in the construction contract? Illustrate their roles in the construction project. 4. What is a Contract Clause? Explain briefly Common Contract Clauses in construction. 5. Describe different notice clauses in construction contract.

Answers

3. Parties involved in the construction contract: The different parties involved in a construction contract are: Owner, Contractor, Subcontractor, Architect/Engineer, Material Supplier. Each party has its own role in the construction project.

4. Contract Clause: A contract clause is a provision in a contract that sets out the rights and obligations of the parties involved in the contract. Common contract clauses in construction: Indemnification clause, Change Order clause, Liquidated Damages clause, Warranty clause, Payment clause, Termination clause.

5. Notice Clauses in Construction Contract:Notice clauses in construction contracts set out the procedures that must be followed when one party needs to give notice to another party. Different types of notice clauses are: Notice to Proceed clause, Notice of Delay clause, Notice of Change clause, Notice of Termination clause. Notice clauses are important because they ensure that each party is aware of its rights and obligations under the contract and that they have sufficient time to take any necessary action. They also help to prevent disputes by ensuring that all parties are on the same page.

To know more about Material Supplier visit:

brainly.com/question/32503300

#SPJ11

A rectangular channel of width W= 8m carries a flows rate Q=3 m3/s. Considering a uniform flow depth d=4 m and a channel roughness ks=30mm. calculate the slope S of the channel. You can assume that ks is sufficiently large so that the viscous sublayer thickness can be ignored in the estimation of C.

Answers

The slope S of the channel which has a roughness of ks=30mm is 0.0001144  [m/m].

To calculate the slope S of the channel, the Manning's formula is utilized. In fluid dynamics, the Manning formula, also known as the Gauckler–Manning–Strickler formula, is used to determine the flow of water in an open channel or a pipeline of circular cross-section, under gravity flow conditions. It is a formula that provides the best results for rectangular channels and is calculated as given below:

$$Q=\frac{1}{n}A(Rh)^\frac{2}{3}S^\frac{1}{2}$$

Where,Q is the flow rate [m3/s]n is the Manning coefficient A is the cross-sectional area of the flow [m2]Rh is the hydraulic radius [m]S is the slope of the channel [m/m]d is the depth of the flow in the channel [m]For the rectangular channel:

$A=dW$

Rh = (d/2)

Therefore,

$Q=\frac{1}{n}(dW)(d/2)^\frac{2}{3}S^\frac{1}{2}$

By rearranging the above equation for S, we get:

$$S = [\frac{Qn}{Wd^{5/3}}]^{2}$$

Given:

W= 8m Q=3 m3/sd=4 mks=30mm

The conversion of ks to m is done as below:

$ks = 30 mm = 0.03 m$

Now, the Manning coefficient is calculated as follows. Manning’s equation includes the roughness coefficient, which is defined as the ratio of the height of a roughness element on a bed to the water depth. The Manning coefficient is calculated as below:

$$n = \frac{1}{ks}(\frac{d}{Rh})^{1/6}$$

By substituting the values of the known variables, we get:

n = 0.019

Substituting this value of n and other known variables in the above equation to find S, we get:

$S=[\frac{3*0.019}{8*4^{5/3}}]^{2}$S = 0.0001144  [m/m].

Therefore, the slope S of the channel is 0.0001144  [m/m].

For more such questions on slope, click on:

https://brainly.com/question/16949303

#SPJ8

Question 1
Richard and Kenneth established an engineering consulting company (named R&K Engineering & Consulting Co. Ltd.) today. It covers a wide range of structural, civil, and geotechnical engineering services in Hong Kong. The initial investment for this business is $1,000,000. The net cashflow at the end of the first year of business is forecast to be only $200,000. But it is expected that the net cashflow will increase at a rate of $10,000 per year starting from the end of Year 2 (EOY 2).
(a) Draw a cash flow diagram for the first 9 years.
(b) Based on MARR of 10% per year, what are the Present Worth (PW) AND the Annual Worth (AW) of ALL the cashflows for the first 9 years? Round off your final answer to the NEAREST integer. (c) If the business is sold for $2,000,000 at the end of Year 9 (EOY 9), can we say this business have achieved an internal rate of return (IRR) greater than 25% per year? Why? (d) (i) If Richard secretly partners with ABC Engineering Company to bid a project which R&K Engineering & Consulting Co. Ltd. is also bidding. Identify the type of ethical issues in this situation.
(ii) Suggest ONE preventive measure for the situation.

Answers

(a) Cash flow diagram for the first 9 years. (b) Calculation of Present Worth (PW) and Annual Worth (AW) using MARR = 10% per year. Illustration of the table of net cash flows for the first 9 years:

Illustration of PW Calculation: Illustration of AW Calculation: Thus, the Present Worth (PW) of all cash flows for the first 9 years is $594,902 and the Annual Worth (AW) is $97,023. (c) Calculation of Internal Rate of Return (IRR):Thus, the Internal Rate of Return (IRR) of the business is 18.08% per year which is less than 25% per year.

So, we can't say this business has achieved an internal rate of return (IRR) greater than 25% per year. (d) (i) Type of ethical issues: Conflict of Interest(ii) Preventive measure: ABC Engineering Company should not bid the project which R&K Engineering & Consulting Co. Ltd. is also bidding and Richard should not share the confidential information of R&K .

To know more about Calculation visit:

https://brainly.com/question/30781060

#SPJ11

What is the MINIMUM vertical reinforcing steel requirement for a 8" thick masonry foundation wall that is 7' 6" high supporting 6' 6" of unbalanced backfill with a lateral load of 60 psf?
1. #7 at 48" o.c.
2. #6 at 48" o.c.
3. #5 at 48" o.c.
4. #4 at 48" o.c.

Answers

The vertical reinforcing steel requirement for an 8" thick masonry foundation wall that is 7'6" high, supporting 6'6" of unbalanced backfill with a lateral load of 60 psf is #5 at 48" o.c. The correct option is 3.

The minimum vertical reinforcing steel requirement for a foundation wall is determined by the height of the wall, the thickness of the wall, the load on the wall, and the unbalanced backfill. The minimum size and spacing of vertical reinforcing bars in a masonry wall are specified in ACI 530-11/ASCE 5-11/TMS 402-11. The vertical reinforcing steel requirement for a masonry foundation wall is determined by the formula:

A = (0.0025hd) / s where A is the area of vertical reinforcement ([tex]in^{2} /ft[/tex]), h is the height of the wall (ft), d is the effective thickness of the wall (ft), and s is the spacing of the bars (in).

The minimum area of vertical reinforcement should not be less than 0.0025 times the product of the height and effective thickness of the wall. The minimum spacing of vertical bars is 48 inches or the thickness of the wall, whichever is less.

For an 8" thick wall with a height of 7'6" and a lateral load of 60 psf, the minimum area of vertical reinforcement is:

0.0025 × 7.5 × 0.67 = 0.0126 ([tex]in^{2} /ft[/tex]).

The minimum size of the vertical bar is #5 (0.162 in2).

Therefore, the minimum number of bars required is:

0.0126 / 0.162 = 0.0777, which is rounded up to 0.08.

Thus, the minimum spacing of vertical bars is 12 / 0.08 = 48 inches. Therefore, the minimum vertical reinforcing steel requirement is #5 at 48 inches o.c., which is option 3.

To learn more about reinforcing steel, visit:

https://brainly.com/question/6875933

#SPJ11

A manufacturing plant produces robotic arms for a surgical robotics company through the following three-stage process:

Stage 1: Receiving. The plant receives raw materials from its suppliers by truck. The plant can receive up to 10 tons (we will use metric tons, so 1 ton = 1000 kg) of raw materials per day. The plant also has enough storage space for exactly 10 tons of these raw materials.

Stage 2: Metal molding and Electronics. The plant uses the raw materials to produce two intermediate components of the arms, the metal molding, and the internal electronics. Separate machines are used to produce metal molding and electronics, and they can all be run simultaneously. There are two machines to convert raw materials into metal molding, and each can convert up to 2 tons of raw materials into 2 tons of metal molding each day. There is one machine that converts raw materials into electronics and it can convert 4 tons of raw materials into 4 tons of electronics units each day. Completed metal moldings and electronics are then stored until Stage 3. For simplicity, we assume that all raw materials can be converted into either metal molding or electronics. Each metal molding weighs 2 kg and each unit of electronics weighs 1 kg.

Stage 3: Assembly. Metal moldings and internal electronics are assembled into robotic arms. There are 50 factory workers who can each assemble 10 arms each hour and work 8 hours each day. Each arm requires 2 metal moldings and 1 unit of electronics. After assembly, the arms are stored and prepared for shipping.

Q: For the system described above, what is the system’s capacity? Where are the bottlenecks?

Answers

The system's capacity is determined by the bottleneck, which is the stage with the lowest throughput.

In this case, the bottlenecks in the manufacturing plant's process for producing robotic arms are the machines for metal molding and electronics production. The capacity of these machines limits the overall capacity of the system.

The system's capacity is limited by the stage with the lowest throughput. In this case, the bottleneck is the metal molding and electronics production stage. The metal molding machines can convert up to 4 tons of raw materials into metal molding per day (2 tons each from two machines), while the electronics machine can convert 4 tons of raw materials into electronics units per day. This means that the metal molding and electronics stage has a combined capacity of 4 tons each per day.

Since each arm requires 2 metal moldings and 1 unit of electronics, the maximum number of arms that can be assembled is limited by the availability of these components. With a daily capacity of 4 tons each for metal molding and electronics, the bottleneck restricts the number of arms that can be produced. The assembly stage, which has 50 workers capable of assembling 10 arms each hour, is not the bottleneck in this case.

Therefore, the system's capacity is determined by the metal molding and electronics production stage. To increase the overall capacity of the system, the plant would need to address the bottleneck by increasing the capacity of the metal molding and electronics machines, either by adding more machines or optimizing their efficiency.

Learn more about electronics here:

https://brainly.com/question/13846898

#SPJ11

1. A 1220 mm-diameter ISI pan, with a depth of 255 mm, was fully filled and was used to simulate the evaporation rate of a reservoir with a surface area of 230 hectares. After 24 hours, the depth of the water dropped 7 mm. What is the daily evaporation of the reservoir and the water evaporated from the reservoir for a month (1 month = 30 days).

Answers

Diameter of ISI pan = 1220 mm, Depth of ISI pan = 255 mm, The water depth in ISI pan reduces by 7 mm after 24 hours and the surface area of reservoir = 230

The volume of water in the ISI pan is V = πr²hwhere r = radius of ISI pan = 1220/2 = 610 mm h = depth of ISI pan = 255 mm Volume of water in ISI pan,[tex]V = π(610)²(255) = 3.83 × 10^8 mm³[/tex]

So, surface area of reservoir = 230 hectares = 230 x 10000 m² = 2.3 x 10^6 m²Depth of water reduced in 24 hours in reservoir can be found using, Volume of water reduced in 24 hours = Surface area of water x Depth of water reduced

Depth of water reduced = Volume of water reduced / Surface area of water

[tex](V - x) / 2.3 x 10^6 m²[/tex]And [tex]x = 7 x 1220 x 1220 mm³/24 hrs = 2.38 x 10^6 mm³/day[/tex]

So, Depth of water reduced = 0.022 m/day

Water evaporated from the reservoir in one day  

[tex]2.3 x 10^6 m² × 0.022 m/day = 50600 m³/day[/tex]

Water evaporated from the reservoir in 30 days = [tex]50600 × 30 = 1,518,000 m³[/tex]

Thus, the daily evaporation of the reservoir is 50600 m³/day and the water evaporated from the reservoir for a month (30 days) is 1,518,000 m³.

To know more about evaporated visit:-

https://brainly.com/question/28319650

#SPJ11

Design a horizontal reversed circular curve by any Methods of your choice Assume your own values (given that it is different from your other designs) to start your own actual design. Take note that your design should be done as presentable as possible following the agreed format and in long sized bond paper. Use BLACK ballpen for all the calculations and tabulations. You are only allowed to use multi-color pens on the sketch part of the design. Submit your designs in PDF with filename Reversed Curve Surname Prepare answer

Answers

To design a horizontal reversed circular curve, we must follow certain steps to obtain accurate and precise results, and the procedure will involve the following steps:

Step 1: Data collection The first step in designing a horizontal reversed circular curve is data collection. This involves collecting the field measurements needed to determine the layout of the curve. Some of the measurements include the length of the curve, the radius of curvature, and the deflection angles.

Step 2: Computation The second step is to carry out the necessary computations, which include the determination of the deflection angles, radius of curvature, length of curve, and chord lengths.

Step 3: Layout The third step is to lay out the design of the horizontal reversed circular curve. This involves marking the start and end points of the curve, as well as the points where the deflection angles are measured.

Step 4: Sketch The final step is to sketch the design of the horizontal reversed circular curve. This includes drawing the chord line and the curve, as well as the tangent lines to the curve at the start and end points. The above process will help you to create an accurate and efficient curve that suits your needs.

To make the design more presentable, you can include the following information: a title page with the title of the design, your name, the date of submission, a table of contents, a list of figures and tables,The design should be presented on a long-sized bond paper using black ballpoint pens. Multi-color pens can be used on the sketch part of the design to make it more visually appealing.

To know more about circular curve visit:-

https://brainly.com/question/29885830

#SPJ11

f) If the saturation headway at a given signalized approach is observed to be 2.3 sec/vehicle, the capacity of a 3-lane approach with a cycle length of 90 sec. and a 0.60 green ratio (effective green to cycle length) is 939 vph. False True
g) If the demand at a given signalized approach is 1500 vph and the degree of saturation is 1.19 then the capacity of the same approach is 1260 vph True False
h) A mall shoppers-only parking lot is being designed. Assume a shopper will on average spend 3 hours to complete their shopping needs. It is expected that on average, 18000
shoppers will visit the mall during its operation hours. The estimated parking demand in space vehicle-hours is 6000.
False True
i) Based on the Signalized Intersection Analysis results (shown in the next page), the LOS for the westbound lane group is C
False True
j) Based on the Signalized Intersection Analysis results (shown in the next page), there would be two critical flow ratios for the Eastbound approach False True
k) Based on the Signalized Intersection Analysis results (shown in the next page), if the volume (demand) in the westbound approach is 980 vph then the volume to capacity ratio (v/c) for the same (westbound) approach is 0.956
True False

Answers

f) False The capacity of a 3-lane approach with a cycle length of 90 sec and a 0.60 green ratio (effective green to cycle length) capacity of approach = (number of lanes) * (saturation flow per lane) * (effective green time)/cycle length= 3 * 1565.217 * 0.60/ 90 =  705.391 vphThus,

g) True Capacity (C) = (saturation flow per lane) * (number of lanes) * (degree of saturation) Therefore,C = 2,3 * 1.19 * 1,500 = 3,448.5 vphGiven the demand of 1500 vph and the degree of saturation of 1.19, the capacity is 3448.5 vph

h) False Parking demand in space vehicle-hours = (total number of parking spaces) * (time for the vehicle to stay parked) * (average number of arrivals in an hour)Parking demand in space vehicle-hours = (18,000 shoppers / day) * (3 hours per shopper) * (1 car per shopper)Parking demand in space vehicle-hours = 54,000 vehicle-hours/day =/= 6000 vehicle-hours The statement is false because the parking demand in space vehicle-hours is not 6000, but 54,000 vehicle-hours/day.

i) True The Westbound lane group has a volume of 1398 vph and a capacity of 1521.08 vph, resulting in a V/C ratio of 0.918, which corresponds to level of service C. Therefore, the statement is true.

j) True Based on the Signalized Intersection Analysis results, there are two critical flow ratios for the Eastbound approach. So, the statement is true.

k) True Given the demand of 980 vph and capacity of 1024.59 vph, the V/C ratio for the westbound approach can be calculated as follows: V/C = (volume) / (capacity) = 980/ 1024.59 = 0.956Therefore, the statement is True as the calculated V/C ratio for the westbound approach is 0.956.

To know more about effective green time visit:-

https://brainly.com/question/14531023

#SPJ11

4. According to their size; boulder, pebble, clay, cobble, sand can be arranged as a) Boulder Clay Sand>Pebble Cobble b) Boulder Sand>Clay>Pebble>Cobble c) Boulder Sand>Cobble>Pebble>Clay d) Boulder>Cobble>Pebble >Sand>Clay
e) Boulder>Cobble>Peblile>Clay>Sand
f) Boulder>Pebble>Cobble >Clay>Sand

Answers

The option that correctly arranges the sediments according to their size is Boulder>Cobble>Pebble>Sand>Clay. Sediments are small pieces of rocks that are eroded by wind or water.

According to their size, boulder, pebble, clay, cobble, and sand can be arranged as follows:

Boulder>Cobble>Pebble>Sand>Clay

A boulder is the largest sediment and can be as large as a small house.

A cobble is a rock that is between 2.5 and 10 inches in size.

A pebble is any rock that is between 0.08 and 2.5 inches in size. Sand has a diameter of between 0.06 and 2mm and is formed by the weathering of rocks.

Clay is the smallest sediment and has a diameter of less than 0.002mm. It is formed from the weathering of rocks and the decomposition of plant and animal matter.

To know more about sediments visit:-

https://brainly.com/question/14306913

#SPJ11

List down five risks in in your specialization. Identify the consequence of the risk and how to deal with this risk. Also show the unethical side of dealing with such risk.

Answers

As a question-answering bot, I do not have a specialization. However, I can provide a general answer to your question. Listed below are five risks that can occur in various specializations, along with their consequences and ways to deal with them:

1. Cybersecurity Risk: Cybersecurity risk occurs when cybercriminals gain unauthorized access to data and systems and steal sensitive information. The consequence of this risk is data theft, financial losses, and reputation damage.2. Supply Chain Risk: Supply chain risk occurs when suppliers fail to deliver products or services on time or provide substandard quality. The consequence of this risk is lost revenue, increased costs, and reputational damage.3. Financial Risk:  The consequence of this risk is reduced  The unethical side of this risk is exploiting employees, like not paying minimum wages, or tolerating workplace harassment and discrimination. occurs when the company's financial performance is affected by factors like interest rates, currency fluctuations, or credit defaults.

4. Legal Risk: Legal risk occurs when the company is exposed to legal actions like lawsuits, regulatory fines, or intellectual property infringement.5. Human Resource Risk: Human resource risk occurs when there is a shortage of skilled labor, high employee turnover, or workplace accidents

To know more about consequences  visit:

brainly.com/question/31038319

#SPJ11

You are the designer of a new sports arena covered by a concrete dome. What roofing material will you specify? a. Sprayed-on Roofing b. Metal Roofing c. Built-up roofing O d. Asphalt Shingles

Answers

As the designer of a new sports arena covered by a concrete dome, the roofing material specified will play a significant role in determining the effectiveness of the structure.  

The ideal roofing material for a sports arena covered by a concrete dome is sprayed-on roofing. This roofing material is perfect for the dome because of its insulating properties, lightweight, and versatility.  

It is also easy to apply and can be customized to meet specific needs. Additionally, sprayed-on roofing is resistant to UV light, which makes it perfect for sports arenas since it will not degrade easily due to sunlight exposure.  

Metal roofing is durable, lightweight, and long-lasting. It can be designed to provide a seamless surface that is aesthetically pleasing. Metal roofing is also fire-resistant, which makes it a safe option for sports arenas.

To know more about material visit:

https://brainly.com/question/30503992

#SPJ11

A column 300 x 300 mm supports a dead load of 948 kN and a live load of 744 kN. The allowable soil bearing pressure is 262 kPa. The base of the footing is 1.7 m below the grade. Assume weight of concrete is 23.4 kN/m³ and that of soil is 16.9 kN/m³. Total depth of footing is 579 mm and has an effective depth of 461 mm. Determine the dimension of the square footing in meters "m". Tip: avoid rounding off the values during the solution, use shift store function of calculators to get the correct answer in 3 decimal places. Note: Input the exact value/dimension in 3 decimal places.

Answers

The required answer is 1.282 m. Given dead load = 948 kN and live load = 744 kN P = Dead load + Live loadP = 948 kN + 744 kN = 1692 kNTotal load on footing = P

(1)The width of the column = 300 mm = 0.3 mThe depth of the footing = 579 mm Effective depth of the footing = 461 mm Therefore, the depth of soil below footing = 579 mm - 461 mm = 118 mm = 0.118 mThe load intensity on the soil under the footing = P/AWhere A is the area of the footing. The maximum allowable bearing pressure, qall is given by:qall = 262 kPa ...

Now, the weight of concrete, wc = 23.4 kN/m³The weight of soil, ws = 16.9 kN/m³Area of the footing = [width of column + 2 × (effective depth of the footing)] × [width of column + 2 × (effective depth of the footing)]

[tex]A = [0.3 + 2 × 0.461] × [0.3 + 2 × 0.461] = 1.28347 m²[/tex]

Therefore, the allowable load, Pallowable = qall × A = 262 × 1.28347 = 336.064 kN

[tex]M = P × a[/tex]Where a is the lever arm =[tex]{(P x b)/2} + d[/tex] ...

[tex]M = P × a = 1692 × [{(b × 1000)/2} + 0.579][/tex]The moment capacity of the footing should be equal to or greater than the moment produced due to the applied load.A = b²So, [tex]b = √(A) = √(1.28347) = 1.1328 m[/tex]

[tex]M = 1692 × [{(1.1328 × 1000)/2} + 0.579] = 1,136,923.68 N-m[/tex]

So, the depth of footing = 1.1 m and breadth of footing,[tex]b = √(A) = √(1.28347) = 1.1328 m[/tex]

The dimension of the square footing is[tex]1.1328 m × 1.1328 m = 1.2815 m²[/tex]

Therefore, the dimension of the square footing in meters "m" is 1.282 m .

To know more about Dead load visit:-

https://brainly.com/question/13507657

#SPJ11

A channel has a flange width of 100 mm and thickness of 2.5 mm
with a web of 250 250 mm and thickness of 2.5 mm. What is the
location of the shear center from the center of the web
section.

Answers

The shear center of a structural section refers to the point about which pure shear loads can be applied without causing any twisting of the section. When a shear load is applied to a section, two kinds of stress develop: axial stress and transverse shear stress.

If these two stresses are not equal and opposite, twisting will occur, and the shear center will not be at the centroid of the section. The formula to determine the location of the shear center is as follows:

Q = (Aw2 - Bf2) / (2Aw)Q =    Distance between the shear center and the centroid of the section

Aw = Area of the webBf = Width of the flangeThe section is a channel with a flange width of 100 mm and thickness of 2.5 mm, and a web of 250 250 mm and thickness of 2.5 mm. The area of the web is 250 x 2.5 = 625 mm². The area of both flanges is 2 x (100 x 2.5) = 500 mm². Therefore, the total area of the section is 625 + 500 = 1125 mm².

The distance between the centroid of the section and the flange is half of the thickness of the web. So the distance from the centroid to the top of the web is 125 mm. The distance from the shear center to the centroid of the section (Q) can now be calculated.

To know more about center visit:

https://brainly.com/question/31935555

#SPJ11

ngineer A worked for Engineer B. On November 15, 1982 Engineer B notified Engineer A that Engineer B was going to terminate Engineer A because of lack of work. Engineer A thereupon notified clients of Engineer B that Engineer A was planning to start another engineering firm and would appreciate being considered for future work. Meanwhile, Engineer A continued to work for Engineer B for several additional months after the November termination notice. During that period, Engineer B distributed a previously printed brochure listing Engineer A as one of Engineer B's key employees, and continued to use the previously printed brochure with Engineer A's name in it well after Engineer B did in fact terminate Engineer A. 1. Was it ethical for Engineer A to notify clients of Engineer B that Engineer A was planning to start a firm and would appreciate being considered for future work while still in the employ of Engineer B? 2- Why 3- List at least one section in the code of ethics that are relevant to scenario described. (Provide both the section identifier and the full code description) 4- Was it ethical for Engineer B to distribute a brochure listing Engineer A as a key employee in view of the fact that Engineer B had given Engineer A a notice of termination? 5. Why 6- List at least one section in the code of ethics that are relevant to scenario described. (Provide both the section identifier and the full code description) 7. Was it ethical for Engineer B to distribute a brochure listing Engineer A as a key employee after Engineer A's actual termination? 8. Why 9. List at least one section in the code of ethics that are relevant to scenario described. (Provide both the section identifier and the full code description)

Answers

1. Ethical or unethical behavior of Engineer A: Engineer A had no ethical obligation to provide Engineer B's clients with notice of his future plans to start a new engineering firm.

However, if there was an agreement or other contractual obligation, he may have violated that obligation by notifying the clients.2. Reasons: Engineer A violated his ethical obligation by notifying the clients of his future plans to start a new engineering firm while still employed by Engineer

B. This action may have been a breach of trust and confidence between the employee and the employer.3. One section in the code of ethics relevant to the scenario: Code of Ethics section 2: Competency "Engineers shall undertake only work that they are competent to perform and shall provide full disclosure of their qualifications and experience when offering their services to the public or prospective employers.

To know more about unethical visit:

https://brainly.com/question/9740334

#SPJ11

Ranging from making environmental claims that are required by law and are therefore irrelevant (CFC-free) to puffery, or exaggerating environmental claims, to fraud, which of the following involves misleading a consumer into thinking that a product or service is more environmentally friendly than it really is? a. Genetic modification The triple bottom line approach c. Sustainability d. Green marketing e. Greenwashing Which of the following are outcomes of a firm "going green"? (Select three) a. Firms can focus more on their own efforts as a distinct unit rather than on the entire supply chain. h Firms can differentiate their products from competitors'. chevenue is increased through better access to certain markets, differentiation of products, and the sale of pollution-control technology. d. Goodwill from stakeholders is increased and money is saved from being more efficient and less wasteful. e. Costs associated with improving risk management and stakeholder relationships are increased.

Answers

Greenwashing involves misleading a consumer into thinking that a product or service is more environmentally friendly than it really is. Hence, the correct option is e.

Greenwashing. Green marketingGreen marketing refers to the practice of promoting products or services based on their environmental benefits or sustainability. Companies may highlight eco-friendly features such as reduced packaging, use of recycled materials, or energy-efficient production methods to appeal to environmentally conscious consumers. Green marketing can be an effective way for companies to differentiate themselves from their competitors, increase customer loyalty, and generate positive PR.Outcomes of a firm "going green" are as follows:1. Firms can differentiate their products from competitors.2. Revenue is increased through better access to certain markets, differentiation of products, and the sale of pollution-control technology.3. Goodwill from stakeholders is increased and money is saved from being more efficient and less wasteful.

Learn more about Greenwashing here :-

https://brainly.com/question/33702003

#SPJ11

give typical applications of timber in the construction industry
and factors which influence the strength of timber

Answers

Timber is one of the most common materials used in the construction industry. It is widely used in both residential and commercial construction due to its natural beauty, versatility, and renewable nature. Here are some typical applications of timber in the construction industry.

Roofing: Timber is a popular material for roofing due to its natural resistance to harsh weather conditions and fire resistance.

Framing: Timber is commonly used as a framing material in buildings due to its lightweight and easy handling properties.

Cladding: Timber cladding is popular in both residential and commercial construction due to its natural beauty and ability to blend well with the surrounding environment.

Flooring: Timber is a popular flooring material in buildings due to its natural beauty and durability.
Condition: The condition of the timber is another factor that affects its strength. If the timber is damaged or has knots, it will be weaker than undamaged timber.

To know more about construction visit:

https://brainly.com/question/791518

#SPJ11

Use the Fiji EIA legislation (the EMA, and the EIA Process Regulations) to answer the questions below. Make sure to include in brackets which part of the legislation (Act/Regulation, section number), you have derived the answer from.
• Once the project proposal has been submitted by the proponent, within how many days should the TOR be finalized?
Whose responsibility is it to prepare the TOR? Is the proponent ever allowed to prepare the TOR themselves?
Does the legislation provide any form/template/suggested layout for the TOR? If so - what section of the legislation is it in?
• Is any kind of public participation required during the scoping stage and preparation of the TOR? If so what kind of public participation?

Answers

According to the Fiji EIA legislation, after the project proposal has been submitted by the proponent, within thirty days the TOR (terms of reference) should be finalized [tex](EIA Process Regulations 2007, Reg. 10(2))[/tex].

The responsibility of preparing the TOR belongs to the Department of Environment (DoE) (EIA Process Regulations 2007, Reg. 10(1)). However, if the project is small or has little environmental impact, the proponent may prepare the TOR after consulting the DoE [tex](EIA Process Regulations 2007, Reg. 10(4))[/tex].

The Fiji EIA legislation provides a suggested format for the TOR, which includes the need for the project, alternative options to the proposed project, description of the proposed project, baseline information, potential impact and mitigation measures, project schedule, and monitoring[tex](EIA Process Regulations 2007, Sched. 3[/tex]).Public participation is a requirement during the scoping stage and preparation of the TOR, and it is recommended that the public is engaged as early as possible in the project development process [tex](EMA, Sec. 6)[/tex].

The legislation provides for public consultation during the scoping stage through consultation with relevant stakeholders to ensure that all concerns and issues related to the project are taken into account in the EIA process [tex](EMA, Sec. 14)[/tex].

To know more about legislation visit:-

https://brainly.com/question/15522014

#SPJ11

Draw the Momentum and shear force MNT diagram of the frame system by solving the frame in the figure whose all elements have constant E value by angle method. n=77

Answers

The bending moment and shear force MNT diagrams are as follows:

Solved by angle method, the frame in the figure whose all elements have constant E value gives the following shear force and bending moment diagrams.

The frame shown in the figure is solved by the angle method to obtain the shear force (SF) and bending moment (BM) diagram. To obtain the shear force and bending moment diagrams, you must first find the support reactions. The following formulae are used to find the support reactions:

ΣFX = 0, ΣFY = 0 and ΣMA = 0.

The degree of statical indeterminacy (n) of the frame is 3, and the number of joints is 4.

As a result, the degree of kinematical indeterminacy (d) is equal to d = 3 - 4 + r, where r is the number of support reactions. r is equal to 3 in this situation.

Therefore, d = 2. As a result, two equations are required to solve for the unknown support reactions. These two equations can be obtained by taking moments around two of the three supports or by using any other appropriate method. The following steps should be taken to find the shear force (SF) and bending moment (BM) diagrams:

Step 1: Draw the free-body diagram of the frame and choose a suitable origin for calculating moments. The resulting free-body diagram is shown below.

Step 2: To calculate the reaction forces at A, B and C, consider the equilibrium equations of the entire structure. ΣFX = 0, ΣFY = 0 and ΣMA = 0.

Step 3: Cut the beam at point D and calculate the shear force and bending moment in each segment. The resultant free-body diagram is shown below.

Step 4: To calculate the shear force and bending moment at point D, consider the equilibrium equations of the isolated beam. ΣF = 0 and ΣM = 0. The shear force and bending moment diagrams are shown below.

Therefore, the bending moment and shear force MNT diagrams are as follows:

Solved by angle method, the frame in the figure whose all elements have constant E value gives the following shear force and bending moment diagrams.

For more such questions on shear, click on:

https://brainly.com/question/30407832

#SPJ8

There are components/criteria to be met by construction projects in order for the project to be considered a success. Briefly discuss the conventional model vs modern model components and how both components differ from each other for the success of the new era of construction project

Answers

Construction projects are considered successful when they are completed on time, within budget, and meet the requirements of the client. The conventional model and modern model both have criteria that must be met for a construction project to be successful.

Conventional Model Components The conventional model consists of the following components:

Time: A construction project should be completed within the specified time frame.

Budget: The construction project should be completed within the budget allotted by the client.

Quality: The construction project should meet the quality requirements specified by the client. Safety: The construction project should be carried out in a safe manner. Modern Model Components The modern model consists of the following

The conventional model components and modern model components are similar, the modern model has added sustainability, innovation, communication, and collaboration as important components for the success of a new era of construction projects.

To know more about conventional model visit:-

https://brainly.com/question/14346834

#SPJ11

The wastewater sludge from an industry has 8% solids that are 65% volatile. The specific gravity of fixed matter is 2.7 and for the volatile matter is 1.1. Calculate the following: a) specific gravity of the wet sludge and b) volume of water (in m3 /kg of dry solids).

Answers

Wastewater sludge is generated from industries as a byproduct of wastewater treatment. It contains 8% solids that are 65% volatile. The specific gravity of fixed matter is 2.7 and for the volatile matter is 1.1.The specific gravity of the wet sludge is calculated as below: Specific gravity of fixed matter = 2.7Specific gravity of volatile matter = 1.1.

Total solids in sludge = 8% = 0.08 Fixed solids in sludge = (100 – Volatile solids) = (100 – 65) = 35% = 0.35Dry weight of sludge = (Total solids/100) × Wet weight of sludge = (0.08 × Wet weight of sludge) = 0.08Wet weight of sludge = Dry weight of sludge/0.08Specific gravity of wet sludge

= [(Weight of fixed solids in wet sludge × Specific gravity of fixed matter) + (Weight of volatile solids in wet sludge × Specific gravity of volatile matter)]/Weight of wet sludge = [(0.35 × Wet weight of sludge × 2.7) + (0.65 × Wet weight of sludge × 1.1)]/ Wet weight of sludge= (0.945 × Wet weight of sludge)/ Wet weight of sludge= 0.945.

Therefore, the specific gravity of the wet sludge is 0.945.Volume of water (in m3 /kg of dry solids) is calculated as below: Weight of water in sludge = (Weight of wet sludge × (100 – % of total solids))/100Dry weight of sludge = (Weight of wet sludge × % of total solids)/100.

To know more about volatile visit:

https://brainly.com/question/30905318

#SPJ11

1)
in arbitration what is meant by a stay in proceedings
2) why an arbitration agreement deemed a contract

Answers

In arbitration, a stay in proceedings means to halt the legal process, thereby suspending the case until a particular matter is resolved. The arbitrator issues an order for a stay in proceedings. a stay in proceedings is done when one party, the defendant, has filed a motion to stay the case proceedings.

The arbitrator may or may not grant a stay in proceedings depending on the factors considered in the motion, including but not limited to the complexity of the case, the timing of the motion, and the interests of justice.

An arbitration agreement is deemed a contract for several reasons. it is an agreement between two parties to resolve their dispute through arbitration rather than in court. the parties must have the legal capacity to enter into an agreement, and their consent must be voluntary.  

the arbitration agreement must conform to the legal requirements of the jurisdiction where it is to be enforced. Sixth, the agreement must be fair and reasonable to both parties, and must not contravene public policy.  

Therefore, it is deemed a contract because it satisfies the legal requirements of a valid contract and creates a legally binding obligation between the parties.

To know more about arbitration visit:-

https://brainly.com/question/24847253

#SPJ11

It is known that the principal stresses acting in the vertical plane are 50 kPa and 100 kPa in the horizontal plane. The magnitude of the normal and shear stresses acting on a plane with a slope of 45 degrees is...
A. 50 kPa and 50 kPa
B. 75 kPa and 25 kPa
C. 75 kPa and 50 kPa
D. 50 kPa and 25 kPa

Answers

The normal and shear stresses acting on a plane with a slope of 45 degrees, given that the principal stresses acting in the vertical plane are 50 kPa and 100 kPa in the horizontal plane can be calculated as follows: Normal and shear stresses acting on a plane with a slope of 45 degrees can be calculated as:

Normal stress = 1/2[(σ1−σ2)+ (σ1+σ2) cos2θ]Shear stress = 1/2[(σ1−σ2) sin2θ]Whereσ1 and σ2 are the principal stresses acting in the vertical and horizontal planesθ is the angle of inclination of the plane The inclination angle of the plane, θ = 45° σ1 = 100 kPaσ2 = 50 kPa.

Normal stress = 1/2[(σ1−σ2)+ (σ1+σ2) cos2θ]=1/2[(100−50)+ (100+50) cos2×45°]= 75 kPa Shear stress = 1/2[(σ1−σ2) sin2θ]=1/2[(100−50) sin2×45°]= 25 kPa Therefore, the magnitude of the normal and shear stresses acting on a plane with a slope of 45 degrees is 75 kPa and 25 kPa, respectively. Hence, option (B) is the correct choice.

To know more about horizontal visit:

https://brainly.com/question/29019854

#SPJ11

AUTOCAD. MAKE A 25 sq floor plan and provide the following:
Residential Electrical
Systems Design
1.Lighting layout
2.Power layout
3.Schedule of loads
4.Riser diagram
5.Branch circuit computations
6.Service entrance computations

Answers

AutoCAD is a computer-aided design (CAD) software that enables architects, engineers, and designers to create, draft, and analyze 2D and 3D models with precision. It’s widely used in the architecture, construction, and manufacturing industries to help with drafting and modeling processes.

Step 1: Create a new floor plan drawing :-Start by opening AutoCAD and creating a new 25 sq floor plan. Choose the units of measurement that you want to work with and set up the drawing limits. Draw the walls, doors, windows, and other features of the floor plan as needed.

Step 2: Lighting layout :-To create a lighting layout, first determine the location and type of lighting fixtures you want to install in the residential area. After that, add the light fixtures to your floor plan by inserting blocks that represent the fixtures. Use layers to organize the lighting layout and apply the appropriate color to the lights.

Step 3: Power layout :-To create a power layout, determine the location of electrical outlets, switches, and appliances. Add electrical symbols to the floor plan, and create layers to organize them based on their purpose. After that, create circuits and add wires between electrical outlets, switches, and appliances.

Service entrance size = Total power requirements / Voltage
Creating a residential electrical system using AutoCAD requires a lot of planning, calculations, and attention to detail. By following the steps above, you can create an accurate and effective electrical system that meets the needs of the building's occupants.

To know more about computer-aided design visit:-

https://brainly.com/question/31036888

#SPJ11

What are some of the considerations that planners must examine in order to determine which approach is most appropriate for the given infrastructure problem and what are some of the trade-offs planners had to make in your community?

Answers

As infrastructure problems are often complex and multi-faceted, planners must take into consideration several factors when determining which approach is the most appropriate to solve a problem.

:1. Feasibility - Before undertaking an infrastructure project, planners must determine whether it is possible to execute it given the available resources, technology, and personnel.2. Environmental impacts - Planners must examine the potential environmental impacts of a project and ensure that any negative effects are mitigated or offset.3. Cost-effectiveness - Planners must determine whether the costs of a project are reasonable and justifiable in light of the benefits that it will provide.4. Social impacts - Planners must consider the social impacts of a project, including its effects on local communities, businesses, and other stakeholders.5. Legal issues - Planners must ensure that any proposed project complies with relevant laws and regulations.


To know more about  consideration visit:

brainly.com/question/30759148

#SPJ11

The environment is always experiencing impacts due to developments, pollutions and contaminations. Based on your understanding of preparing an EIA and TIA reports, explain the steps and processes that should be conducted during the acquisition of the
EIA and TIA data.

Answers

Environmental Impact Assessment (EIA) and Traffic Impact Assessment (TIA) are the two most common forms of impact assessments used in development projects. These reports are important as they assess the potential environmental and traffic impacts of proposed development projects and offer measures to mitigate the potential impacts.

The process of conducting an EIA involves several stages, including screening, scoping, analysis of alternatives, identification of environmental and socio-economic impacts, assessment of significance, development of mitigation measures, and finally, review and approval. The following are the steps to be conducted in EIA and TIA reports:Step 1: Screen the proposed development project to identify if an EIA or TIA is needed.  Step 2: Scoping – Identify key issues that need to be addressed in the impact assessment .Step 3: Identify alternatives to the proposed project, including the no-action alternative. Step 4: Identify the potential environmental and socio-economic impacts of the proposed project and assess their significance. Step 5: Develop mitigation measures to reduce or avoid the potential impacts of the project. Step 6: Prepare the EIA or TIA report and submit it for review and approval. Step 7: Monitor and implement the mitigation measures and periodically assess their effectiveness.

The process of conducting an EIA and TIA requires the collection of data and information, which should be done through surveys, field studies, stakeholder consultations, and other relevant sources. The data collected should be analyzed and evaluated to identify potential impacts and develop appropriate mitigation measures. In conclusion, the acquisition of EIA and TIA data is an essential part of the impact assessment process, and it is crucial to follow the proper steps to ensure that potential environmental and traffic impacts are properly addressed.

To know more about   development projects visit:

brainly.com/question/19464435

#SPJ11

Other Questions
1. An analyst has determined that when the price of product X increases from $10 to $12, the quantity demanded declines from 30 units to 28 units. The price elasticity of demand for product X is closest to: (Show your solution) - 5 points 2. Discuss at least three factors that affect demand. (6 points) 0) Class comments Add a class comment Which of the following statements regarding a principal's liability for the torts of its agents is TRUE? Select one: A. A principal is only responsible for the torts of it agents if it specifically authorized the activity by the agent that constituted the tort. B. A principal is never responsible for the torts of its agents. C. A principal is responsible for the torts of the agent who is acting in the actual or apparent scope of the agent's duties or authority. D. A principal is always responsible for the torts of its agents. E. A principal is only responsible for torts committed by agents who are also employees of the principal. I need to write an "Affidavit of Support" for my daughter to prove that she and her husband are a married couple. I have to write an affidavit of support because they were not married in the church, and thus, the church did not issue a marriage certificate. However, they were married in our traditional way, and it's arranged marriage. My daughter and her husband are students and live in different states, and we have known each other for more than one year. For that purpose, I need to write a letter to support that my niece and her husband are a genuine couple. Please help me. You can add anything you want, and please write for me at least 200 words or more. Thanks a lot for your help. The world price of a refrigerator is $500. The value of imported components used to make the refrigerator is $387. The tariff on imported refrigerators is $74. % (round to two decimal What is the nomi .Which of the following is a true statement about goals?o They must be updated weekly.o They should focus on several areas of your life.o They are the smaller, more defined steps you take to meet objectives.o They should be seemingly unrealistic in order tochallenge yourself. 3. Last month the company sold 1.55 million Deluxe boxes at an average price of $28 per box. This month the company raised the price to $29 and sold 1.35 million boxes. The variable cost per unit is $20 and the fixed costs are $3 million per month. Assume these costs don't change in the short term.What is the price elasticity of demand?Can the demand be characterized as price elastic, price inelastic, or neither?By how much did revenues increase or decrease as a result of the change in price?By how much did profits increase or decline?QuantityPriceOriginalNew% change% changeElasticity of DemandElasticity:By how much did revenues increase or decrease as a result of the change in price?By how much did profits increase or decline?Deluxe boxes sold per month (millions)PriceRevenue (millions)Variable Cost per Deluxe boxVariable Cost (millions)Fixed cost per monthTotal Cost (Millions)Monthly Profit (millions) Should more tasks be automated? Why or why not? Explain your answer.Can the problem of automation reducing cognitive skills be solved? Explain your answer. what is inequalities Under its executive share option plan. None Berhad granted options on 1 January 2020, that permit 20 senior executives to purchase 50,000 each of the company's ordinary shares within the next six years, but not before December 31, 2023 (the vesting date). The exercise price is the market price of the shares on the grant date, RM12 per share. The fair value of the options, estimated by an appropriate option pricing model, is RM3 per option. No forfeitures are anticipated. i) Ignoring taxes, what is the total compensation cost pertaining to the share options? ii)Ignoring taxes, what is the effect on earnings in the year after the options are granted to executives? (iii)Suppose that unexpected turnover during 2021 caused the forfeiture of 15% of the share options. Compute the amount of compensation expense for 2021. (iv) the market price is $20 per share. Prepare the appropriate journal entry to record the exercise of 80% of options on September 1, 2024, when the market price is $20 pershare (v)Suppose that on 31 December 2025, the remaining 20% of options expire without being exercised. Ignoring taxes, what journal entry will None Berhad record? 10marks Urgent The table below shows the year and the number of people unemployed in a particular city for several years. Determine whether the trend appears linear. If so, and assuming the trend continues, in what year will the number of unemployed first reach 43? (Round your answer down to the nearest year. If the trend does not appear linear, enter NOT LINEAR.) Year 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 Number Unemployed 750 670 650 605 550 510 460 420 380 320 On January 1, 2021, Hirschbach Motors Company, an equipment and truck manufacturer sold equipment to McCoy Transportation Company that cost $150,000. Hirschbach Motors received as consideration a 5% interest-bearing note requiring payments of $80,000 annually for 3 years. The first note payment is to be made on December 31, 2021. The prevailing rate of interest for a note of this type on January 1, 2021, was 5% (FV of $1. PV of $1. EVA of $1. PVA of $1. EVAD of $1 and PVAD of S1) (Use appropriate factor(s) from the tables provided.). Required: 1. Prepare the journal entry for McCoy Transportation Company's purchase of the machine on January 1, 2021 2. Prepare the journal entry for the first installment payment on December 31, 2021 3. Prepare the journal entry for the second installment payment on December 31, 2022 4. Prepare the journal entry for the third installment payment on December 31, 2023. olete this question by entering your answers in the tabs below. TRUE / FALSE."Climate change may decrease eutrophication through increases inrunoff from extreme weather events, What is the logic behind these efforts to a centralized organization? Is there a compatibility between strategy and organization structure?Who is Charlie Bell? What operations at Microsoft does he run to implement the Strategy? How has he tried to reorganize these operations? (address this in the context of adaptable leadership and strategy) Support your answer by using references. 4. Suppose that the short-run labor demand curve is LD 100 10w, where w is the wage rate. Moreover, both unskilled natives and unskilled immigrants both supply their labor inelastically, i.e. the labor supply curve is Ls = Q, where is the labor force in the labor market. Assume that unskilled natives and unskilled immigrants are perfect substitutes for the firms. Initially, there is 10 natives and 0 immigrants. (a) What is the equilibrium wage rate initially?(3 marks) (b) Suppose the number of immigrants increases from zero to 10. What is the new short-run equilibrium wage rate?(3 marks) Consider the set N of positive integers to be the universal set. Sets H, T, E, and P are defined to the right. Determine whether or not the sets H' and P' are disjoint. Are H' and P' disjoint? O A. Yes, because there is at least one prime number that is greater than or equal to 100. O B. No, because there are no composite numbers less than or equal to 100. O C. No, because there is at least one composite number that is less than or equal to 100. O D. Yes, because there are no prime numbers greater than or equal to 100. H = {NEN|n> 100} T = {nEN| n 2 a. If you make only this minimum payment, how long will it take for you to repay the $1,100 balance (assuming no more charges are made)? b. If you make the minimum payment plus $10 extra each month (for a total of $29.80 ), how long will it take to repay the $1,100 balance? c. Compare the total interest paid in Part (a) with the total interest paid in Part (b). at that time. If the MARR is 10% per year, how much can the hospital afford to pay for this device? A=-1,0,1,2,4,6,7 I=-2,-1,1,2,8 QUESTION 1 The following conditions apply for water: T=55 C, vapor pressure P sat =15.8kPa and H vap = 42.91 kJ/mol. Use the Clapeyron equation to estimate the vapor pressure of the water at T 2=70 C. Show all calculations to obtain full marks! Which of the following is not considered a typical chronic adaptation to endurance training? a. Increased mitochondrial density in skeletal muscle b. Increased End Diastolic volume during exercise c. Increased VO 2max d. Increased maximum heart rate e. Increased capillary density in muscle A mortgage company quotes a lending rate of 7% APR with monthly repayments (that is, monthly compounding) or 7 41% with payments once every year. Which is the better deal for the borrower? (a) Pay once a month (b) Pay once a year (c) Both are equivalent (d) The two deals cannot be compared Answer for (5) 6. (Note: Full computations are not necessary for this problem. The mumbers are just a useful guide to think through the problem). Today is Anita's birthday and she is planning for retirement. She wishes to have an annual income of $50,000 per year for 20 years starting exactly one year from now. She receives her income once a year, and always on her birthday. She has decided that at the current interest rate (which is x% ) she should set aside $600,000 today to achieve her retirement income goal. As she is walking to the bank to deposit the funds with her banker, she learns that the interest rate has gone up above %. Which of the following statements is true? (a) Anita will need to set aside more than $600,000 because the interest rate has gone up. (b) Anita will need to set aside less than $600,000 because the interest rate has gone up. (c) Anita will need the same $600,000 because her income requirement has not changed. (d) We cannot say whether Anita needs to set aside more or less money than $600,00 because we do not know the original interest rate.